🧱 CFC 212Facade scaffolding: components, erection and dismantlingChapter 8 of 10 in the section

Dismantling scaffolding: reverse order, and what is never dropped

Dismantling facade scaffolding exposes erectors to heightened risks of falling and struck-by-object hazards. This chapter details the methodical sequence of operations in the reverse order of erection, removal under collective protection, the absolute ban on throwing components, and the physical organisation of ground cordoning to secure the work area.

Key takeaways

  • Dismantling is carried out strictly in the reverse order of the manufacturer's assembly instructions.
  • Removing the top guardrail requires temporary collective protection or suitable personal equipment.
  • Throwing any material down from working platforms is strictly prohibited on the construction site.
  • The zone below must be rigorously cordoned off and prohibited from access before any component is removed.

The strict reverse order and managing the final guardrail

On Swiss construction sites, Suva statistics confirm that dismantling scaffolding causes more fatal accidents than its erection. Erectors tend to lower their vigilance when dealing with a familiar structure whose apparent stability masks progressive weakening. Dismantling does not mean taking the structure apart opportunistically: the work requires systematic deconstruction in strictly the reverse order of the assembly instructions. According to art. 26 OTConst, facade scaffolding must be installed as soon as the fall height exceeds 3 m; during dismantling, this same threshold requires maintaining flawless protection until each level is completely evacuated.

  1. 1. Preliminary cleaning of platformsBefore removing any metal fastener, decks are thoroughly swept clean. Rubble, mortar residues, wooden packers, and tools left behind by finishing work trades are brought down.
  2. 2. Removal of supplementary equipmentDebris nets, weatherproofing tarpaulins, cantilever brackets, and roof overhang extensions are removed bay by bay, preserving safe access via ladder access decks.
  3. 3. Removal of toeboards and intermediate railsOn the highest level, timber or aluminium toeboards and intermediate guardrails are dismantled. The erector remains protected behind the upper main guardrail during this phase.
  4. 4. Removal of decks and advance guardrailsBefore removing the last perimeter guardrail of a level, a temporary advance guardrail is installed from the deck immediately below, or the erector clips onto a structural anchor point.
  5. 5. Removal of vertical frames and diagonalsThe facade standards or frames are unlocked, disengaged from their spigots, and lowered, followed by the longitudinal bracing diagonals of the level being dismantled.
  6. 6. Phased removal of facade tiesWall ties into the masonry are only unscrewed progressively as the relevant level is taken down. No tie located below the active working platform may be removed ahead of time.

Controlled lowering of components and tight cordoning of the ground zone

The temptation to speed up the pace sometimes leads some erectors to drop components to the ground or throw them towards a flatbed lorry. This practice is strictly prohibited. The Construction Work Ordinance requires measures to ensure that falling objects or materials do not endanger any worker. Throwing a metal component or a deck irreparably deforms the steel or aluminium, creating invisible micro-cracks that compromise the component's mechanical strength upon its next reuse. Furthermore, the risk of ricochet at ground level constitutes a fatal hazard to third parties.

Methods for vertical lowering of scaffolding components
MethodRequired equipmentOperating conditionsOperating limits
Electric swivel-arm hoistSteel wire rope, safety catch hook, pivoting jibVerified fixing to standard, remote control with emergency stopMaximum working load must be scrupulously observed
Rack-and-pinion material hoistGuided platform, level barrier gatesFull stop at loading level, gate closedRequires dedicated ties maintained until its dismantling
Lifting rope with gin wheelSelf-locking brake gin wheel, hemp or synthetic ropeClove hitch or textile sling on every bundleRestricted to low heights and small batches of components
Chain of workersHandling gloves, ergonomic postureOne worker per staggered deck levelProhibited for heavy loads or 2 m frames

At the base of the structure, the potential drop zone must be strictly cordoned off. The safety perimeter is marked out by rigid physical barriers, such as mesh site fencing panels, and not merely by barrier tape, which remains easily crossed. The width of the ground zone must incorporate the scaffolding's projection plus a lateral buffer accounting for potential ricochets. Strict no-entry warning signs with the mandatory hard hat pictogram must be visibly fixed at every access point.

Methodical level-by-level removal: structural stability and tie retrieval

Dismantling facade scaffolding permits no crew shortcuts. The absolute rule is level-by-level deconstruction, from top to bottom, perfectly mirroring the erection sequence. During this operation, the temptation to remove ties across several storeys in advance to save time represents the primary cause of overturning of temporary works under wind loads or the sway of handled loads.

According to art. 26 OTConst, facade scaffolding must be installed as soon as the fall height exceeds 3 m; the top guardrail must project at least 80 cm above the edge of the highest area presenting a fall hazard (100 cm if the guardrail is less than 60 cm from the edge). This collective protection requirement also governs the end of the site: no section of frame or perimeter protection is removed without first securing the storey immediately below.

Intervention sequence and tying rules per level during dismantling
Component removedErector checkpointTie removal condition
Top guardrail and toeboardsWearing personal fall protection equipment with chinstrap on the hard hatKeep all ties for the working deck in place
Working decks and trapdoorsRetreat from the level below or from a protected bayNever unbolt the tie before the deck is lifted
Diagonals and ledgersImmediate risk of vertical standard bucklingRetain bracing beneath the active dismantling deck
Vertical frames or tubular standardsControlled vertical disengagement, without twisting the spigotsFinal removal of facade tie only at this stage

Mechanical handling, lowering without dropping, and ground organisation

Dropping scaffolding components from a working platform constitutes gross misconduct on the construction site. Even small components such as right-angle couplers, spigots, timber sole plates, or safety pins must be packed into mesh stillages or hoist buckets, then lowered using a hoist or manual pulley block.

At workstations and traffic routes, measures must be taken to ensure workers are not endangered.

art. 17 OTConst

To comply with the duty to protect personnel against falling objects, the ground crew sets up an impassable barrier: rigid fencing such as mesh site barriers, warning tape supplemented by strict no-entry signs. The perimeter covers the width of the structure plus the hoist swing area and a buffer corridor for rotating the standards being handled.

  1. Vertical lowering of componentsUse a swivel-arm hoist or a site material hoist compliant with the Machinery Safety Ordinance. Frames and decks are strapped in suitable lifting cradles; lowering is carried out at a constant speed under the visual control of the ground receiver.
  2. Sorting and checking for deformationsUpon receipt in the cordoned-off area, every frame, diagonal, and deck undergoes strict sorting. Any warped standard, cracked deck, or bent claw hook is immediately taken out of the storage flow and labelled for scrap or workshop repair.
  3. Palletisation and bundlingStack components by type in dedicated metal racks. Frames are stacked vertically or supported horizontally, then strapped before handling with a forklift truck or the company transport lorry.
  4. Sealing facade drill holesAs anchor plugs are removed, fixing holes drilled into masonry or concrete are sealed using watertight plugs or repair mortar depending on the substrate type and the external thermal insulation system.

Managing unforeseen events and emergency stops during dismantling

Dismantling facade scaffolding exposes the crew to sudden structural imbalances whenever a load-bearing or stabilising component is removed out of sequence. Art. 26 OTConst mandates facade scaffolding whenever the fall height exceeds 3 m, with a top guardrail extending 80 cm above the upper working area, or 100 cm if the guardrail is less than 60 cm from the edge. During dismantling, each removed platform turns the level below into a newly exposed working deck. If a tie proves warped, pulled out by another trade, or jammed in the masonry, proceeding downwards is strictly prohibited until the stability of the adjacent bay is restored using a temporary tie.

Managing falling objects remains the critical risk during jamming phases. In accordance with OTConst, a safety helmet must be worn during scaffolding erection and dismantling, with a chinstrap particularly when working with fall protection equipment. A jammed component must never be forced with a sledgehammer from a platform lacking full guardrails. It is strictly prohibited to discard metal components or timber decks by dropping them from the standards. In the event of a cable hoist or return pulley jamming, the load remains secured to the scaffolding frame while the exclusion zone on the ground is locked down using rigid barriers.

  • Immediate reporting to the foreman of any missing ties on levels not yet dismantled.
  • Fitting tube-and-fitting ties to directly replace defective wall anchors before frame removal.
  • Immediate evacuation of the ground impact area at the first sign of abnormal sway in the facade plane.
  • Access lockdown using rigid prohibition signs at the base of each inclined ladder or access deck.

Frequently asked questions

How to react if a lower tie has been removed before dismantling the scaffolding?

The erector immediately stops dismantling upper levels. They reinstate the missing tie or install temporary propping using tube and fittings on the bay concerned. No bracing component or deck may be removed until the structure has recovered its initial rigidity. The ground area remains completely sealed off during this consolidation work.

What to do if wind gusts pick up while lowering frames?

As soon as wind compromises the handling of decks or operator stability, the foreman halts operations. Erectors reinstall temporary guardrails over the exposed area, securely clamp down remaining platforms, and lower all loose components stored awaiting removal. The hoist is locked out and the scaffolding is locked off at ground level.

Why is it forbidden to remove two platform levels simultaneously?

Removing decks across two consecutive storeys eliminates the horizontal diaphragm of the structure and deprives erectors of a protected working surface. This practice exposes the worker to a high fall with no intermediate catchment platform. Removal must strictly be performed bay by bay and level by level, moving downwards methodically with the safety guardrail.

How to manage a ground zone if third-party workers breach the cordon tape?

Flexible barrier tape is prohibited for marking out an exclusion zone beneath scaffolding being dismantled. The crew erects rigid freestanding or mesh barriers at least two metres high. If a worker enters, hoisting and handling operations are halted immediately. The trespasser is escorted out before any handling of metal components resumes.

Texts and standards cited

  • OTConstduty to wear a safety helmet during all work where workers may be endangered by falling objects or materials; helmet worn in any case during construction work until completion of the structural work, near cranes and earthmoving equipment, during excavations, demolition, and erection and dismantling of scaffolding (para. 2); helmet with chinstrap particularly during work with fall protection equipment or rope access (para. 3).
  • OTConst art. 26facade scaffolding in building construction work: facade scaffolding must be installed as soon as the fall height exceeds 3 m; the top guardrail must project at least 80 cm above the edge of the highest area presenting a fall hazard (100 cm if the guardrail is less than 60 cm from the edge) (para. 2).