Key takeaways
- The tinsmith bracket is installed at eaves level to make work at the verge and eaves safe.
- The top rail of the guard rail must project above the fall point in accordance with regulatory heights.
- The clear width of the platform ensures tradespeople can pass and materials can be laid down.
- For pitches exceeding 60 degrees, work is carried out exclusively from suspended or mobile elevating work platforms.
Positioning at the eaves and statutory protection dimensions
Erecting a tinsmith bracket or catch scaffolding aims to create a continuous physical barrier at the roof eaves. Laying out the uppermost working lift must be planned as early as marking out the façade scaffolding structure, ensuring the platform height allows the operative to work at chest height on the eaves strip whilst maintaining effective fall protection.
Appropriate measures must be taken to prevent falls where the drop height exceeds 2 m (tinsmith bracket and/or perimeter guard rail depending on roof pitch); on roofs with a pitch greater than 60°, work is carried out solely from scaffolding or a mobile elevating work platform (para. 3).
art. 41 OTConst
To ensure this safety, the projection height of the guard rail above the roof edge is strictly governed. According to art. 26 OTConst, the top rail of the façade scaffolding must project at least 80 cm above the edge of the highest fall-risk area; this increases to 100 cm if the guard rail is less than 60 cm from the edge.
| Distance from guard rail to eaves | Minimum top rail projection | Required components |
|---|---|---|
| Less than 60 cm | 100 cm above the edge | Top rail, intermediate rail, 15 cm toe board |
| 60 cm or more | 80 cm above the edge | Top rail, intermediate rail, 15 cm toe board |
Adapting the catch device to the roof pitch
The pitch of the roof slope directly alters the mechanics of a fall and the path of an object sliding down the roof. The steeper the pitch, the higher the impact speed against the edge protection. The scaffolder must adapt the type of vertical screening or safety net fitted to the scaffolding accordingly.
- Low-pitch roofs (up to 25°)Installation of a standard tinsmith bracket fitted with a three-part guard rail (top rail at 1 m, intermediate rail, 15 cm toe board) or an enclosed protection frame.
- Medium and steep pitch roofs (25° to 60°)Mandatory provision of a continuous catch screen (close-mesh net or reinforced wire mesh) securely fixed to the scaffolding standards to catch materials and brake a sliding person.
- Very steep roofs (over 60°)Direct work on roof slopes without a load-bearing structure is prohibited. The scaffolder erects a suspended platform or provides dedicated access points; work is carried out exclusively from the scaffolding.
Construction details and sizing of the tinsmith bracket
Erecting a tinsmith bracket complies with strict geometric requirements to catch any operative or material sliding down the slope effectively. According to art. 41 OTConst, appropriate measures must be taken at roof edges to prevent falls where the drop height exceeds 2 m. To perform its catching function, the tinsmith bracket working platform must have a minimum clear width of 60 cm (corresponding to width class W06 in scaffolding erection). The vertical position of the bracket platform is just as critical: the catch platform must not be installed more than 1 m 50 below the level of the roof eaves, limiting the kinetic energy generated during a fall.
The horizontal distance between the scaffolding structure and the edge of the roof framework or underlay must be checked precisely when installing brackets. Excessive spacing would eliminate the catching effect. As a rule, the cantilever bracket must be adjusted so that the inner edge of the scaffold deck sits as close to the façade as possible whilst clearing rafters and gutters. If the gap exceeds 30 cm, installing inner guard rails or infill decking becomes mandatory to ensure deck continuity.
| Erection parameter | Statutory value / Tolerance | Construction site check point |
|---|---|---|
| Maximum height decking/eaves | Max. 1.50 m | Adjust the uppermost vertical bay to prevent excessive height differences. |
| Clear walkway width (bracket) | Min. 0.60 m (class W06) | Keep the walkway clear of any stored gutters or tiles. |
| Clear gap between edge/eaves and bracket | Max. 0.30 m without protection | Install infill decking or an inner rail if the gap increases. |
| Catch guard rail height | Min. 1.00 m above decking | Calculate height from the walkable surface of the tinsmith bracket. |
Catch solutions for steep pitches and rear wall installation
The roof pitch directly dictates adaptation of the catch device. For moderate pitches (up to 25° to 30°), combining a standard three-rail guard rail on the upper walkway platform may suffice if the eaves geometry allows. As soon as the pitch exceeds 30°, the risk of a person sliding off the slope and over ordinary rails increases significantly. In this case, the scaffolding must be equipped with a solid catch screen or close-mesh safety net (continuous rear wall) secured to the perimeter guard rail.
- Wind load assessment on the rear wallAdding a safety net or solid sheeting to the tinsmith bracket increases wind resistance. The erection team must double the scaffolding ties on the upper standards before fitting catch components.
- Erecting eaves brackets and extension framesFix the cantilever brackets at the intended height below the eaves, then install the scaffold standards designed to receive the catch guard rail.
- Installing edge protection and checking the toe boardFit the safety net or wire mesh without gaps. Ensure that the toe board of at least 15 cm is in place to stop tinsmith parts or tiles from sliding off.
- Handover check and taggingCheck the upper anchorage, ensure there are no gaps between roof and catch screen, then attach the handover tag granting access to tinsmiths and roofers.
Managing installation discrepancies and bringing devices into compliance
On the construction site, matching the actual geometry of the roof timbering with the scaffolding structure frequently reveals critical non-conformities at the eaves edge. The most common mistake involves setting the top working level to a theoretical floor height, creating an excessive vertical step to the gutter or too large a horizontal gap to the fascia board. When this geometric offset compromises catch effectiveness or prevents direct access to metalwork, the scaffolder must intervene before any access is granted to following trades.
- Finding and prohibiting accessAs soon as poor positioning at the eaves or an opening exceeding tolerances is identified, close off access to the lift concerned using a barrier rail and warning notice.
- Level adjustment via bracketsInstall offset inner brackets or readjust right-angle couplers on the standards to set the platform to the exact height below the eaves edge, maintaining the required clear width.
- Adapting the guard rail or netExtend the tubular standards to raise the wire-mesh rear wall or safety net to catch anyone sliding down the slope.
- Signing off snags and handover sheetRecord modifications in the daily inspection log and sign off handover of the structure to the tinsmith or roofer.
When added roof insulation thickness pushes the roof plane upwards or outwards, the platform must be widened using cantilever brackets anchored to the frames. The contractor then applies CO, notifying the client without delay if an unforeseen structural change compromises the compliance of the protection.
Frequently asked questions
What should be done if the eaves overhang prevents erecting the scaffolding close to the wall?
The top lift should be widened using cantilever brackets projecting towards the façade. The scaffolder adjusts the deck position below the eaves to maintain the clear width needed for tinsmith work, whilst limiting any residual gap against the gutter. Additional ties counteract overturning forces caused by this cantilever at the top of the scaffolding.
How is the protection adapted if the roof pitch changes from 25° to 40° during re-roofing?
Changing the roof pitch requires adapting the catch device. Above 30°, a simple perimeter guard rail will no longer retain an operative sliding across battens. The scaffolder must install a continuous rear screen or a safety net fixed to heightened standards, ensuring reliable interception right at the eaves line.
What gap tolerance is permitted between the tinsmith bracket and the gutter?
The horizontal gap between the inner edge of the decking and the fascia board or gutter must be kept to the practical minimum for the tinsmiths. Any gap wider than a scaffold board requires installing infill decking on brackets or a rigid bridging plate. Under no circumstances may the gap become a trapping or fall zone.
Can the tinsmith bracket be used to store tiles?
No, a tinsmith bracket is sized primarily as a workstation and a catch zone at the roof edge. Stacking pallets or dense packs of tiles on it introduces unintended point loads on the brackets and blocks safe passage. Heavy material storage requires dedicated structural calculations and loading bays.
Texts and standards cited
- OTConst art. 41measures to be taken at roof edges: appropriate measures to prevent falls where drop height exceeds 2 m (tinsmith bracket and/or perimeter guard rail depending on roof pitch); on roofs with a pitch greater than 60°, work solely from scaffolding or a mobile elevating work platform (para. 3)
- COmaterials and ground: the contractor is liable for the sound quality of materials supplied; if materials supplied by the client or the ground specified by them are found to be defective, or if another circumstance compromises the proper or punctual completion of the work, the contractor informs the client immediately, under pain of bearing the consequences (para. 3)