🧱 CFC 212Anchorages, stability and wind resistanceChapter 9 of 10 in the section

Façades Without Anchor Points: Glazing, Cladding, and Load Transfer

Faced with a glazed façade, fragile cladding or a historic facing, drilling directly into the substrate is prohibited. This chapter details alternative methods for stabilising façade scaffolding: ballast sizing, installation of raking shores, reveal-clamping anchors, and the regulatory process for written validation.

Key takeaways

  • Anchoring to a fragile façade requires a specific stability study to compensate for the absence of wall plugs.
  • Base ballasting and bracing using raking shores resist wind overturning forces.
  • Window-reveal anchoring utilizes the building's internal structure via struts and pads.
  • Any derogation from standard anchors requires a written measure validated with a specialist under the OTConst.

Anchoring without wall ties: raking shores, ballasting, and window reveals

When the building envelope does not permit the insertion of mechanical or chemical anchor plugs — a frequent case on fully glazed façades, thin cladding systems, or listed heritage elements —, the scaffolder must implement alternative load-transfer solutions. Tensile and compressive wind forces must be transferred to the structure through other mechanical means to ensure the overall stability of the scaffolding.

Comparison of stabilisation solutions without façade drilling
TechniqueOperating principleExecution constraintsPrimary use
Raking shoresInclined tubular struts shoring the structure to the groundLarge ground footprint, requires a stable foundation surfaceLow height, clear zones at the base of the building
Base ballastingConcrete blocks added at the base to counter overturningVerification of the bearing capacity of the slab or groundFree-standing towers, low-height scaffolding without openings
Window-reveal reveal tieClamping with clamps or struts across the window openingsRequires openable windows and joinery protectionBuildings with accessible windows, internal/external renovations

Window-reveal anchoring consists in clamping the concrete wall or the lintel through an open window using scaffold tubes fitted with struts and screw jacks. Softwood packing pieces or elastomer pads must be inserted between the steel and the structure to prevent damage to joinery frames or reveals. This method provides rigid resistance to tensile and compressive forces.

Ballasting and raking shores are used when the façade has no usable openings. Counterweight calculations must incorporate the surface area exposed to regional wind loads, the possible presence of protective nets or sheeting, and the total height of the assembly. For complex assemblies, the cost of engineering and dedicated equipment represents an item to be budgeted for from the tendering phase, typically in the region of 1,500 to 4,000 CHF depending on the scale of the structure.

Regulatory framework and formal validation by a specialist

Where it is technically not possible or too dangerous to erect an edge protection barrier, a façade scaffolding, a safety net, or a catch scaffolding, equivalent protective measures must be taken and laid down in writing with the assistance of an occupational safety specialist.

art. 29 OTConst

The application of art. 29 OTConst imposes a strict protocol whenever the standard anchoring pattern defined by the scaffold manufacturer cannot be applied to the letter. The absence of anchor points embedded in the load-bearing substrate alters the load distribution within the tubular structure. The scaffolder must not improvise a ballasting or bracing layout without prior technical justification.

  1. 1. Identification of standard anchoring impossibilityIdentify fragile areas (glazing, composite panels) precluding any drilling during the technical site visit.
  2. 2. Engineering study and dimensioningHave the specialist determine wind reaction forces, required ballast weights, and the layout of raking shores.
  3. 3. Establishment of the written protocolFormalise the equivalent protective measure in a document drafted and signed in accordance with safety requirements.
  4. 4. Erection and joint inspection handoverErect the structure according to the specific plan and carry out the written handover inspection of the assembly prior to making it available for use.

If bracing sheeting or advertising banners are used on scaffolding stabilised by ballasting or raking shores, wind loading is substantially increased. The competent person designated by the employer must inspect the condition of connections daily, ensure that ground ballast blocks have not slipped, and check that window-reveal struts maintain proper tension.

Constructive solutions without drilling: raking shores and ballasting

When the façade substrate consists of insulating glazing, fragile sandwich panels, or demountable cassette cladding, installing mechanical anchors by direct plug fixing is prohibited. The scaffolder must resort to autonomous stabilisation systems that transfer compressive and tensile loads away from fragile surfaces.

Transferring loads via raking shores and ballasting represents the primary alternative. The scaffold frame is widened at the base by means of inclined members bearing on the ground or an external slab. This arrangement converts the overturning moment caused by wind into compressive loads transmitted to the ground and tensile forces counteracted by concrete counterweights.

Comparison of stabilisation solutions without direct wall ties
TechniqueBearing zoneRequired componentsConstruction site constraints
Base ballastingBase of the scaffolding on load-bearing groundCalibrated concrete blocks, safety clamps, tie tubesLarge footprint, verification of ground bearing capacity required
Inclined raking shoresGround or receiving external slabBracing tubes, swivel couplers, sole platesHigh lateral footprint at ground floor level
Window revealInternal slab or concrete wallThrough-tubes, protective timbers, clamping screw jacksReserved for openable windows or removed frames

Counterweights must be rigidly connected to the structure using demountable couplers complying with assembly standards and steel tubes to prevent any sliding under wind gusts.

Window-reveal ties and the role of the specialist

Window-reveal ties consist in passing bracing tubes through the window opening to secure the scaffolding to the internal slab or an internal load-bearing wall. Timber pads of hardwood must be provided to protect frames and sills against local indentation.

This solution demands meticulous care during erection: screw jacks bear on both sides of the reveals or directly on the rough surfaces of the concrete slab. Clamping force must be controlled to prevent deforming the window frame if it remains in place.

  1. 1. Assessment and concept by the specialistA structural steel engineer or an occupational safety specialist analyses wind loads, self-weight of the structure, and drafts the calculation note certifying scaffold stability.
  2. 2. Preparation of openings and protective measuresPlacement of spreader timbers and protective foam at window frames to distribute tube pressure without damaging weatherproofing surfaces.
  3. 3. Erection of the internal clamping assemblyFastening of transverse tubes locked against the inner face of the building's load-bearing structure using adjustable ledgers.
  4. 4. Recording and inspection handover reportDrafting of the written validation document required by the construction work ordinance, signed by the site foreman and the engineer, incorporating the layout plan for ballasting or clamped reveals.

Any configuration change during the construction site operations requires an immediate update to the anchoring document detailing specific measures. The site supervisor must keep the written justification on the construction site, readily available for inspection bodies.

Managing unforeseen issues and failures of non-standard anchors

On the construction site, erecting scaffolding in front of fragile or glazed façades exposes the erection crew to structural failures or buildability issues. When a window-reveal tie proves impossible due to a stuck window sash, or when a raking shore lacks ground footprint, the site foreman must apply an emergency stoppage and immediate securing procedure.

In accordance with art. 29 OTConst, when it is technically impossible or too dangerous to install standard anchoring or standard edge protection, equivalent protective measures must be defined and laid down in writing with the assistance of an occupational safety specialist. Under no circumstances must the scaffolder improvise a makeshift anchor on a fragile component such as an aluminium window frame or lightweight composite cladding.

  1. Finding and cordoning offStop scaffold erection on the unbraced bay and secure the perimeter at ground level.
  2. Specialist consultationConsult the structural engineer or qualified specialist to validate an alternative (increased ballast, additional diagonals, or adapted reveal clamping).
  3. Written validationRecord the modified measure in the site diary and on the scaffold drawing before resuming work.

Frequently asked questions

Can a scaffold raking shore bear directly on laminated glass?

No, this is strictly prohibited. Glazing, even laminated or reinforced, is not a load-bearing element capable of resisting horizontal wind push or suction loads. The raking shore must be anchored securely to the ground or rest on a verified concrete or steel structure, without transferring any direct mechanical stress to the glazed surface or its frame.

How do you size ballast for free-standing scaffolding without wall ties?

Ballast sizing depends on the height of the structure, the wind-exposed surface area, and the presence of netting or sheeting. It must be covered by a rigorous stability calculation prepared by an engineer or specialist. Ballast blocks must be weighed, identified, and mechanically clamped to the base of the structure to prevent sliding.

Who must draft the written protective measure under art. 29 OTConst?

Drafting is the responsibility of an occupational safety specialist or an engineer specialising in structural steelwork/scaffolding, in collaboration with the site management. This written document describes the chosen substitute solution (ballasting, raking shores, window reveals), its structural calculations, and specific erection and inspection instructions.

What should be done if a window-reveal tie damages a window frame?

A reveal tie must always incorporate timber spreader packing or synthetic pads to prevent direct steel-to-joinery contact. If damage occurs, the scaffolder halts installation of that anchor, takes photographic records with the site supervisor, and obtains approval for reinforced protective packing before re-tightening the clamping jacks.

Texts and standards cited

  • OTConst art. art. 29 OTConstother fall protection measures: equivalent protective measures laid down in writing with a specialist