Tie grid: how many, where, and why none may be removed

Ties ensure overall stability and prevent the structure from overturning under wind loads. You will learn how to set out the exact grid defined in the technical instructions, how to increase tie density at edges and standards heads, and how to enforce absolute integrity of every attachment point against other trades.

Key takeaways

  • The tie grid is governed by the manufacturer's assembly instructions and standard SN EN 12811.
  • Standard spacing is generally arranged every two levels in a staggered pattern on internal standards.
  • Lateral edges and scaffolding heads require systematic tying at every deck level.
  • The removal of a tie by a third-party trade creates an immediate risk of progressive collapse.

Set out the grid according to the instructions and increase density at edges

On a facade scaffolding, transverse stability does not depend on chance or workshop habit. The layout of the fixings strictly complies with the manufacturer's technical instructions, calculated in accordance with the requirements of standard SN EN 12811. This European standard, applied in Switzerland, defines service loads, wind actions and the necessary structural verifications. The vertical standards must be connected to the load-bearing structure of the building to transfer pull-out and compressive forces perpendicular to the facade, as well as forces parallel to it.

In the standard zone of a closed facade without netting or sheeting, the standard configuration usually requires a tie point every two levels, meaning a vertical interval of four metres, arranged in a staggered pattern every two bays. This layout forms a regular grid that distributes forces across the entire steel frame. As soon as frames receive external hop-up brackets, debris nets or advertising sheeting, the windage area increases considerably: the instructions then dictate a reduction in spacing, which may require a tie at every level and on every vertical standard.

Increasing tie density concerns two critical zones subjected to maximum pull-out stresses: vertical edges and the top of the temporary structure. At the edge, the first standard located at the edge of the facade must be tied at every deck level, without applying a staggered pattern. This continuous line of attachment prevents the structure from peeling away under wind gusts sweeping across wall corners. At the scaffolding head, at the level of the top deck or the crown guardrail, the upper overhang experiences a direct leverage effect. Every inner and outer standard must receive a rigid tie there to prevent overturning outwards.

Minimum layout of tie points according to the zone of the structure
Zone of the scaffoldingStandard configuration without sheetingConfiguration with netting or sheeting
Central standard zone1 tie per 20 to 24 m² (staggered)1 tie per 8 to 12 m² according to structural analysis
Vertical edges (gables, corners)Every deck level (every 2 to 4 m)Every standard at every vertical level
Top level (scaffolding head)Every standard tied below the top deckEvery standard doubled with a rigid tie
Pedestrian walkways and openingsTies above bridging beamsReinforced banding according to structural engineer's analysis

Maintain the integrity of the grid and prohibit unauthorised dismantling

The network of ties forms an inseparable system. As soon as a tie rod, eye bolt or connecting tube is removed, the redistribution of tensile and compressive stresses overloads neighbouring points. This local loss of equilibrium leads to buckling of the standards under wind loads or irreversible deformation of the tubular frame. During the operational phase, scaffolders face repeated requests from painters, plasterers or external thermal insulation installers wishing to clear the working area.

Any person outside the scaffolding team is strictly prohibited from loosening a coupler, extracting an anchor plug or cutting a rigid link. In accordance with prevention principles, the employer must take the safety arrangements and protective measures that meet recognised technical rules, pursuant to art. 3 OPA. The mechanical stability of the temporary structure is the responsibility of the accepting scaffolder. Anyone deliberately altering this system jeopardises the safety of all trades working on the platforms.

  1. Analysis of the modification requestThe chargehand locates the fixing interfering with the facade works and checks permissible load transfers on the layout drawing.
  2. Installation of the compensatory fixingDrill and install a new temporary tie on the adjacent frame or the level immediately below, connected with a steel tube and two right-angle couplers.
  3. Removal of the initial componentUnscrew the interfering rod only after verifying the effective tightening of the compensatory point to the recommended torque.
  4. Final reinstatementAs soon as the work on the wall is completed, reinstall the final tie into the hardened substrate before releasing the temporary point.

Tie management requires flawless communication on the construction site. When handing over the handover protocol, the scaffolder explicitly records the ban on modifying the tie system. If a missing or sheared tie is detected during regular inspections, access to the affected sector must be locked off with red signage prohibiting its use. The scaffolding foreman incurs criminal liability pursuant to art. 229 CP, which penalises anyone who intentionally or through negligence breaches the recognised rules of construction and endangers the life of others.

Local deviation of the grid and load transfer via cross-ties

On a construction site, theoretical drilled holes defined by the manufacturer according to standard SN EN 12811 frequently encounter structural obstacles: large glazed surfaces, transom panels, blind boxes, or external thermal insulation components without load-bearing capacity. Moving a tie point without compensation impairs the overall resistance of the frame against positive and negative wind pressures. Load transfer must therefore be re-established using balancing tubular ties installed with compliant right-angle couplers.

Bridging or V-shaped tie assembly
Coupling assembly consisting of steel tubes and right-angle couplers, allowing tensile and compressive forces from a theoretically untieable standard to be transferred to two solid tie points drilled set back or into adjacent load-bearing areas of the structure.
Tie deviation configurations and approved compensations
Obstacle encounteredTechnical impossibilityCompensatory arrangementLoad transferred
Continuous ribbon glazingDrilling impossible in lintel or spandrelThrough-tubular frame or reveal tie clamped onto jambsDirect tension and compression
Surface-mounted louvre blindMasonry depth inaccessibleOffset to adjacent standard with horizontal tube reinforced with a double couplerLoad perpendicular to facade
Balcony without concrete return wallAbsence of solid wall opposite standardV-tie engaging two anchors under the upper slabCombined tension and shear loads
Re-entrant corner of facadeDirect access to concrete blocked by geometryBracing tube clamped across two standards with verified raked tieTransverse and longitudinal stability

The grid spacing specified in assembly manuals is never an indicative suggestion. When drilling cannot be carried out in line with a scaffolding node, the tie tube must be connected to the standard with a standard coupler as close as possible to the intersection of the standard, the transom and the ledger. If the distance between the tie coupler and the node exceeds twenty centimetres, a second coupler must be fitted to prevent potential slip, or a diagonal brace must lock out local bending of the standard under wind action.

Temporary removal protocol for finishing trades and reinstatement

Operations by finishing trades, particularly during insulation installation, rendering or flashings installation, often clash with scaffolding fixing points. Unilateral removal of a tie compromises the mechanical stability of the structure. The contractor executing the work must comply with the recognised rules of construction to prevent collapse, failing which their liability pursuant to art. 229 CP may be engaged in the event of danger to life or limb.

  1. Formal deactivation requestThe requesting trade submits a written request to the scaffolding erector or to the site management, specifying the affected standards and the expected duration of the hindrance caused by the tie.
  2. Installation of the temporary replacement tieBefore any work on the existing anchor, the erector installs a compensatory tie at the immediate upper or lower level, or on an adjacent bay, in accordance with the load-bearing capacities specified in the technical instructions.
  3. Clearance and treatment of the working areaThe original tie is dismantled by the qualified scaffolder. The artisan carries out their insulation or waterproofing works, leaving, if necessary, a sleeve opening for the reinstatement of the final tie point.
  4. Re-establishment of the grid and removal of the compensatory tieAs soon as the local task is completed, the erector reinstalls the final rod and eyelet, torques the coupler to the specified value, ensures proper bracing against the wall, then removes the temporary tie.

For rendering or painting works requiring full clearance of a facade, the erector uses reveal jacks or so-called flying ties alternated from floor to floor. The operation is always carried out in successive stages so as never to exceed the limit threshold of untied standards defined by the manufacturer's assembly instructions. Safety information and access restrictions must appear visibly on the scaffolding inspection tag located at the main access point.

Management of tie non-conformities and emergency shutdown

On a building construction site, discovering a missing or severed tie point calls into question the overall stability of the structure. Ties form a continuous network that transfers forces perpendicular and parallel to the facade, in accordance with the calculations of standard SN EN 12811. If an operative removes a connection to apply render or install a subframe without coordination, the affected zone experiences an uncalculated load transfer to adjacent points. The risk of standards buckling or overturning outwards under a wind gust becomes immediate.

  1. Immediate access prohibitionAs soon as a compromised grid is observed, close off access to the affected level and upper platforms using physical barriers and explicit signage.
  2. Formal notice to site managementNotify the defect in writing to the site supervisor or to the site management, recording the precise location and nature of the observed alteration.
  3. Compliant reinstatement or deviationSummon the scaffolding team to re-establish the severed tie or install a replacement tie with triangulated load transfer to adjacent standards, in accordance with the assembly instructions.
  4. Inspection prior to reopeningCheck that couplers are torqued to specification, test anchor resistance, and lift the access restriction on the inspection log.

Frequently asked questions

What should be done when an artisan has removed a tie to work on the facade?

Access to the affected scaffolding section must be locked off immediately using a chain or a prohibition notice. Notify the site supervisor and summon the qualified scaffolding team. Only a scaffolder may reconstruct the connection or install a triangulated replacement assembly connected to neighbouring nodes, in accordance with the manufacturer's technical specifications and the rules of standard SN EN 12811.

Why do the manufacturer's instructions require more ties on edge standards?

The extremities of the scaffolding experience vortices and wind pull-out forces that are significantly higher than those in the central zone of the facade. Technical instructions therefore prescribe a systematic increase in tie density along edges and at the top of the structure. Neglecting this closer grid spacing exposes the structure to rapid torsional deformation, which can lead to a progressive pull-out failure of adjacent ties during severe weather or persistent bise winds.

How can the tie grid be adapted when facing a wide glazed opening?

When drilling into the solid substrate is impossible directly opposite an opening, the instructions permit a local deviation. The load must be transferred to lintels, reinforced concrete spandrels or lateral reveals. To compensate for the lack of a direct point, scaffolders install reinforcing tubes and horizontal diagonal braces, creating a triangulated beam that redistributes loads to the tied nodes.

Can a painter or a proofer install a temporary tie themselves?

No. The finishing trade has neither the qualification nor the authorisation to modify the structure of a working scaffolding. The location, the choice of the appropriate anchor plug for the base material, compliance with tightening torque and the geometry of tie tubes are exclusively the responsibility of the CFC scaffolding erector. Any improvised modification engages the liability of the executing company in the event of damage or failure.

Texts and standards cited

  • SN EN 12811Temporary works equipment - Scaffolds: Performance requirements and general design
  • OTConstorganisation of occupational health and safety: the employer designates on each construction site a competent person responsible for occupational safety and health protection, who is authorised to issue directives to workers (para. 1); any person who, through their conduct or condition, exposes themselves or endangers other persons must be expelled from the construction site (para. 2)
  • CP art. 229breach of the recognised rules of construction: whoever intentionally breaches the recognised rules of construction when directing or executing a construction or demolition work, and thereby knowingly endangers the life or physical integrity of persons, shall be liable to a custodial sentence not exceeding five years or to a monetary penalty; in the case of negligence, to a custodial sentence not exceeding three years or to a monetary penalty