Key takeaways
- The ground-level exclusion zone protects against falling scaffolding components during assembly.
- Art. 17 OTConst imposes strict measures to protect individuals against falling objects.
- A crew member visually monitors the zone if rigid barrier cordons are incomplete.
- Occupying public land requires a prefectural or municipal order with a pedestrian diversion.
Calculation of barrier width and ground-level protection requirements
During the erection or dismantling phases of facade scaffolding, gravity means that any dropped object follows a direct downward trajectory or ricochets off the structure or facade. To guarantee the safety of construction site workers and third parties, the lower sector must be rigorously isolated. Art. 17 OTConst requires effective measures to be taken at workstations and passageways to prevent any hazard related to falling materials or equipment.
- Ground-level exclusion zone
- Temporary physical safety perimeter established at the base of the structure during assembly or dismantling, access to which is strictly prohibited to anyone outside the erection crew.
The width of the cordoned-off ground zone is calculated based on the total height of the structure and the nature of the components being handled (tubes, frames, 3-metre decks). As a general rule, for standard scaffolding up to 20 metres high, the minimum ground protection zone must extend across a width of at least 2 metres from the outer face of the scaffolding upright. If the height exceeds 20 metres, or when long components are handled manually, this width is increased to at least 3 metres to allow for the potential bounce of components.
| Height of the working zone | Minimum ground distance (from base) | Required enclosure type |
|---|---|---|
| Up to 10 metres | 1.50 metres | Linked rigid barriers or reinforced guidance |
| From 10 to 20 metres | 2.00 metres | Fixed free-standing construction site barriers |
| More than 20 metres | 3.00 metres | Opaque rigid barriers and signage |
Perimeter supervision and management of co-activity on public land
Physical cordons do not eliminate the need for suitable human supervision. During the lifting of metal components or toeboards, one of the scaffolders on the ground acts as an area spotter. This worker continuously checks that no other trade or passer-by crosses the barrier. In the event of an intrusion, an order to immediately stop manual handling or rope hoisting is given to the scaffolders working at height.
- Prior verification of the perimeterThe team leader ensures that the ground-level zone is cleared of all third-party equipment, vehicles, or obstacles before handling begins.
- Installation of physical enclosureErect rigid barriers across the required width and close off access to doors or building exits that lead directly into the working area.
- Assignment of supervisionDesignate the ground scaffolder responsible for receiving components and monitoring the safety perimeter during critical phases.
- Controlled passage authorizationIf temporary transit is unavoidable, suspend all operations at height until the area is completely cleared.
When scaffolding is erected along a roadway edge or on a municipal pavement, the exclusion zone directly encroaches on public land. In the case of a narrow street or a pavement that cannot be fully closed to traffic, strict engineering and operational measures are required. The scaffolding contractor must obtain a public domain usage permit from the municipal or cantonal technical departments before opening the construction site.
Health and safety planning must incorporate the assembly schedule to avoid peak pedestrian or school hours. When co-activity on public land is unavoidable without closing the street, using a mobile elevating work platform or a crane truck with an integrated working zone and standardised road signage replaces manual hoisting along the facade.
Dimensioning of the exclusion zone and active perimeter supervision
During the assembly and dismantling of facade scaffolding, the risk of falling materials (tubes, frames, decks, spigots, or hand tools) requires the implementation of a rigorous exclusion perimeter at ground level. Art. 17 OTConst mandates the implementation of securing and isolation measures to prevent ground personnel or co-active workers from being endangered by falling objects or structural components.
The basic physical rule dictates that any object dropped or sliding off a deck falls vertically, but undergoes unpredictable rebounds off the underlying components of the structure. For this reason, the width of the cordoned-off zone is calculated directly from the working height currently being executed. Rigid construction site fencing or barrier tape must be positioned offset from the outer plumb line of the highest scaffolding level.
| Assembly / dismantling height | Minimum barrier distance (setback) | Required physical device | Access arrangements |
|---|---|---|---|
| Up to 10 m | 2.00 m | Red/white warning tape or mobile barriers | Total prohibition, access restricted to lifting crew |
| From 10 m to 20 m | 3.00 m | Rigid construction site fencing (mesh type H = 2.00 m) | Locked or guarded access gate |
| Above 20 m | 1/10th of the height (min. 4.00 m) | Opaque rigid fencing with protective fan if co-activity exists | Enclosed zone under direct control of the team leader |
In accordance with art. 5 OTConst, the employer designates a competent person on the construction site responsible for monitoring the enforcement of safety and exercising their right to give instructions. During all vertical handling phases of structural components, a scaffolder or scaffolder's assistant remains stationed at ground level to visually monitor the integrity of the exclusion zone. This person prevents any entry by third-party workers or passers-by and communicates with the crew stationed at height using clear signals or site radios.
Interventions on public land and traffic constraint management
In urban environments or along road corridors, the ground footprint required for safety barriers often conflicts with the public domain (pavements, cycle paths, traffic lanes). When municipal or cantonal authorities refuse total closure of the street or pavement, the contracts manager and the scaffolding site manager must implement diversion arrangements or reinforced physical protections.
- Obtaining the public domain usage permitSubmit the encroachment application to the highways department or local trading police at least ten days before work begins, attaching the site setup plan with the selected barrier width.
- Implementation of pedestrian diversionsCreate a safe pedestrian route on the roadway using ballasted concrete or plastic separation barriers, guaranteeing a minimum clear width of at least 1.20 m.
- Continuous overhead protectionInstall a covered walkway bridge (impact-resistant pedestrian tunnel) at ground floor level from the start of the first bay assembly if the pavement remains open to public traffic.
- Temporary road signageInstall construction site signage compliant with local requirements and ensure high-visibility clothing is worn by all personnel operating at street level.
When delivery of scaffolding components is carried out by crane truck or articulated boom truck along a busy roadway, the operating radius of the boom and the unloading zone must be incorporated into the overall protective perimeter. A qualified traffic controller regulates traffic if the encroachment reduces the width of the roadway.
Management of perimeter drift and diversions on public land
During the base erection, anchoring, or removal phases of facade scaffolding, the cordoned-off ground zone remains the primary defence against impacts from small items, structural components, or hand tools. Construction site physics imposes an absolute rule: any component dropped by scaffolders falls along a direct path or rebounds unpredictably off ledgers and brackets. The ordinance on the safety and health protection of workers in construction work mandates compliance with this constraint by installing rigid exclusion devices to protect neighbouring workstations and traffic.
Managing this perimeter becomes more complex when the structure adjoins a public road and encroachment on the pavement or roadway is unavoidable. If obtaining a total closure of the public domain from the municipal or cantonal authority is impossible, co-activity demands reinforced organization. Standard barrier tape ('rubalise') is strictly inadequate for blocking pedestrians. A security check booth or pedestrian barrier fence complemented by continuous physical barriers must be installed.
Maintaining this exclusion zone requires active supervision by a dedicated person on the ground. This spotter remains in direct radio contact with the scaffolder at height. Their role is to prevent any pedestrian entry, manage foot traffic flows during component hoisting or lowering operations, and immediately halt handling if a road user approaches an area not covered by a Protect bridge or protective catch canopy.
Frequently asked questions
What is the minimum width of the ground exclusion zone during assembly?
The barrier width must correspond to the working height or potential rebound distances identified during construction site planning. It must cover the vertical alignment of the facade plus a safety margin proportional to the scaffolding height. In the presence of unclosed pedestrian or vehicle routes, object-arresting structures or sealed protective gantries must be installed beforehand.
Is simple barrier tape sufficient to cordon off the exclusion zone?
No. Plastic ribbon or barrier tape does not constitute an effective physical barrier against entry by third parties or site users. Cordoning must be carried out using stable, rigid barriers that clearly direct pedestrian flows away from the danger zone. The presence of a spotter on the ground is essential to physically prohibit access during the handling of heavy components.
Who must provide ground supervision during the installation of tubes and frames?
Responsibility lies with the scaffolding company, which assigns a trained person to the construction site. This ground spotter ensures barriers remain in place, makes certain no other trade enters the perimeter, and maintains permanent visual or radio contact with the erection crew on the upper level to halt hoisting if an intrusion occurs.
How should work proceed on public land if the authority refuses to close the pavement?
When complete occupation of the pavement is refused, erecting scaffolding requires the installation of a footbridge or fully enclosed protective gantry over the pedestrian area. Assembly work above this area may only start once the protective structure is fully assembled, anchored, and secured against falling small components.
Texts and standards cited
- OTConst art. 17protection against the collapse of construction elements or the fall of objects and materials