Key takeaways
- The counterweight offsets the rated load and the outreach according to a strict safety factor.
- Each ballast block must be tared, calibrated, and mechanically locked onto the rear jib stem.
- The independent safety wire rope passes through an automatic fall arrester with self-locking jaws.
- The static and dynamic test at ground level validates the winches and brakes prior to lifting.
Jib stability calculation and securing of roof counterweights
Anchoring a suspended platform relies on the strict balance of moments between the suspension over the void and the rear framework on the roof. The jib acts as a lever on a fulcrum formed by the front support. The scaffolding erector must know the maximum working load of the cradle, the self-weight of the structure, winches, and wire ropes, as well as the exact lengths of the front outreach and the rear wheelbase. Any calculation must include a safety factor against overturning of at least 3, in accordance with technical rules for temporary suspended platforms.
Counterweights must never be improvised with salvaged materials from the construction site, such as bricks, opened bags of cement, or water drums prone to leaks. Only manufactured ballast blocks, stamped with an engraved, indelible unit mass, are permitted. The blocks must be stacked on the rear pin of the jib and secured by a through-safety pin, locked with a padlock or a locknut. This mechanical locking prevents any unintentional removal or shifting of the weights under the effect of operating vibrations and wind.
| Front outreach | Rear wheelbase length | Load per suspension point | Minimum counterweight mass per jib |
|---|---|---|---|
| 0.80 m | 2.40 m | 500 kg | 500 kg |
| 1.20 m | 2.40 m | 500 kg | 750 kg |
| 1.50 m | 3.00 m | 500 kg | 750 kg |
| 1.50 m | 2.00 m | 500 kg | 1125 kg |
The roof bearing surface requires careful verification to prevent crushing of the waterproofing membrane or thermal insulation. Timber baulks or distribution sole plates of adequate thickness must be placed under the front and rear baseplates. According to art. 3 OPA, the employer shall take protective measures complying with recognised rules of technology to prevent accidents. The erector must therefore obtain confirmation from the building's technical manager regarding the allowable slab load before any tensioning of the wire ropes.
Fall arrester, secondary safety wire rope and test protocol before commissioning
Each end stirrup of a motorised suspended platform must receive two separate and independent wire ropes: the suspension wire rope, driven by the traction hoist, and the passive safety wire rope, passing through the automatic fall arrester. This secondary wire rope remains slack during normal operation, but is constantly ready to arrest the cradle or platform deck should the main wire rope break or the reduction gear fail mechanically.
- Blocstop / Automatic fall arrester
- Mechanical safety device traversed by the independent safety wire rope, fitted with a clamping jaw system. It instantly locks onto the wire rope as soon as the descent speed exceeds a critical threshold or the longitudinal tilt of the platform deck exceeds the permitted limit.
- Visual inspection of wire ropes and anchoragesExamine the suspension wire rope and the secondary wire rope over their entire working length. Check for the absence of broken strands, birdcaging deformations, kinks, or oxidation. Check the tightness of thimbles and wire rope grips at the head eyelet on the jib.
- Installation of the safety wire rope and arming of the fall arresterThread the safety wire rope into the fall arrester casing mounted on the hoist stirrup. Align the line of drop vertically without friction against slab edges. Place a tensioning weight at the bottom of the secondary wire rope to ensure correct guidance through the jaws.
- Manual trip test of the locking mechanismOperate the fall arrester test trigger or lever to verify the immediate snap-shut of the retaining jaws onto the dry wire rope. Reset the mechanism manually according to manufacturer specifications before electric operation.
- Static and dynamic test at ground levelLoad the platform with the increased rated test load on the ground. Raise the cradle to 20 centimetres above the ground to verify brake holding performance, the absence of abnormal jib deflection, and the rigid seating of the locked counterweights.
The user may only allow personnel into the cradle after an acceptance report has been issued. Art. 229 CP punishes anyone who breaches the recognised rules of construction and endangers human life. This penal framework serves as a reminder of the severity of omitting ballast or skipping a test. Dynamic tests must also validate the proper operation of the automatic anti-tilt sensor: if the platform tilts by more than a few degrees, the downstream fall arrester must lock to halt the travel and prevent occupants from slipping.
Roof layout and mechanical locking of the suspension
Anchoring a suspended platform requires a thorough analysis of the roof supporting structure prior to fitting any component. The scaffolding erector checks the load-bearing capacity of the slab or main beams intended to support the jib spreader plates. A roof waterproofing membrane cannot directly bear concentrated loads without the insertion of appropriate timber baulks or steel spreader plates. The front arm of the jib must project over the edge of the building without making contact with the parapet or flashing, thereby preventing any parasitic shear force transfer onto a non-structural element.
Counterweights cannot consist of makeshift materials such as sandbags, bricks, or water containers prone to evaporation or rupture. Only original precast ballast blocks, calibrated and stamped with an indelible nominal value, are permitted on the jib cradle. Each block must be slid onto the retaining bar and secured with a locking pin or padlock to prevent any unintentional removal by third parties.
- Verification of the presence of the end stop and locking pin on the counterweight support bar.
- Installation of rear triangulation tiebacks connected to a structural anchor point of the structural work if specified for the jib.
- Spirit-level check on the horizontal beam to ensure that the suspended load applies a strictly vertical load on the jib head.
- Provision of a safe access zone for maintenance personnel at the roof edge with installation of the required collective protection measures.
The employer shall organise work on the construction site in accordance with art. 3 OPA in order to implement protective measures complying with recognised technical rules. This requirement specifically dictates that the calculated bearing loads under the jib levelling jacks must be validated prior to applying the cradle's live load.
Wire rope connections, fall arrester inspection, and load testing
The kinematic safety of a suspended cradle relies on absolute independence between the motorised drive system and the emergency arrest mechanism. Each suspension stirrup receives two separate galvanised steel wire ropes, free of broken strands, kinks, or flattening. The traction wire rope runs through the traction hoist, whilst the safety wire rope runs completely through the automatic fall arrester mounted above the motor casing.
The mechanical fall arrester operates on the principle of centrifugal clamping jaws or inertia levers. In the event of a traction wire rope break or overspeed during descent, the internal jaws instantly clamp onto the secondary wire rope to bring the platform deck to a halt without producing abrupt deceleration destructive to the platform framework. An anti-tilt sensor also cuts winch controls if the deck tilts beyond the manufacturer's threshold.
| Component inspected | Inspection method | Immediate acceptance criterion |
|---|---|---|
| Traction wire rope | Visual and dimensional using callipers | Nominal diameter complied with, sound core, no kinks or broken wires within a lay length |
| Safety wire rope | Manual pull and pass-through in the housing | Absence of excessive grease, end weight intact, straight run under tension |
| Automatic fall arrester | Manual tripping using test lever | Immediate locking of jaws onto the wire rope with no observable slippage |
| Roof ballast blocks | Count and weight verification against calculation sheet | Total weight compliant, mechanical locking in place, locked cotter pins |
| Motor brake | Emergency stop under proof load at ground level | Instantaneous stop without millimetric drift or slippage under load |
- Preliminary suspension at ground levelLoad the platform with test weights representing the rated working load increased according to technical specifications, then lift the assembly to 20 centimetres above the ground to settle the slings and check jib reaction.
- Verification of counterweight footingsAccess the roof to examine the behaviour of the spreader plates and verify that there is no lift-off whatsoever of the rear supports under the effect of the lever arm.
- Rope-break simulation and emergency tripManually trigger arrest on the secondary wire rope according to the machine manual procedure to confirm the effectiveness of the mechanical locking under load.
- Recording in the inspection logComplete the equipment inspection register with the joint signatures of the qualified erector and the construction site manager before issuing the handover certificate.
Carrying out these checks and installing protective equipment complies with the recognised rules of the trade. In accordance with art. 229 CP, whoever intentionally breaches the recognised rules of construction and knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or to a monetary penalty; this sanction also applies in the event of negligence in the form of a custodial sentence not exceeding three years or a monetary penalty.
Managing suspension anomalies and emergency decommissioning
On a suspended platform, any mechanical anomaly observed on the suspension or winch requires a strict shutdown protocol. When a fall arrester trips without apparent cause or abnormal slippage occurs on the suspension wire rope, the site foreman suspends operations immediately. In accordance with art. 3 OPA, the employer shall take protective measures complying with recognised technical rules to prevent accident risks.
- Immediate safeguarding of personnelErectors in the cradle attach their fall arrest lanyards to independent anchor points or await stabilised rescue if the platform deck shows an abnormal tilt. Under no circumstances must any attempt be made to force open the fall arrester housing under load.
- Lockout of controls and visual inspectionIsolate the main power supply at the roof electrical distribution board to prevent any inadvertent operation. From the roof terrace, the foreman checks the seating of the jibs, the integrity of the ballast locking pin, and the alignment of the steel wire ropes.
- Assisted evacuation and equipment shutdownIf the platform cannot reach the ground or a safe landing by emergency manual descent, organise evacuation in accordance with the site rescue plan. Lock out the winch with a lockout padlock and post a warning notice strictly prohibiting its use.
Return to service requires intervention by a competent person responsible for safety, in accordance with OTConst. Following replacement of defective parts and verification of counterweight masses, a new test report is drafted and signed before any work stations are reoccupied.
Frequently asked questions
How should one respond if the automatic fall arrester trips abruptly during descent?
Descent controls must be halted without straining the motor. Give a brief upward pulse to take tension off the safety wire rope and relieve the clamping jaw of the fall arrester. Check that the cradle deck is level: excessive tilt trips the centrifugal mechanism. If the blockage persists or the wire rope is pinched, initiate the rescue procedure without tampering with the internal components of the mechanism.
What should be done if unexpected displacement of the jib counterweights is observed on the roof terrace?
Immediately lock out the winches at the distribution board and stop platform operations. Evacuate the cradle if it is resting on the ground, or tie it off to the façade to eliminate tensile forces on the jib. Reposition the counterweight blocks according to the layout plan, verify the overturning stability factor, then securely lock the through-retaining rod with its safety pin before any further testing.
What is the procedure if the safety wire rope frays or exhibits broken wires?
The platform must be lowered to the ground or secured on fixed supports to remove all load. Access to the temporary structure must be locked out with warning notices. Replace the entire safety wire rope reel with a wire rope compliant with the suspended platform manufacturer's specifications. Reinsert the wire rope into the automatic fall arrester, adjust the bottom tension when slack using the ballast weight, and carry out a functional test.
How is the fall arrester trip test carried out before resuming work?
The test is conducted with an empty platform, less than one metre above the ground or a solid landing floor. Manually actuate the quick-release lever or simulate suspension wire rope failure according to the manufacturer's instruction manual. The jaw must instantaneously arrest the safety wire rope without slippage exceeding the stopping tolerance. Reset the mechanism, inspect the wire rope surface, and record the test on the commissioning sheet.
Texts and standards cited
- OPA art. 3protective measures and installations: the employer shall take the protective arrangements and measures that meet the provisions of the ordinance, other applicable occupational safety provisions, and recognised rules of safety technology and occupational medicine.
- OTConstorganisation of occupational safety and health protection: the employer shall designate on each construction site a competent person responsible for occupational safety and health protection, who is able to issue instructions to workers (para. 1); any person who, through their behaviour or condition, endangers themselves or others must be removed from the construction site (para. 2).