Key takeaways
- Any modification of the scaffolding strictly requires a prior written request countersigned by the site management.
- Removing an anchor without immediate compensation invalidates the initial handover inspection report.
- SUVA directives mandate the installation of substitution anchors before any removal on the facade.
- Remediation and inspection are subject to a quantity survey backcharged to the requesting trade.
Prior request and SUVA rules for relocating anchors
During the installation of external thermal insulation or cladding panels, facade anchors frequently present a physical obstruction for the facade installer. The temptation is strong in the field to unscrew the threaded rod, dismantle the tie tube, or remove an expansion plug without informing the scaffold erector. This common but prohibited practice alters the statics of the temporary structure and transfers impermissible buckling stresses onto neighbouring standards.
To reconcile finishing work progress with safety, a strict administrative and technical procedure is essential. The facade installer must submit a prior written request to the scaffolder and site management at least five working days before the scheduled intervention in the area concerned. This form details the exact location of conflicting anchors, grid dimensions, and the planned phasing for applying finishing coats.
- Notification in writing with identification of the ties on the scaffolding drawing provided at the time of handover.
- Engineering of a substitution system: installation of reveal ties on window reveals or relocation to an adjacent node.
- Prior installation of compensating anchors before any loosening of couplers or extraction of original screw eyes.
- Verification of the load-bearing capacity of the new support points according to the scaffolding manufacturer's technical data sheets.
The fundamental principle of the SUVA directives is based on systematic compensation: the erector never releases a fastening without having first secured the standard at an adjacent level. In the case of a ventilated facade, using offset brackets or through-tubes passing through open joints allows the anchor to be maintained while guaranteeing the airtightness of the thermal envelope.
Remediation protocol, handover re-inspection, and backcharging of interventions
As soon as a structural component is moved, the presumption of conformity established upon handover of the structure expires. Scaffolding modified by a third party without notice must be immediately decommissioned by the erector using a red SUVA prohibition sign to ban access until the sector has been completely revised. The employer takes protective arrangements and measures that comply with the provisions of the ordinance on the prevention of accidents and occupational diseases, in accordance with art. 3 OPA.
- Joint inspection record of alterationsThe chargehand erector inspects the facade area in the presence of the facade installer's team leader and notes disconnected anchors, loosened couplers, and any deformations of the structure.
- Re-establishment of the mechanical connectionThe scaffolding team installs new permanent or temporary ties, retightens right-angle couplers to the prescribed torque, and checks the plumb of vertical standards.
- Preparation of the handover re-inspection reportA new dated and signed inspection report records the authorised modifications, the structural integrity of the installation, and authorises access once again for the other trades.
- Joint quantity survey for backchargingThe daywork timesheet stating intervention hours, travel distance, and deployed equipment is submitted for approval to the site management.
Financial liability for adaptations rests entirely with the trade that requested them or caused the damage. If the modification was planned via a written request, services are invoiced according to the schedule of unit prices or on daywork terms following prior approval by the site management. If it involves unauthorised tampering identified after the fact, the erector is entitled to apply standard industry emergency rates to secure the site without notice.
| Situation identified on site | Required technical action | Certification document | Entity liable for costs |
|---|---|---|---|
| Advance request from the facade installer | Anchor relocation with compensation | Adaptation sheet and site management approval | Facade installer (or site management item per contract) |
| Unauthorised removal discovered during inspection | Immediate securing and overhaul | Defect notice and new report | Company responsible for dismantling |
| Final reinstatement after cladding completion | Permanent fixing according to initial drawing | Reinstatement inspection report | Facade installer via the site account |
Managing liabilities requires absolute documentary rigour. By issuing the handover re-inspection report accompanied by the daywork quantity survey to the site management, the erector protects their contractual liability under the rules of standard SIA 118 and reactivates the operating warranty for all site users.
Recording unauthorised modifications and immediate protective measures
On ventilated facade or external thermal insulation construction sites, untimely dismantling of anchors by substructure installers remains a major cause of accidents. As soon as an erector or team leader observes that a tie strap, reveal prop, or eye anchor has been removed without prior authorisation, the structure loses its original structural conformity.
A trade removing a rigid connection alters wind load distribution and transfers critical pull-out forces onto neighbouring anchors. The scaffold erector's response must freeze the situation without delay to prevent any risk of the structure collapsing.
- Securing and cordon-offProhibit access to modified working decks by removing access ladders or installing physical barriers fitted with the prohibition sign.
- Joint survey of defectsPhotograph cut, unscrewed, or relocated attachment points, identifying each bay and each lift relative to the original layout drawing.
- Formal notice to site partiesInform the site management and the facade installer in writing of the immediate suspension of the structure's certificate of conformity.
- Structural assessmentDetermine the necessity of installing temporary diagonal braces or temporary ties in sound areas prior to any re-intervention.
The site foreman must not tolerate any reloading until the structure has been inspected by a qualified person from the scaffolding company. Art. 5 OTConst specifies that on every construction site, the employer designates a competent person responsible for occupational safety and health protection who is able to issue instructions to workers. This responsibility excludes any self-management of anchor points by third parties untrained in scaffold erection.
Remediation costing, handover re-inspection, and contractual management
Remedying an anchor relocated by another trade does not fall under the routine maintenance stipulated in the initial contract. Any corrective intervention requires deploying qualified scaffolders, suitable plug-and-anchor fixings for masonry or concrete substrates, as well as recalculating the permissible load in accordance with SUVA directives.
| Technical step | Intervening trade | Deliverable or substantiation | Financial allocation |
|---|---|---|---|
| Unplanned anchor removal | Facade installer / Cladding fixer | Joint inspection record of work stoppage | Interruption costs attributable to third party |
| Supply and fitting of new anchor | Qualified scaffold erector | Torque / pull-out test report | Daywork invoicing to defaulting company |
| Installation of extension or offset anchor | Qualified scaffold erector | Offset sketch and structural calculation note | Materials and labour schedule |
| Conformity handover re-inspection | Scaffolding supervisor | New signed inspection report | Fixed technical approval fees backcharged |
When cladding prevents access to the original wall plug, the erector adapts the system using through-extension tubes, extended frame screws, or specific fixings into lintel returns. Drill holes must maintain the minimum edge distances in concrete specified by the mechanical or chemical anchor manufacturers.
Anchor disputes: tagging out, formal notice, and liability discharge
On ventilated facade or rendering construction sites, unilateral dismantling of scaffolding ties by secondary trades generates heated disputes during backcharging. If the facade installer refuses to sign the daywork sheet or disputes the remediation invoice, the erector must immediately refer management of the incident to the site management.
- Securing and closing off accessAs soon as an uncoordinated anchor removal is identified, the weakened sector must be tagged out. The SUVA disclaimer sign or red access prohibition signage is affixed to the relevant access ladders and deckings.
- Formal notice to site managementThe erector notifies the site management and the client in writing that the structure has lost its structural conformity due to third-party intervention. This notification discharges the scaffolder from collapse risks until handover inspection has been formally renewed.
- Remediation and handover re-inspection reportOnce approval from the site management is secured via a daywork order or modification order, the team repositions anchors close to the framework, installs test fixings if required, and drafts a new inspection report.
Under Swiss law, art. 365 CO requires the contractor to notify the client if any circumstance jeopardises the proper execution of the work. Concurrently, CP criminally penalises any intentional or negligent violation of the recognised rules of the building trade that knowingly endangers human life or physical integrity. Leaving scaffolding without anchors exposes the supervisor to these criminal penalties.
Frequently asked questions
Can the facade installer replace a scaffolding tie strap themselves with a temporary raking prop?
No. SUVA directives and the Construction Work Ordinance strictly limit the modification of structural components to professionals trained in scaffold erection. Improvised propping distorts the distribution of horizontal and vertical loads. If a facade installer modifies bracing or tubes, they incur their own civil liability and strip the structure of its conformity, compelling the scaffolder to immediately tag out the affected bay.
How should the prior request be formalised before installing cladding substructure panels?
The facade installer must submit a written request to the site management at least 48 hours in advance. The document indicates the bay coordinates, the reference marks of the eye bolts to be moved, and the installation date. The appointed scaffolder then plans the intervention: installing temporary offset anchors before removing the obstructing ties, ensuring the continuous stability mandated by SUVA.
Who bears the cost of the handover re-inspection after moving an anchor?
The site management approves the daywork order with the scaffold erector for installation, dismantling, and inspection labour. Then, according to site coordination rules and standard SIA 118, the amount is backcharged directly to the requesting facade subcontractor. Verification hours and updating the handover inspection report form an integral part of this invoice.
What should be done if an anchor has been severed on the facade without notice?
The scaffolder enforces protective measures: closes off the access ladder, takes dated photographs of the disconnected standard, and sends a stoppage notice to the site management. As CP penalises endangering others during construction work, no one may climb back onto the platforms until a compliant fastening is reinstated and verified with a new inspection sheet.
Texts and standards cited
- norme SIA 118General conditions for construction work and handling of contractual disputes
- CO art. 365Contractor's obligation to immediately inform the client if any circumstance jeopardises the proper execution of the work
- CPViolation of the recognised rules of the building trade endangering human life or physical integrity