🧱 CFC 212Handover, periodic inspections and documentsChapter 3 of 10 in the section

Periodic inspection: how often, after which events, and by whom

This chapter details the practical organisation of periodic inspections for in-service facade scaffolding. You will learn how to define the frequency of inspection visits according to site progress, conduct targeted checks after each critical weather event, record your findings in the inspection logbook, and clearly define the respective responsibilities between the scaffolding company and the users.

Key takeaways

  • The initial handover report validates the structure only on the exact day it is made available on the construction site.
  • Regular periodic inspection confirms the integrity of ties, anchorages, and guard rails throughout the entire service period.
  • Any severe gale, severe frost, or snowfall requires an immediate review before reuse.
  • Rigorous maintenance of the inspection logbook provides written proof of compliance for the temporary structure.

Regular periodic inspection guarantees safety beyond the handover day

The formal acceptance of a facade scaffolding certifies that the structure meets contractual and standard requirements at a specific moment. As soon as the day after this handover, daily construction site operations alter the structure's environment. Successive trades, plant vibrations, load handling, and differential settlement of base packing progressively alter the joints. A structure declared flawless when the yellow warning signs were installed can lose its stability a few weeks later if its components undergo unforeseen loads.

Service and working scaffolding must undergo regular inspections to verify their fitness for purpose and ensure that mechanical strength and stability requirements remain satisfied throughout the entire period of use.

SN EN 12811

In practice in French-speaking Switzerland, the scaffolder or the competent person designated by the user company conducts a weekly visual inspection across all active bays. This routine is not limited to a glance from the base of the facade: the inspector walks the decks, checks the latching of access trapdoors, and inspects the continuity of collective protective equipment.

  • Checking the ground footing: unsplit hardwood sole plates, greased levelling base jacks, absence of settlement or scour beneath the base plates.
  • Checking the vertical geometry: plumb of the standards, presence of bracing diagonals, and tightness of the couplers.
  • Inspecting collective protective equipment: uninterrupted presence of the top rail, intermediate rail, and toe-board.
  • Examining mechanical anchorages: verification of anchor screws, wall ties in the masonry, and absence of tubes dismantled by other trades.
  • Monitoring the work area: cleanliness of the platforms, absence of overloading from brick or mortar pallets exceeding the specified load class.

Inspection after severe weather and systematic recording in the logbook

Weather actions constitute one of the major causes of scaffolding failure. Sheeting and protective debris netting significantly increase wind loading. As soon as gusts exceed critical thresholds, massive snowfalls load the upper decks, or a freeze-thaw cycle destabilises the bearing capacity of the natural ground, an exceptional inspection is mandatory before allowing personnel back onto the working platforms.

  1. Prohibit access by immediate cordoning-offTurn around or conceal the authorisation notice at the bottom of the access ladders. Affix the red notice strictly prohibiting access until the assessment has been carried out.
  2. Check wind resistance and tiesInspect the condition of windbreak netting and advertising banners. Check whether the fixing points to the structural work have experienced pull-out or shear under the effect of gusts.
  3. Examine the support of base plates and jacksCheck the packing at the base after torrential rain or a thaw. Ensure that no rainwater runoff has eroded a void beneath the timber load-spreading sole plates.
  4. Clear snow and secure the decksRemove accumulated snow overloads from the service decks and eliminate slip hazards before reopening access for workers.

An inspection only holds legal and technical value if it leaves a tamper-evident physical record. This is the fundamental purpose of the inspection logbook, kept on the construction site and held available for labour inspectors or SUVA specialists. This logbook records each visit, the current weather, observations made, and corrective actions implemented before lifting any access prohibition.

Example of a tracking sheet for the inspection logbook of service scaffolding
Date and timeReason for visitDefects notedActions taken and sign-off
12 October, 07:30Weekly periodic visitTwo toe-boards displaced on level 3, west facadeReinstated immediately, packing secured, signed by foreman
04 November, 08:00Inspection after bise wind stormNetting torn on level 5, one anchor distorted on north edgeAccess closed in bay 2, anchor replaced, netting retensioned, signed by erector
19 January, 07:00Inspection after frost and heavy snowIce build-up on access trapdoor, soft ground at baseSnow cleared, base jacks retightened, signed by site supervisor

Inspection protocols according to standard SN EN 12811 and structural inspection points

Initial acceptance confirms compliance of the structure at the exact moment of erection. However, daily use by the various trades, vibrations induced by material handling, and weather actions modify the static equilibrium of the structure. Applying the technical principles of standard SN EN 12811 requires a methodical check of the condition of load-bearing components during each scheduled inspection.

Structural inspection points and acceptance criteria during the periodic visit
Inspected componentCritical inspection pointsTolerance or rejection criteria
Base plates and packingBearing capacity of supporting ground, differential settlement beneath base jacks, overturningZero play under base jack, timber load-spreading sole plate without splits or rot
Anchorages and tiesCoupler tightness, condition of the eye screw in the structural work, tube deformationNo loosening, tightening torque in compliance with workshop specifications
Working platformsLatching of trapdoors, presence of anti-uplift devices, cracks in the plywoodZero permanent deformation, tightly flush platform without gaps exceeding trade standards
Collective protective equipmentHeight of the top guard rail, presence of the intermediate guard rail and toe-boardContinuous elements, fully engaged fit without excessive play or unauthorised removal
Netting and sheetingTension of ties, tears in wind-exposed zones, fixings to standardsNo excessive flapping, additional anchorages checked if sheeted

The scaffolding erector inspects the integrity of the load-bearing framework as a priority. On construction sites subject to fast-paced schedules, the unauthorised dismantling of anchorages or diagonals by third parties to facilitate access to an opening constitutes the major structural risk. The inspecting craftsman does not simply carry out a visual check from the ground: they climb every bay to physically test the rigidity of connections and the fixing of platforms.

Inspection responsibilities, lifting of reservations, and keeping the inspection logbook

Site safety organisation relies on a strict demarcation of remits. Pursuant to art. 5 OTConst, the employer designates on each construction site a competent person responsible for occupational safety and health protection, who is able to issue directives to workers. Art. 3 OPA further specifies that the employer must make arrangements and take protective measures that comply with the provisions of the ordinance, other applicable occupational safety regulations, and recognised technical safety standards.

  1. Joint inspectionThe scaffolding foreman walks the facade scaffolding methodically, torque sheets and inspection spanners in hand, preferably with the site manager.
  2. Recording non-conformitiesAny defect noted — distorted member, settled packing, missing toe-board — is immediately recorded with precise referencing by bay and lift level.
  3. Protective measuresIf the structure presents a fall or overturning hazard, access is immediately locked at ground level using physical barriers and formal prohibition signs.
  4. Signing off the logbookThe inspection is formalised in writing in the site logbook, countersigned by the inspector, and handed over to the site management.

Rigorous management of the inspection logbook protects the erection company against unauthorised modifications carried out on the scaffolding. As soon as a substantial modification is requested by a trade — shifting a platform, adding a lifting davit —, the operation requires a new formal verification prior to recommissioning, recorded on the access notice board located at the foot of each ladder or access tower.

Managing critical non-conformities and decommissioning the structure

When a periodic check or a post-bad weather inspection reveals a structural defect — anchor torn out by the Foehn, base jack destabilised by scour, guard rail dismantled by another trade —, the scaffolding instantly loses its compliance. The person signing off the inspection cannot settle for passive observation. The erector or the designated safety manager must immediately prohibit access to the temporary structure to prevent any serious accident.

  1. Physical closure of access pointsRemove the first-level access ladders or lock the trapdoors using chains and padlocks. Erect a physical barrier across each flight of stairs or ground passage with explicit prohibition signs.
  2. Updating signage on siteImmediately remove the green acceptance tag from the notice board at the foot of the scaffolding and replace it with a red tag stating «Scaffolding prohibited from use».
  3. Recording in the inspection logbookEnter the exact defect in the inspection logbook, specifying the date, time, location of the affected bay, the defect found, and the identity of the inspector who decommissioned the structure.
  4. Formal notification to site managementTransmit the stop-use notice in writing to the site management and the user companies to formalise the prohibition against climbing onto the structure.

The organisation of occupational safety and health protection on the construction site falls under art. 5 OTConst, which provides for the designation of a competent person able to issue directives to workers. In the event of a deliberate failure to comply with recognised rules during construction work endangering human lives, art. 229 CP applies.

Frequently asked questions

Who is entitled to complete and sign the periodic inspection logbook?

The regular visual inspection may be carried out by a competent person trained in occupational safety, designated by the user company or the scaffolding erector. However, whenever a structural modification, anchor replacement, or repair occurs after bad weather, only a qualified scaffolding erector may record the technical intervention and validate recommissioning in the construction site inspection logbook.

At what wind speed must the scaffolding be inspected?

As soon as gusts exceed level 2 warnings from MeteoSwiss (around 70 km/h) or after any violent local event such as a summer storm or a Foehn event, an inspection is mandatory before work resumes. The inspector checks the tension of sheeting, the condition of netting, the soundness of anchorages, and the absence of working platform uplift in accordance with standard SN EN 12811.

What must be done if another trade has removed diagonals or anchorages?

The scaffolding must be decommissioned immediately: affix the red prohibition sign and physically secure the trapdoors or ladders. Removing stability components without agreement alters the initial static calculation. The event is recorded immediately in the inspection logbook and reported to the site management. Only the scaffolding erection company may intervene to reinstate the components and formally lift the access prohibition.

Where must the scaffolding inspection logbook be kept?

The inspection logbook must remain permanently on the construction site, available for immediate consultation. It is generally kept in the site management site office or placed in a waterproof pouch directly on the main scaffolding notice board. It contains the initial handover report, the periodic inspection sheets, and the record of exceptional inspections carried out after severe weather.

Texts and standards cited

  • OTConst art. 5organisation of occupational safety and health protection: on every construction site, the employer designates a competent person responsible for occupational safety and health protection, who is able to give directives to workers (para. 1); any person who, through their conduct or condition, endangers themselves or others must be removed from the construction site (para. 2).
  • CP art. 229violation of the rules of the art of building: anyone who, in managing or executing a construction or demolition, intentionally breaches the rules of the art and knowingly endangers the life or physical integrity of persons shall be liable to a custodial sentence not exceeding five years or a monetary penalty; in the case of negligence, to a custodial sentence not exceeding three years or a monetary penalty.