🧱 CFC 212Erector safety and co-activity on the construction siteChapter 10 of 10 in the section

Cold, rain and short days: organising the erector's workstation in winter

Working on scaffolding during the bad season directly exposes erectors to harsh weather conditions. This chapter details concrete site organisation measures to control the risks associated with cold, frozen decking and early darkness. You will learn how to equip teams, adapt working paces, secure access routes and arrange breaks in the warm according to Swiss rules.

Key takeaways

  • Art. 37 OTConst mandates appropriate protective measures when working in the cold.
  • Frost and snow on decks require systematic clearing before pedestrian access.
  • Autonomous artificial lighting secures walkways and storage areas in late afternoon.
  • Breaks in a heated room preserve erectors' manual dexterity and alertness.

Protecting erectors against cold, wind and slippery surfaces

Erecting facade scaffolding places the worker on the front line against bad weather. Perched along walls, the erector handles frozen metal components that accelerate heat loss through conduction. Wind channelled along facades amplifies wind chill, numbing fingers and reducing the precision essential for locking wedges, couplers and decks. To comply with art. 37 OTConst, the employer takes the necessary measures to protect workers during work carried out in the cold.

  • Provision of thermal personal protective equipment: waterproof handling gloves with thermal insulation that maintain tactile sensitivity, breathable technical underwear and waterproof high-visibility parkas.
  • Non-slip, insulating soles for safety footwear, avoiding a direct thermal bridge with the steel or aluminium of frames and decks.
  • Supply of thermal beanies or liners without irritating seams, compatible with mandatory hard hat use.

The organisation of ground storage also determines handling safety. Standards, decks and temporary guardrails placed directly on loose soil risk becoming frozen in. Material batches must rest on raised timber dunnage to facilitate slinging without snagging or severe thermal shock with tightening tools.

Setting up end-of-day lighting and organising breaks in the warm

In November, December and January, the early decline of natural light compromises the perception of surface relief and fixings from mid-afternoon onwards. An erector handling bulky components more than ten metres above the ground cannot rely on misleading cast shadows. According to art. 15 LTr, regular breaks must be guaranteed during the working day to allow exposed bodies to recover.

Organisational measures for shortened winter days
Workstation concernedWinter constraintPractical measure on the construction site
Access tower and laddersEarly dusk from 16:30Wide-angle LED floodlights mounted on external standards out of the walkway
Erection deckingLoss of grip and visibilityRechargeable waterproof floodlights with wide beam sweeping the active lift
Ground unloading areaLorry traffic and liftingAutonomous lighting tower aimed at the sorting area and the lorry
Physiological recoveryNumbness and hypothermiaHeated site hut or container with drying rack and hot drinks available

For costing winter installations (generators, supplementary lighting and thermal welfare shelters), refer to the detailed price schedules on /soumissions/. When extreme frost conditions or wind gusts prevent safe handling, the foreman halts lifting operations to avoid any risk of falling material or personnel.

Logistical coordination and securing workstations against frost

On construction sites exposed to winter conditions in Romandie, continuous exposure of scaffolding erectors requires rigorous technical planning starting right from the delivery of frames and brackets. Cold alters the behaviour of metallic materials, stiffens safety lanyards and turns the slightest residual moisture into black ice on aluminium standards and decks. According to art. 37 OTConst, during work carried out in high heat or in the cold, the necessary measures must be taken to protect workers. For the erector of temporary structures, this begins with the systematic mechanical clearance of circulation surfaces before any transfer of loads at height.

Winter weather constraints and operational erection measures
Weather factorDirect impact on scaffolding componentTeam corrective measureTemporary suspension threshold
Morning frost / Black iceTotal loss of grip on decks and ledger railsSpreading of non-corrosive aggregates and prior manual scrapingContinuous sheet of hard glaze ice not mechanically treatable
Bise or sustained cold windIntense wind-chill effect, wind catching framesReduced unit lifting, partial sheeting deferred until after guyingGusts rendering handling and guiding of standards unstable
Sticky snowUnforeseen overloading of bays, blocked access hatchesImmediate clearing of rungs and hatches using plastic shovelsAccumulation concealing decking edges and bearing supports
Driving rain and coldSlippery tools, loss of finger sensitivity on ratchetsAccelerated rotation of ground and decking crews, lined waterproof glovesThorough soaking reducing alertness or tightening effort

Component transport requires specific attention on the ground. Items placed on muddy ground that is re-freezing quickly become unstable or stuck to the surface. Storing on dunnage timbers and protecting with breathable tarpaulins prevents incorporating weighted or soiled parts into node joints, where freezing of a spigot can prevent the proper socketing of vertical standards.

Time management, retreat and equipment maintenance during winter

Managing exposure time at the workstation dictates overall safety. The team leader adjusts the erection pace to prevent critical operations, such as facade anchoring or cantilever bracket levelling, from being performed at the edge of daylight extinction or under advanced thermal fatigue. The requirements of the construction work ordinance regarding workstations require that personnel have equipment that preserves muscular responsiveness and dexterity.

  1. Preventive inspection of tightening toolsRatchet wrenches, lifting winches and snatch blocks must be degreased of frost-congealed residues and lubricated with low-temperature fluid oil to prevent any sudden seizing during coupler tightening.
  2. Arrangement of access routes and clearance areasInternal communication ladders between levels must remain entirely free of ice. Opening and closing spring-assisted trapdoors requires visual and mechanical verification at each team ascent.
  3. Safe retreat at the end of a shortened dayAs soon as light fades, the workstation is left in a strictly self-stable condition. All ties for the reached level must be installed and verified before leaving the construction site, without deferring ties to the next day.
  4. Drying and reconditioning of equipmentFall arrest harnesses, ropes and lanyards wetted during the day are stored in the heated room to dry away from direct heat radiation sources, thus avoiding premature hardening of textile fibres.

Coordination with site management must formalise realistic intervention windows. When facade elements or supporting slabs are trapped in snow, the scaffolder cannot be forced into erection rates incompatible with snow removal and visual inspection of base plates. Cost estimates for temporary heating or shelters form distinct items that can be analysed on the specialist platform /soumissions/.

Critical weather management and erection stoppage

On a facade scaffolding construction site, the sudden onset of black ice, violent gusts or early darkness poses an immediate hazard to the team's physical integrity. Art. 37 OTConst recalls that during work carried out in high heat or in the cold, the necessary measures must be taken to protect workers. When frost eliminates grip on work decks or wind destabilises the manual lifting of frames, continuing assembly becomes technically indefensible.

  1. Assessment and immediate securing of the bayThe team leader halts the hoisting of components. Decks already positioned must immediately be locked with their wind locks, temporary or permanent guardrails fixed, and bare standards guyed or tied to the facade to prevent wind uplift.
  2. Blocking access and retreating into the warmAccess to the current lift is physically barred at the foot of access ladders with barrier rails. The team retreats to the heated site hut to warm up, dry personal gear and reassess weather conditions with the site manager.
  3. Formal notice to site managementIn application of the Code of Obligations (CO), the contractor immediately notifies the client or their representative when bad weather prevents normal progress of the works, recording in writing the status of blocked areas and the protective measures taken.

Work on the construction site can only resume after ice films have completely melted or after the application of a de-icing agent compatible with aluminium and galvanised steel, supplemented by checking that lighting levels reach at least 50 lux on every active working plane.

Frequently asked questions

At what lighting threshold must erection be halted at the end of the day?

As soon as natural daylight declines to where wedges, pins and deck locks can no longer be clearly distinguished, work stops if no supplementary lighting is installed. According to occupational safety guidelines, a minimum level of 50 lux is required on erection platforms. If corded or mast-mounted floodlights do not cover the active bay, the team leader withdraws personnel.

Can the client refuse a stoppage caused by persistent frost?

No. The physical safety of erectors takes precedence over execution schedules. If frost makes bearing surfaces slippery and mechanical de-icing proves ineffective, continuing constitutes a serious hazard. The scaffolder records the stoppage in the site logbook and submits a formal notice of delay under the Code of Obligations (CO). Responsibility for forcing a worker onto black ice falls directly under criminal law.

What thermal requirements apply to the construction site break room?

The site canteen or hut must be properly insulated and heated to a stable ambient temperature of at least 20 °C. It must include a drying system for wet jackets and gloves, seating with backrests, as well as facilities to provide hot water and warm drinks. Breaks in the warm must allow for complete physical recovery before any new lifting outdoors.

How should snow accumulation on decks being installed be handled?

It is forbidden to erect a new bay on a lift obstructed by snow. Erectors must first clear the work decks using plastic scrapers so as not to damage the non-slip plywood or aluminium surfaces. If the snow has compacted into ice under workers' boots, access is prohibited until slippery areas have been completely eliminated with suitable fine salting.

Texts and standards cited

  • OTConst art. 37sun, extreme heat and cold: during work carried out in the sun, in extreme heat or in the cold, the necessary measures must be taken to protect workers.
  • CPbreach of the recognised rules of the building trade: whoever, in directing or executing a construction or demolition project, intentionally breaches the recognised rules of the trade and thereby knowingly endangers the life or physical integrity of people incurs a custodial sentence of up to five years or a monetary penalty; in the case of negligence, up to three years or a monetary penalty.