🧱 CFC 212Anchorages, stability and wind resistanceChapter 10 of 10 in the section

High-rise scaffolding: load transfer, intermediate brackets and calculation

This chapter details the structural requirements imposed on scaffolding exceeding manufacturers' standard configurations. The team leader and the site supervisor learn how to determine the need for a specific structural report, dimension the installation of intermediate load-transfer brackets, and incorporate essential design lead times into the general construction site schedule.

Key takeaways

  • The manufacturer's standard configuration no longer covers stresses beyond standard certified heights.
  • Standard SN EN 12811 governs the design assumptions for operational and climatic loads.
  • Intermediate load-transfer brackets transfer vertical loads directly into the load-bearing framework of the building.
  • Structural engineering requires an irreducible lead time of several weeks before supply and erection.

Verification by calculation and limits of standard configurations

Technical instructions provided by facade scaffolding manufacturers are based on precise certified configurations, generally limited to standard heights not exceeding 24 to 30 metres without heavy structural adaptations. As soon as the structure exceeds these thresholds or receives features that alter wind exposure, such as impermeable sheeting or netting, the scaffolding becomes a non-standard special structure. The accumulation of dead loads and live loads along the standards generates axial forces that can cause the base standards to buckle. It is therefore strictly prohibited to erect the structure without formal calculations.

Standard SN EN 12811 specifies performance requirements and general and structural design methods for facade access and working scaffolding.

SN EN 12811

The structural calculation report for non-standard scaffolding must be prepared by a civil engineer or an engineering office specialising in lightweight steel structures. This technical document analyses the overall stability of the framework under the most unfavourable combination of actions in accordance with Swiss construction standards. It incorporates the self-weight of the steel or aluminium, the designated service load class for the decks, and the maximum dynamic wind pressures associated with the geographic zone and site roughness.

Pursuant to art. 3 OTConst, construction work must be planned so that the risk of accidents is as low as possible, which requires verifying the stability of the installation well before the equipment arrives on site. Scaffold foremen ensure that the calculated vertical loads do not exceed the ultimate capacity of the base timber packings and base jacks.

Intermediate load-transfer brackets and integration into the works schedule

When the total height of the building risks crushing the lower standards or when the ground bearing capacity at the base of the facade is insufficient, the erector must split the vertical load transfer. The proven technique consists in installing one or more tiers of intermediate load-transfer brackets anchored into the structural work. These triangulated steel structures, composed of reinforced sections or lattice beams, take up the entire self-weight and superimposed loads from the upper lifts to transfer them directly into the reinforced concrete slabs or shear walls of the host building.

  1. Identification of structural supportsVerify the position of the reinforced concrete load-bearing elements in close coordination with the civil engineer responsible for the primary structure.
  2. Installation and anchoring of bracketsSecure the steel brackets using through-bolts with backing plates or certified concrete anchors suited to the calculated tensile and pull-out forces.
  3. Erection of upper starting base jacksInstall base jacks and the first frames of the suspended scaffolding directly onto the horizontal ledgers of the load-relief brackets.
  4. Mechanical disconnection or load breakCreate a mechanical separation on the lower tier standards to prevent vertical loads from the upper section from transferring down to the base.

Deploying high-rise scaffolding requires rigorous anticipation in the contractor's scheduling. The design lead time to be included in the schedule typically spans four to six weeks prior to the initial intervention on site. This period includes the technical exchange phase between the scaffolder's design office and the project engineer, the production of setting-out drawings, the approval of tie points, and the ordering of special components or bespoke sections.

Under art. 365 CO, if any circumstance compromises the regular or timely execution of the work, the contractor must inform the client. A delay in the transmission of concrete drawings or in the validation of bracket anchor points stalls the engineering studies and alters the overall erection schedule.

Requirements of SN EN 12811 and structural report for non-standard structures

As soon as working scaffolding exceeds the maximum height permitted by the manufacturer's technical instructions — generally set between 24 and 30 metres depending on the tie layout — or when it is fitted with full sheeting altering wind exposure, the erection falls outside the scope of standardised typical configurations. Execution therefore requires a structural calculation report for non-standard scaffolding, prepared by a civil engineer or a specialised technical design office. This technical procedure formalises the load path, verifies standards against crushing or buckling, and precisely dimensions the ties.

Standard SN EN 12811 specifies performance requirements, structural design criteria, and calculation methods for facade scaffolding and temporary working platforms, particularly by defining service load combinations, permanent dead loads, and climatic actions induced by wind.

SN EN 12811

The drafting of the structural report for a high-rise structure relies on several mandatory checks required by standard SN EN 12811. The engineer must verify global and local stability at ultimate limit states (ULS) and serviceability limit states (SLS):

  • Vertical load run-down at the base of the standard: cumulative self-weight of the tubular components, working platforms, guardrails, protective equipment, and temporary service loads distributed across the simultaneously loaded levels.
  • Buckling check of the lower standards: modelling the effective buckling length, incorporating the vertical diagonal spacing pitch and the tightening of right-angle couplers.
  • Calculation of pull-out and shear forces at tie points: modelling dynamic wind pressure on the facade, increased with altitude and multiplied if the structure is fitted with debris netting or impermeable sheeting.
  • Bearing capacity of the ground support: checking pressures applied beneath base plates and dimensioning timber sole plates or steel spreader beams on concrete slabs or prepared ground.

Intermediate load-transfer brackets: implementation and schedule planning

On a tower or an extensive building facade, the load-bearing capacity of the lower levels of steel standards eventually reaches its mechanical limits. To avoid systematically doubling up standards or using very heavy-gauge components, the preferred engineering solution is to split the structure vertically using an intermediate load-transfer bracket. These brackets, made of structural steel sections or dedicated lattice trusses, are anchored directly into slab edges or reinforced concrete shear walls of the building.

Setting-out parameters for intermediate load-transfer brackets according to facade typology
Load-bearing element on facadeBracket anchoring systemPrimary load transmissionErector inspection points
Reinforced concrete slab edgeThrough-threaded rods or high-performance chemical anchorsDominant vertical shear and tension at upper anchorTightening torque, embedment depth, and concrete condition
Blind reinforced concrete wallBolted steel base plates or corbel sections welded to embedded platesCombined direct tension and vertical shearFlatness of the bearing plate and alignment of drilled holes
Primary steel frameHigh-strength beam clamps or forged wedge couplersSlip along structural members and localised bendingAbsence of axial play and controlled tightening with a torque wrench

Transferring vertical loads to the upper floors of the building requires strict coordination between construction site stakeholders. The scaffolding erector must not commence bracket erection without the structural load validation report issued by the civil engineer responsible for the primary structure.

Integrating this complex temporary structure requires managing the design lead time to be included in the overall works schedule. Drafting the structural report, obtaining validation from the client's structural engineer, conducting pull-out testing on concrete, and potentially fabricating bespoke anchoring components require rigorous anticipation well before equipment is brought onto the construction site.

  1. Dimensional survey and receipt of structural drawingsCollection of formwork and reinforcement drawings for the structural work to identify concrete areas capable of receiving load-transfer brackets without clashing with prestressing tendons or embedded building services.
  2. Structural calculations and force modellingPreparation of the structural calculation report in accordance with standard SN EN 12811, determination of support reactions, and submission of tie loads to the building engineer for prior approval.
  3. In situ pull-out tests and fastener validationPerformance of pull-out tests on sample anchors installed in the actual base material, in order to record the effective resistance of the through-bolts or bonded anchors in the site execution log.
  4. Erection of brackets and base transferLevel installation of steel transfer structures, locking of safety mechanisms, then erection of the upper scaffolding bays starting from this new intermediate support platform.

Managing load transfer discrepancies and erection stoppages

On high-rise scaffolding, any discrepancy observed between the assumptions in the structural report and actual site conditions requires an immediate halt to erection at the platform level concerned. Typical anomalies include encountering an unreinforced or cracked concrete shear wall where heavy anchors were planned, coupler play exceeding the tolerances permitted by standard SN EN 12811, or physical impossibility of installing the intermediate load-transfer bracket on the slab edge specified by the civil engineer.

  1. Securing the area and notificationThe team leader halts vertical progress, secures the ground exclusion zone, and posts an access prohibition sign on the scaffolding. The contractor applies art. 365 CO by informing the client that the host substrate exhibits a defect compromising the regular execution of the works.
  2. Joint inspection survey and revision of structural reportThe site foreman records precise dimensions of the defect (residual concrete thickness, pull-out strength via rebound hammer test or axial tensile test) and transmits the data to the appointed engineering office to recalculate standard buckling and load redistribution.
  3. Compensatory measures on siteFollowing written validation from the engineer, the team doubles up the tubular standards over the two lower lifts, installs ring-lacing using tubes and right-angle couplers, or adds supplementary transverse bracing to relieve the critical area.

Scaffold erection operations may only resume after the issuance of a technical addendum to the original structural report, initialled by the engineer responsible for the temporary works and the consultant for the primary structure. Any recorded stoppage periods are formally noted in the construction site minutes, with an official adjustment to the contractual erection schedule to prevent any rushed work detrimental to erector safety.

Frequently asked questions

What should be done if the facade concrete does not achieve the required strength to anchor load-transfer brackets?

The erector must immediately halt load transfer and notify the site management. The project's civil engineer must specify an alternative solution: through-bolting completely across the wall using internal spreader backing plates, or relocating the load-transfer bracket down to the lower level where the concrete has fully cured. Mechanical expansion anchors must never be forced beyond what is specified in the structural report.

How is the structural report adapted if the client decides to add micro-perforated sheeting during the works?

Adding netting drastically alters the wind drag coefficient under standard SN EN 12811. The design office must recalculate all horizontal and vertical forces. This alteration generally requires doubling the facade tie density, adding V-braced ties, and verifying that the intermediate brackets can withstand the increased dynamic component without risking platform uplift.

What lead time should be allowed for revising a structural report if an unforeseen obstacle appears on the facade?

An average of 5 to 10 working days should be anticipated, depending on the complexity of the changes. This includes the joint dimensional survey, computer modelling of the new forces by the scaffolding engineer, verification of support reactions by the building's civil engineer, and formal approval by the site management prior to any physical modification of the steel structure on the construction site.

Can the absence of an intermediate bracket be compensated for by reducing the spacing between standard ties?

No. Ordinary ties primarily resist horizontal forces perpendicular and parallel to the facade caused by wind. The exclusive function of the intermediate load-transfer bracket is to take up permanent and operational vertical loads to prevent base standards from buckling. Relocating or omitting a bracket strictly requires recalculating the load-bearing tubes, never relying on mere construction site guesswork.

Texts and standards cited

  • CO art. 365materials and site: the contractor is liable for the good quality of materials supplied; if materials supplied by the client or the ground designated by the client is found to be defective, or if any other circumstance compromises the regular or timely execution of the work, the contractor must immediately inform the client, failing which the contractor bears the consequences (para. 3).
  • CPviolation of the recognised rules of building work: whoever, in directing or executing a construction or demolition project, intentionally breaches the recognised rules of building work and knowingly endangers the life or limb of persons is liable to a custodial sentence not exceeding five years or to a monetary penalty; if committed through negligence, to a custodial sentence not exceeding three years or to a monetary penalty.
  • SN EN 12811Temporary works equipment - Scaffolds: performance requirements and general design for temporary working structures.