Key takeaways
- The green notice certifies the formal handover of the scaffolding by a competent person from the company.
- The red display indicates incomplete or modified works, formally prohibiting access to all trades.
- Any structural modification results in the immediate revocation of the authorisation of use by the scaffolder.
- Prohibiting access without a valid notice protects civil liability and criminal liability on Swiss construction sites.
Access signage according to Suva directives and the handover protocol
On Swiss construction sites, access to the decking of facade scaffolding is strictly contingent upon the presence of a visible access notice, positioned at the primary ascent point, usually on the first flight of the staircase tower or on the first-level access trapdoor. According to Suva directives and recognised technical rules, this display informs each user in real time of the structural integrity and readiness of the installation. Accessing an uninspected structure or one undergoing erection exposes workers to a mortal danger of falling from a significant height.
- Access notice (scafftag)
- Standardised display device consisting of a rigid holder and a reversible or interchangeable insert, affixed to scaffolding ascent points to indicate unambiguously its operational status, its permissible load limits, and the identity of the responsible scaffolder.
| Displayed colour | Status of the structure | Authorised persons | Operational consequences |
|---|---|---|---|
| Red (or empty holder) | Non-compliant scaffolding, incomplete or undergoing erection/dismantling | Only qualified scaffolders equipped with their fall arrest equipment | Strict ban on climbing for all trades (painters, bricklayers, tinsmiths, roofers) |
| Green (completed insert) | Scaffolding fully inspected, handed over, and deemed compliant | All trades authorised by the site management | Authorised use strictly within the stated load class and width limits |
The green notice is posted exclusively after the full completion of erection and the execution of a rigorous visual and mechanical inspection by the scaffolding company. The employer shall take the steps and protective measures that meet the requirements of the Ordinance, other applicable occupational safety provisions, and the recognised rules of safety technology and occupational medicine, in accordance with art. 3 OPA. This handover inspection specifically covers anchoring into the substrate, alignment of standards, fastening of ledger braces, continuity of triple-rail edge protection, and the absence of excessive gaps across decking.
- Company name and full contact details of the scaffolding erection company.
- Load class in accordance with Swiss technical standards and permitted uniformly distributed load.
- Exact date of the final handover inspection and name of the qualified scaffolder who checked the structure.
- Any usage restrictions (sheeted areas, prohibition on storing heavy pallets, hop-up brackets).
Removal of the notice during alterations and strict prohibition on bypassing
The green insert is not a permanent authorisation. It certifies the compliance of the installation at a specific point in time. As soon as a modification occurs on the structure — removing an anchor to treat a facade, removing a toeboard to install a threshold, taking down a ledger brace, or cutting through a safety net — the scaffolding instantly loses its original compliance. Only a qualified scaffolder holds the technical authority to remove the green insert and revert the structure to red signage.
- Identification of modification or degradationThe chargehand identifies an alteration (anchor removed by a third party, storm that shifted cantilever brackets, plant impact on base jacks).
- Immediate revocation of access authorisationThe green insert is immediately removed from the holder; the underlying red notice becomes visible, locking out access.
- Physical closure of access pointsInstallation of a physical barrier at the first ladder or flight of stairs to prevent any physical entry.
- Reinstatement and re-inspectionScaffolders carry out the structural rectification, verify coupler torque, and reinsert the dated and signed green insert.
The prohibition on passing a red notice applies to all users without exception: subcontractors, site management, engineers, or foremen. No justification of site emergency, quick measurement-taking, or paint touch-up permits any derogation from this rule. In the event of an accident occurring on scaffolding where the red notice was deliberately bypassed, the criminal liability of the persons involved may be directly engaged under art. 229 CP, which penalises the violation of the recognised rules of the art of building endangering the life or physical integrity of persons.
Operational status of the notice and operational responsibilities
On a site in French-speaking Switzerland, the access notice fixed to the ladder or at the base of the staircase tower constitutes the tangible act that formalises the completion of erection operations and authorises use of the structure. As long as the structure is undergoing assembly, access displays the prohibition notice, represented by the red face or the absence of the authorisation slip in the sealed card holder. Inserting the green handover slip transforms the facade scaffolding into a handed-over collective workstation. From this moment onward, the compliance liability of the structure rests upon this physical marking.
Only an authorised scaffolder — the master scaffolder or the foreman of the scaffolding company that erected the structure — has the right to flip this notice to display the green authorisation face. A finishing work tradesperson, a painter, or even the site management has no legal or technical authority to validate this access. Pursuant to art. 3 OPA, the employer shall take the steps and protective measures that meet the requirements of the Ordinance, other applicable occupational safety provisions, and the recognised rules of safety technology and occupational medicine. Affixing the access notice stems directly from this principle of prevention.
| Visible status of the notice | Technical meaning | Person authorised to modify the display | Permitted use |
|---|---|---|---|
| Completed green face | Scaffolding fully erected, anchored, inspected, and handed over | Master scaffolder or foreman of the scaffolding company | Authorised use for trades in accordance with permitted loads |
| Red face / Prohibition notice | Scaffolding undergoing erection, under modification, or unsafe | Scaffolders exclusively | Access strictly prohibited to all trades |
| Empty holder or missing notice | Absence of formal handover or structure modified without inspection | Scaffolder (for regularisation) | Total prohibition on climbing onto the structure |
The green face of the document is not merely a visual green light: it records the operational limits of the structure. It must state the name of the responsible scaffolder, the date of handover, the permissible live load per square metre of decking, as well as the specific purpose of inside brackets or working platforms. Loading a deck beyond the indicated value immediately voids the issued authorisation.
Notice removal, structural alteration, and prohibition on bypassing
As soon as a modification takes place on the structure — removal of an anchor to plaster a facade, temporary removal of a sway brace, or taking off a top guardrail to load a pallet —, the scaffolding instantly loses its compliant structure status. If the scaffolding company is summoned to modify a bay, its first technical measure consists of disabling access by removing the green insert or flipping the notice to its red face. This immediate reclassification formally prohibits anyone from climbing onto the entire facade or onto the section concerned.
Bypassing a prohibition notice constitutes one of the most critical offences on a building construction site. Stepping over a chain blocking the staircase, climbing over edge protection from a floor window, or ascending the outer standards when the lower access is padlocked directly engages the offenders' liability. The Construction Work Ordinance imposes strict rules on providing safe structures: when scaffolding is barred, it is deemed non-existent as collective protection.
In the event of an accident occurring on scaffolding to which access was prohibited by a red notice or whose structure was unlawfully modified, investigating authorities examine the technical negligence committed. Art. 229 CP penalises anyone who, when directing or carrying out a construction or demolition, intentionally breaches the rules of the art and thereby knowingly endangers the life or physical integrity of persons, with a custodial sentence not exceeding five years or a monetary penalty, and with a custodial sentence not exceeding three years or a monetary penalty if the act is committed through negligence.
- Check each morning for the presence and legibility of the green notice at the base of access stairways.
- Immediately report any damaged, torn-off, or red-flipped notice to the site management.
- Systematically refuse access to the structure as soon as an anchor has been loosened or a tube removed.
- Wait for the requalification inspection and the new signature of the master scaffolder before resuming work after any modification.
Rigorous management of these notices ensures ongoing safety on site. The scaffolder remains the guarantor of the geometry and stability of the installation; the notice at the foot of the stairs is the sole mechanism conveying this technical guarantee to daily users.
Managing breaches, damage, and emergency remedies
On a site in French-speaking Switzerland, discovering scaffolding modified without authorisation or an altered access notice requires a methodical reaction. If a trade removes anchors, dismantles braces, or takes off boards to install a track or external insulation, the structure loses its certified stability. The master scaffolder or foreman applies the securing procedure immediately: access must be closed off physically and administratively without awaiting arbitration from the site management.
- Immediate physical closure of the flight of stairs or access ladder by means of a locked rigid barrier.
- Systematic flipping of the access notice to its red prohibition face or removal of the green insert from the inspection holder.
- Written notice of cessation of use issued to the client, the site management, and the company responsible for the damage.
- Joint factual record supported by date-stamped photographs documenting the removal of anchors, guardrails, or platform decks.
Recommissioning the structure cannot stem from a mere verbal agreement. In accordance with SUVA directives and the Construction Work Ordinance, only a qualified scaffolder is authorised to return the structure to compliance, verify the tightening torques of couplers, and test anchor pull-out resistance. Once the reinstatement work is complete, a new formal inspection is documented on the handover report before reinserting the green access notice.
The employer also applies OTConst, which mandates appointing on every construction site a competent person responsible for safety, authorised to issue instructions and to dismiss any person who endangers others. The scaffolder records any dispute in the site logbook to preserve the traceability of their service.
Frequently asked questions
What should be done if a green notice is displayed but an anchor has been removed?
Access is immediately prohibited. Even with a green notice inserted, the removal of an anchor voids the technical compliance of the structure. The chargehand present must block passage at the base of the access tower, flip the notice to the red prohibition face, and notify the scaffolder for reinstatement followed by a formal check of fixings prior to any further use.
Does a painter or facade plasterer have the right to flip the access notice themselves?
No. SUVA directives restrict the manipulation of the access notice to the scaffolding company that erected and handed over the structure. Third-party users have no authority to certify the stability or compliance of scaffolding. Only the master scaffolder or the specialist commissioned for inspection may switch the display from red to green after recording compliance on the inspection report.
Does the absence of a notice at the foot of the stairs authorise climbing onto the structure?
Absolutely not. On Swiss construction sites, the absence of an access notice is regulatory equivalent to a total prohibition on use. Scaffolding without signage is deemed to be undergoing erection, under modification, or abandoned without safety inspection. Access remains strictly barred for all trades until the official green notice has been posted with the date and the scaffolder's signature.
How can access prohibition be physically established on a staircase tower?
The red prohibition notice must imperatively be supplemented by an impassable physical closure. Recognised good practice consists of installing a locked metal safety gate or a tubular guardrail element secured with couplers at the base of the ascending flight. A simple piece of two-tone barrier tape does not constitute a sufficient obstacle to physically prevent workers from entering an uninspected structure.
Texts and standards cited
- CP art. 229violation of the rules of the art of building: whoever, when directing or carrying out a construction or demolition, intentionally breaches the recognised rules of the art and thereby knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; if committed through negligence, not exceeding three years or a monetary penalty
- OTConstorganisation of occupational safety and health protection: the employer shall appoint on each construction site a competent person responsible for occupational safety and health protection, who is able to issue directives to the workers (para. 1); any person who, through their conduct or condition, endangers themselves or others shall be dismissed from the construction site (para. 2)