🧱 CFC 212Erector safety and co-activity on the construction siteChapter 6 of 10 in the section

Coactivity on scaffolding: who uses it, who alters it, who is liable

On a French-speaking Swiss construction site, several trades follow one another or coexist on the same façade scaffolding. You will learn how to secure shared use in writing, lead technical coordination between trades, enforce the strict ban on any alteration without the scaffolder's approval, and onboard new operatives.

Key takeaways

  • Making scaffolding available requires a written protocol specifying authorised loads and access routes.
  • Any modification of load-bearing components or guardrails by a third-party user remains strictly prohibited.
  • Weekly coordination allows decking to be adapted without compromising the stability of the structure.
  • Systematic briefing of newcomers prevents dangerous practices and the unauthorised removal of ties.

Formalising shared use and coordinating site interventions

On construction or heavy refurbishment construction sites, façade scaffolding serves bricklayers, plasterers-painters, tinsmiths, blind installers, and joiners successively or simultaneously. Without rigorous organisation, this shared structure becomes a major source of technical defects and contractual disputes. The scaffolder provides equipment conforming to a specific load class and in a layout determined with the site management. For this structure to maintain its integrity, the transfer of operational responsibility must be clearly documented right from acceptance of the work.

In accordance with art. 3 OTConst, works are planned such that the risk of occupational accidents, occupational illnesses, or damage to health is kept as low as possible, with site-specific measures stipulated in the works contract. For the scaffolding contractor, this involves drafting a shared-use handover protocol countersigned by the client or site management and the user site foremen. This document specifies the maximum permissible load on the working decks, the approved access levels, and the prohibition of overloading.

Coordination between contractors is not limited to signing an initial handover sheet. During weekly technical meetings held with the site management, the scaffolding chargehand must review intervention schedules. If façade specialists install external thermal insulation requiring an extended bracket or if tinsmiths need to lift box gutters, these needs must be notified at least one week in advance. Anticipating this avoids improvised adjustments that jeopardise the overall safety of the site.

  • Checking alignment between the structure's load class and materials stored by trades.
  • Scheduling selective removal of netting or sheeting based on external plastering progress.
  • Arbitrating access to temporary staircases to prevent congestion during peak hours.
  • Joint inspection of the general condition of decking and toeboards after each structural work phase.

Enforcing the no-alteration rule and briefing newcomers

The fundamental rule on any Swiss construction site remains absolute: scaffolding must not be touched. A user, whether a painter, roofer, or subcontractor, is under no circumstances permitted to remove a brace, loosen a coupler, detach a toeboard, or unscrew an anchor tie on the grounds that it interferes with their façade work. As soon as a structural component or edge protection is dismantled without calculations or authorisation, the overall stability of the structure is compromised and the fall hazard is immediate.

The employer complies with art. 5 OTConst by appointing a competent person for occupational safety and health protection on each construction site who is authorised to issue directives to workers, noting that anyone who endangers other persons through their behaviour must be dismissed from the construction site. If an operative removes a guardrail to pass a pallet of windows through without restoring the protection, the scaffolder must document the incident in writing, barricade the area, and alert the site management to enforce this measure.

Roles and responsibilities matrix on in-service scaffolding
Action on the structureThird-party tradeScaffolder (CFC 212)
Relocating an obstructing tieStrictly prohibited from interferingInstalling a compensatory tie before transfer
Removing a guardrail for material loadingProhibited without written authorisationInstalling a swing gate or safe loading bay
Cleaning working decksDaily cleaning obligationVisual inspection during maintenance rounds
Installing additional sheeting or nettingUnilateral attachment strictly prohibitedVerification of wind loads prior to installation
  1. Displaying the user notice boardPlace a visible sign at the base of each staircase or access ladder stating the maximum load, inspection date, and scaffolder's emergency phone number.
  2. Safety induction for incoming operativesBrief incoming chargehands on their very first day to remind them of the strict ban on modifying scaffolding components.
  3. Establishing the joint inspection recordInspect the structure with the newcomer prior to their access to the decks to document any pre-existing damage.
  4. Immediate reporting of defectsInstruct every worker on the obligation to report immediately if a loose guardrail or deformed anchor tie is observed.

Systematic briefing of newcomers constitutes the final line of defence against operational errors. Temporary workers or specialist installation crews are often unaware of the structural constraints of the tower or façade line. By delivering a concise ten-minute site safety induction, backed by an attendance sign-off sheet, the scaffolding contractor protects its equipment and ensures each operative works on a safe platform without compromising that of others.

Traceability of maintenance inspections and recording damage

As soon as standing scaffolding accommodates several trades simultaneously—plasterers-painters, waterproofers, tinsmiths, or blind installers—the structural integrity deteriorates under the impact of material handling and repeated traffic. The scaffolding contractor remains responsible for maintenance of the structure throughout the hire period specified in the works contract. To prevent disputes over the origin of defects, the scaffolding supervisor logs every periodic inspection in a construction site inspection register, countersigned with the site management.

Maintenance inspection and defect traceability schedule
Component inspectedCommon defect observedSafety consequenceImmediate action required
Wall ties and base jacksAnchor bolt unscrewed or tie tube removed to install insulationLoss of wind stability and risk of bay overturningRestoration by the scaffolder and entry in the site record
Edge protectionIntermediate rail or toeboard removed to pass sheet metalworkMissing fall protection breach for subsequent usersImmediate refitting with locking pins and warning to the contractor at fault
Decks and trapdoorsAccess hatch propped open or deck board overloadedRisk of tripping through the hatch opening or load failureClosing the access and clearing excess stored materials
Netting and sheetingDebris netting slashed to feed through a materials hoistFalling tools and debris towards ground-level transit routesReplacing the damaged roll at the expense of the responsible contractor

When a user contractor reports damage that occurred during their shift or finds a guardrail dismantled upon arrival, access to the affected area must be suspended without waiting for the weekly inspection round. The scaffolding chargehand carries out remedial work as soon as notice is received from the site management. Under art. 5 OTConst, the employer appoints a competent person on each construction site responsible for occupational safety and health protection, capable of issuing instructions to workers; anyone who, through their behaviour or condition, endangers themselves or others must be dismissed from the construction site.

Handover of levels, phased dismantling, and scaffolder liability

The end of a construction site involves a progressive departure of teams. Often, façade specialists complete their rendering on the top level while painters are still finishing the base walls and metalworkers install permanent guardrails on balconies. Partial dismantling of scaffolding must never be improvised: it alters the load path distribution and exposes lower levels that remain in service. The level release protocol formalises the end of use by secondary trades and authorises the scaffolder to begin phased dismantling.

  1. Notification of area releaseThe site management confirms in writing that trades have cleared their equipment, removed debris, and swept the decks of the topmost operational level.
  2. Joint inspection record of site conditionThe scaffolding chargehand and site manager ensure no residual materials remain on the frames and confirm that the façade presents no obstruction for dismantling.
  3. Securing access to levels due for dismantlingInstalling a physical barrier with a red prohibition sign at the base of access hatches below the targeted level, preventing any third-party personnel from entering.
  4. Systematic dismantling and tie recalculationDismantling component by component from the top level downwards. Anchors are released only as standards are struck down, never anticipating lower levels.

The scaffolder retains technical liability for elements left in place for remaining trades. Under OTConst, requirements for peripheral guardrails mandate a top rail with an upper edge at least 100 cm above the working surface, at least one intermediate rail, a toeboard of at least 15 cm, and a maximum gap of 47 cm between components. If the residual configuration can no longer provide these statutory dimensions during partial dismantling, the structure must be closed off and locked out against any use until fully removed.

Managing breaches, formal notice, and safety shutdowns

On a construction site involving multiple trades, unauthorised tampering with a temporary structure constitutes a breach of the commitments agreed in the written shared-use protocol. When a team of plasterers, tinsmiths, or painters removes ties, disengages braces, or removes a rail to ease pallet transit without prior coordination, the scaffolder must never accept the fait accompli.

  1. Immediate inspection and recordingDocument the damaged area with dated photographs. Identify the contractor working on the affected bay and record missing structural elements in the scaffolder's daily log.
  2. Physical isolation of accessImmediately close the compromised bay or level using a rigid prohibition barrier. Display an explicit red prohibition sign indicating that the scaffolding is out of service.
  3. Written notice to site managementIssue a suspension of use notice to the site management and the responsible contractor. State that the structure is declared unsafe for use until reinstated by the scaffolder.
  4. Remediation and clearance of reservationsIntervene solely with qualified scaffolding personnel to refit or replace missing components. Reinstate the inspection protocol prior to reopening.

Under art. 3 OTConst, works are planned such that the risk of occupational accidents, occupational illnesses, or damage to health is kept as low as possible, and site-specific measures are specified in the works contract. Furthermore, art. 5 OTConst provides that the employer appoints a competent person on each construction site responsible for occupational safety and health protection who is able to issue directives to workers, noting that anyone endangering others must be dismissed from the construction site.

Frequently asked questions

Can a contractor remove a top rail to deliver materials to a level?

No. Removing a guardrail or handrail by another trade is strictly prohibited without prior agreement. If a bulky delivery requires a temporary opening, the request must be submitted during the coordination meeting. Only the qualified scaffolder performs the temporary modification and installs mandatory compensatory protections before restoring edge protection immediately after the operation.

What should be done if a façade contractor removed anchor ties without notice?

The scaffolder or chargehand immediately shuts down the affected area. Access is physically barricaded with formal prohibition signage. The incident is reported in writing to the site management to summon the contractor at fault. The scaffolder reinstates the structure at the responsible party's expense. The structure may only be put back into service after a full re-inspection and sign-off in the inspection register.

How is the use of scaffolding formalised across multiple contractors?

The site management and users sign a handover protocol drawn up at acceptance of the work. This document defines the permissible load class, restates the absolute no-alteration rule, and details daily operating instructions. Every new contractor arriving during the project must countersign this document prior to accessing the working platforms.

Who is responsible for briefing new subcontractors arriving on the construction site?

The incoming trade's employer must instruct their own employees and subcontractors before starting work. They rely on the site safety plan and the scaffolding usage protocol provided by the site management. This safety induction reiterates the prohibition against modifying scaffolding, the maximum permissible loads, and the designated access routes.

Texts and standards cited

  • OTConst art. 3planning of construction work: works are planned such that the risk of occupational accidents, occupational illnesses, or damage to health is kept as low as possible; site-specific measures are stipulated in the works contract.
  • OTConst art. 5organisation of occupational safety and health protection: on each construction site, the employer designates a competent person responsible for occupational safety and health protection, who is able to issue directives to workers; anyone who endangers other persons must be dismissed from the construction site.