🧱 CFC 212Mobile, suspended and temporary structuresChapter 4 of 10 in the section

Temporary roof scaffolding: covering a roofing site during works

By the end of this chapter, you will be able to determine the span and load-bearing requirements for temporary roof scaffolding. You will master calculating the permissible snow load, setting up effective water drainage and the essential elements to include in the mandatory structural calculation report before erection.

Key takeaways

  • The span of the aluminium beams determines the type of bracing and the centre-to-centre spacing of the support towers.
  • The minimum snow load must be calculated based on the site altitude and SIA standards.
  • Rainwater drainage requires a continuous flow line separated from facades and access routes.
  • The mandatory structural calculation report covers wind action, snow and load transfer.

Roofing span and justification of the snow load

Installing temporary roof scaffolding for the refurbishment of a timber frame or roof covering requires rigorous dimensioning of the load-bearing structure. The span crossed by the aluminium or steel lattice girders directly governs the profile section, the permissible deflection and the type of anchoring required on the existing structure or in the ground. When the span exceeds 15 metres, the scaffolder must adapt the centre-to-centre spacing of the trusses and double certain transverse connections to avoid lateral-torsional buckling under climatic loads.

The permissible snow load on the tarpaulin or sheeting profile constitutes the critical parameter during winter in the context of Romandie. The calculation is not limited to the basic value linked to the site altitude: it integrates the pitch of the temporary roof scaffolding trusses and the sliding capacity of the waterproofing membrane. If the pitch is less than 15 degrees, the risk of wet snow accumulation requires increasing the design load taken into account or providing an intervention system for mechanical snow clearance.

Assessment criteria for span and surcharges
ParameterTechnical requirementImpact on erection
Span from 10 to 20 mStandard 75 cm aluminium lattice girdersProgressive installation with bottom chord bracing
Span exceeding 20 mReinforced girders or steel framework systemRequirement for heavy-duty support towers or through-wall ties
Snow surchargeDimensioning according to site altitude (SIA standards)Tighter truss spacing and maximum tarpaulin tension

Rainwater channelling and safety checks before acceptance

The drainage of rainwater collected by a large-surface temporary roof represents a considerable volume of water during storms or rapid thaws. The scaffolder must design oversized temporary gutters capable of collecting rainfall without overflowing towards the interior of the exposed structure or onto the working platform of the facade scaffolding. Discharge of this water takes place away from walkways and construction site electrical installations, ideally connected to the main rainwater network.

  1. Checking the roof pitchCheck the tension of the tarpaulins and the regularity of the slopes to avoid any water ponding (retention of standing water) deforming the profiles.
  2. Dimensioning downpipesFix flexible or rigid downpipes of sufficient diameter along the standards, anchored at regular intervals.
  3. Verification of the anchor calculation reportEnsure that the tensile force on facade anchors generated by wind uplift on the temporary roof complies with values approved by the engineer.

Before handing over the temporary structure to the finishing work trades or carpenters, a technical acceptance report confirms the conformity of the temporary roof. This document validates that transverse loads and any ballasting strictly match the specifications set out in the structural calculation report approved by the design office.

Load path transfer and anchoring of the load-bearing framework

The temporary roof radically alters the mechanical behaviour of the working scaffolding that serves as its support. The triangulated aluminium or steel girders, often spanning across distances greater than 15 or 25 metres above the roof space being refurbished, generate considerable combined stresses. The dead weight of the trusses, the keder tarpaulins and climatic loads translate into concentrated vertical loads at the support standards, but also horizontal forces causing pull-out or overturning under wind suction.

The underlying scaffolding must imperatively be reinforced. Single standards are doubled or tripled according to the structural results, thereby creating rigid support towers connected by tubular ledgers and diagonal braces in all three dimensions. At the wall plate level of the temporary roof, the connecting base plates must prevent any longitudinal sliding or uplift during gusts. Transferring loads to the ground requires rigorous verification of the permissible bearing capacity of the founding soil or slabs supporting the base jacks.

Behaviour of loads transmitted to the supporting scaffolding according to the nature of the stresses
Nature of actionMain mechanical loadCritical transmission zoneRequired construction measure
Dead weight + snow surchargeHigh axial compressionVertical standards and base sole platesReinforced standards, systematic doubling, wide spreader sole plates
Positive wind pressureTransverse thrust and bendingWall plate nodes and facade diagonal bracesPlan bracing, rigid ties using tubes and couplers
Wind suction (uplift)Axial tension and pull-outTruss junctions and high anchorsMechanical locking pins, high-strength expansion anchors
Lateral-torsional buckling of trussesTorsion and global instabilityRoof bridging connectionsTubular spacer beams, cross bracing cables

Tying into masonry or concrete slabs constitutes the critical factor for overall stability. Standard working ties are not suitable: fixed points capable of simultaneously absorbing tensile and shear forces are essential. Calculated pull-out forces regularly exceed the capacity of ordinary wall plugs, requiring heavy-duty anchor bolts or threaded through-rods with backing plates.

Structural requirements, engineer calculation report and erection protocol

The installation of temporary roof scaffolding deviates from standardised facade scaffolding configurations. Due to large wind-exposed surfaces and substantial clear spans, a specific structural calculation report, drafted by a civil engineer or a qualified technical office, is an indispensable prerequisite before any on-site assembly begins.

The structural calculation report precisely defines support reactions, the required sections for triangulated trusses, the horizontal and vertical bracing scheme, as well as the exact anchor grid. It takes into account the site altitude, local wind exposure and the period the structure remains in place to model climatic loads according to standard SIA 261. Erectors must have annotated shop drawings available on the construction site to adhere strictly to bolted connections and calculated spacings.

  1. Ground pre-assembly and visual inspectionAssembly of triangulated truss components on the ground using certified pins and checking the straightness of chords, condition of connectors and tarpaulin keder tracks.
  2. Crane lifting and coupling onto wall platesHandling bays using a spreader beam to avoid parasitic bending, then positioning and immediate mechanical locking onto the scaffold tower heads.
  3. Bridging and immediate stabilisationInstallation of transverse tie tubes, fitting cross bracing cables, and torque-tightening of right-angle couplers before detaching the lifting equipment.
  4. Safe installation of sheetingPulling reinforced tarpaulins through the aluminium profile grooves using ropes from safe working platforms, then tensioning with ratchet straps to eliminate flapping.

The conformity of the installation engages the liability of stakeholders in accordance with technical rules. According to CP, whoever intentionally or negligently violates the recognised rules of construction when directing or executing a building project and thereby endangers the life or physical integrity of persons is liable to criminal penalties. This provision highlights the importance of rigorous erection in accordance with the approved structural plan.

The general organisation of the construction site requires strict anticipation of accident prevention measures. As set out in art. 3 OTConst, works are planned so that the risk of occupational accidents, occupational illnesses or health hazards is kept as low as possible. When erecting these temporary roofs at height, the use of safe platforms or attachment to temporary lifelines integrated into the trusses guarantees continuous protection for scaffolders.

Handling losses, weather surcharges and structural failures

On a roofing construction site under a temporary roof, the occurrence of unforeseen violent wind, sudden snow accumulation or a torn tarpaulin requires immediate coordinated action. The absolute priority remains the evacuation of threatened areas beneath and around the temporary structure. The erection manager or foreman records the incident in the site logbook and issues a formal notice to the site management. Pursuant to CO, the contractor must inform the client if any circumstance jeopardises the proper or timely execution of the work, under penalty of bearing the consequences.

When water forms a pond on the tarpaulin due to poor tensioning or a blocked temporary gutter, the concentrated load can rapidly exceed the load-bearing capacity of the transoms. The response team punctures the membrane in a controlled manner into watertight containers located on the lower floor if the risk of bay collapse becomes critical, before retensioning the sheeting once conditions have stabilised.

In the event of a dispute relating to partial settlement or major water ingress, the parties rely on standard SIA 118 to arrange a joint inspection record. Scrupulous adherence to recognised trade practice protects the execution team. According to CP, whoever, when directing or executing construction or demolition work, intentionally breaches the rules of the construction art and knowingly endangers the life or physical integrity of people is liable to a custodial sentence not exceeding five years or a monetary penalty, the sanction being up to three years or a monetary penalty for negligence. Keeping complete layout drawings, anchor records and the signed structural calculation report from the engineer is the only way to establish the conformity of the delivered temporary work.

Frequently asked questions

How should you respond when a temporary roof tarpaulin tears in a wind gust?

The scaffolder immediately cordons off the ground perimeter to prevent falling object hazards. Access to the framework of the temporary roof scaffolding is restricted to personnel equipped with a fall arrest harness attached to the structural lifeline. If weather conditions prevent the immediate replacement of the tarpaulin sheet in its tracks, the team securely ties down loose flaps to stop flapping and prevent tearing of the supporting transom.

What should be done if accumulated snow exceeds the load permitted by the structural calculation report?

The site management and the scaffolder must prohibit access beneath the temporary roof. Snow removal must not be improvised directly from the tarpaulin: it is carried out by scraping from lateral service platforms protected by guardrails complying with the Construction Works Ordinance. If technically impossible, installing a temporary forced-air heating system in the roof space accelerates melting without overloading the frame.

Who is liable for water damage if a temporary gutter overflows into the building?

Liability depends on the works contract and the maintenance protocol defined during the acceptance of the work. The scaffolder is responsible for hydraulic dimensioning and the correct installation of gutters in accordance with recognised trade practice. However, regular periodic cleaning to remove leaves or construction waste is the responsibility of the general contractor or the trades working under the roof, in accordance with standard SIA 118.

Can the temporary roof scaffolding anchors be modified without consulting the engineer?

No, any modification of ties or relocation of anchor ties is strictly prohibited without written consent from the engineer who drafted the structural calculation report. Temporary roof scaffolding is subject to considerable uplift and overturning forces under wind action. Removing or loosening a tie to free up access for tinsmith work compromises the overall static equilibrium of the structure and directly engages the liability of the team leader.

Texts and standards cited

  • COmaterial and site: the contractor is liable for the good quality of the material supplied; if the material supplied by the client or the ground designated by the client is recognised as defective, or if another circumstance jeopardises the proper or timely execution of the work, the contractor immediately informs the client, under penalty of bearing the consequences (para. 3).
  • CPviolation of recognised rules of construction: whoever, in directing or executing a construction or demolition, intentionally breaches the rules of construction and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; for negligence, up to three years or a monetary penalty.
  • norme SIA 118General conditions for construction works.