Key takeaways
- Art. 17 OTConst requires specific protective measures at exposed workstations and passageways.
- A rigid protective fan must withstand material impacts and effectively deflect falling items.
- A toeboard of at least 15 cm and safety netting retain small hand tools.
- The erector is liable for damage caused to third parties by defective or incomplete equipment.
Technical protective devices: protective fans, toeboards and safety netting
During the erection or use of a façade scaffolding, the areas located beneath workstations or along public access routes present a high risk of falling materials, rubble or hand tools. Art. 17 OTConst requires measures to be taken at workstations and passageways so that workers and the public are not endangered by falling objects or materials.
To fulfil its role, the protective fan must be dimensioned to withstand the impact of a heavy item or a load falling from upper levels. It is built using heavy timber planks or rigid metal decks assembled without gaps, sloped towards the façade to prevent materials from rebounding onto the public highway. When the structure overhangs a pavement or a building entrance, this protective screen must cover the full recommended passageway width and be fitted with a side enclosure.
| Equipment | Primary role | Installation specifications |
|---|---|---|
| Protective fan | Intercept heavy objects and free-falling materials | Solid rigid decking, sloped towards the building, dimensioned according to working height. |
| Protective toeboard | Prevent equipment from sliding at working floor level | Minimum height of 15 cm, securely fastened with no gap to the scaffolding deck. |
| Safety netting | Contain flying rubble and small hand tools | Fitted taut on the outer face, mesh size suited to the type of work being performed. |
Protection at source relies on the systematic installation of the toeboard on every working level. In accordance with the Construction Works Ordinance, the toeboard must have a height of at least 15 cm and fit tightly against the decking to prevent the passage of a bar, a hammer or rubble. In addition, installing safety netting or a micro-perforated tarpaulin stretched over the outer face of the structure retains projections generated during repointing, rendering or grinding work.
Liability towards third parties and erector's safety obligation
The scaffolding erector assumes direct liability for the stability and compliance of the collective protection elements provided. When scaffolding overhangs the public highway or private access routes, a failure in securing a protective fan or the absence of a toeboard can cause substantial property damage or severe injuries to members of the public.
Under art. 229 CP, anyone who, intentionally or through negligence, breaches the recognized rules of construction when directing or executing building work, and thereby endangers the life or physical integrity of persons, is liable to criminal penalties.
Swiss Criminal Code
In addition to the criminal liability of the site manager or operative on the construction site, the Code of Obligations (CO) governs the civil consequences of damage caused to others. A company that hands over a temporary structure that is incomplete or does not comply with the rules of the art risks having to compensate all losses caused to third parties affected by a falling object.
- Analysis of the passageway zoneIdentify pedestrian flows, building entrances and traffic beneath the scaffolding before defining the extent of the protections.
- Erection and anchoring of the assemblyAssemble the protective fan and secure the netting or reinforced toeboards directly to the load-bearing structure according to the manufacturer's manual.
- Inspection upon acceptanceCheck the continuity of the protective fan, the absence of gaps between components and the secure fit of joints before commissioning.
- Maintenance and daily monitoringRegularly inspect the condition of nets and clear away debris accumulated on protective fans to prevent overloading.
Technical implementation of protective fans and retaining toeboards
Above circulation routes and construction site access points, the mere presence of a standard guard rail is not enough to guarantee the safety of people walking at ground level. Falling tools, bolts, hammers or masonry debris represent a critical hazard. Art. 17 OTConst requires specific layout measures to be implemented at workstations and passageways to prevent workers and third parties from being endangered by falling objects or materials.
To block projections at source, the scaffolding toeboard acts as a continuous barrier at floor level. According to art. 22 OTConst, the toeboard must have a height of at least 15 cm. In areas with a high risk of falling objects, such as above a public pedestrian walkway or a building entrance, a reinforced toeboard or fully sealed decking (gap-free junction between packing pieces and standards) is required to prevent small equipment from sliding through.
| Equipment | Main function | Installation and erection criteria |
|---|---|---|
| Protective fan | Intercept falling heavy or bulky objects above access points | Minimum projection suited to the passageway clearance, continuous gap-free decking, slope directed towards the façade. |
| Reinforced toeboard | Prevent tools and equipment from sliding along the decking floor | Minimum height of 15 cm under art. 22 OTConst, fitted tight against standards with no bottom gap. |
| Safety netting | Catch small debris, bricks and flying rubble | Close mesh secured to the structure, fitted in addition to external guard rails. |
The protective fan constitutes a cantilevered structure capable of absorbing the impact of an object falling from a substantial height. The erector must ensure that the fan has strong, tight-fitting decking, securely anchored to the vertical scaffolding standards. The slope of the fan decking must direct debris towards the façade and not outwards onto the public passageway.
Combination with netting and erector's liability towards third parties
When hacking off, grinding or render demolition works are carried out at height, the protective fan and toeboards are supplemented by close-mesh safety netting over the full height of the bay. This netting prevents rubble from dispersing outside the scaffolding footprint and protects the public highway below.
- Analysis of the passageway zoneIdentify pedestrian access routes, building entrances and traffic lanes beneath the temporary structure prior to starting erection.
- Installation of basic protectionsInstall regulatory toeboards of at least 15 cm and verify the absence of free gaps between the deck and the structure.
- Erection of the protective fanFasten the outrigger arms and fit the sealed deck of the fan above the passageway, ensuring that all anchorages are locked.
- Netting installation and inspectionTension the safety net over the outer face of the scaffolding and record the compliance of the assembly in the handover inspection report.
In addition to strictly applying the rules of the art of building, the scaffolding company must coordinate its measures with site management. If the construction site overhangs the public domain, pavement diversions or sealed pedestrian tunnels complete the installation to eliminate any risk of property damage or personal injury to third parties.
Incident management and scaffolding erector liabilities
On a building construction site, material or a tool falling from a façade scaffolding onto a passageway represents a critical risk for members of the public and site workers. When the containment system fails or an incident occurs, the scaffolding erector must react immediately by stopping work and securing the ground perimeter to prevent any secondary accidents.
In accordance with OTConst, measures must be taken at workstations and passageways to prevent workers from being endangered by falling objects or materials. If personal injury or property damage occurs as a result of the absence or defective erection of protective components, the site manager faces penalties under art. 229 CP for breach of the rules of the art of building. The erector's vigilance extends to continuous checks that components remain firmly in place.
- Emergency cordoning of the passagewaySecure the drop zone with physical construction site barriers and stop work on the upper levels of the scaffolding.
- Technical inspection of the installationExamine the condition of the fan anchorages, the tension of the safety netting and the fixing of reinforced toeboards to identify the point of failure.
- Reinstatement and recordingReplace damaged components, retighten connections and record corrective actions in the inspection report before authorising the reopening of the passageway.
Frequently asked questions
How do you size a protective fan above a public highway?
Sizing the protective fan depends on the working height of the scaffolding and the width of the underlying passageway. The fan must cover the entire circulation zone with sufficient projection to intercept the falling trajectory of materials. The structure must withstand foreseeable impacts and be combined with tight decking supplemented by close-mesh safety netting.
What is the difference between a standard toeboard and a reinforced toeboard?
A standard toeboard has a minimum height of 15 cm to retain small objects lying on the deck. A reinforced toeboard offers a higher profile or increased rigidity to withstand higher mechanical stresses and prevent heavy equipment from sliding over the edge. It acts as the primary containment barrier at the base of the scaffolding edge protection.
Who is responsible for maintaining the protective fan during construction site use?
The scaffolding erector hands over a compliant, formally inspected structure. During the operational phase, the general contractor or subcontractors working on the scaffolding must ensure that the structure is not altered. In the event of damage or accumulation of heavy debris on the fan, the designated competent person for safety must arrange for cleaning or repair.
Does safety netting replace the requirement for a toeboard?
No, safety netting in no way replaces a toeboard. The toeboard is a mandatory rigid component of façade scaffolding edge protection to stop objects from sliding at foot level. Netting acts as supplementary protection over the full height of the frame or beneath the fan to catch small hand tools or flying masonry debris.
Texts and standards cited
- OTConstprotection against collapse of construction elements or falling objects and materials
- CP art. 229breach of the rules of the art of building