🧱 CFC 212Anchorages, stability and wind resistanceChapter 2 of 10 in the section

Anchor pull-out test: how many to test and how to record it

On an old or heterogeneous façade, scaffolding anchorage does not rely on a simple visual assessment. This chapter details the pull-out testing method using an on-site dynamometer: representative sampling to inspect depending on the substrate, proof load to apply without damaging the system and drafting the test report recorded in the technical file for the works.

Key takeaways

  • The theoretical strength of an anchor plug guarantees nothing without direct measurement on an old substrate.
  • Standard SN EN 12811 governs the verification of the load-bearing capacity of façade fixings.
  • The minimum proportion of tested anchors adapts to the geological and constructive variability of the masonry.
  • The signed pull-out test report constitutes the technical proof of stability provided to site management.

Defining sampling and test load according to the masonry

On new reinforced concrete structures, the fixing manufacturer's data apply directly, provided that the drill hole diameter and embedment depth are respected. Conversely, on an old building constructed from molasse, hollow clay bricks or rubble stone laid in lime mortar, pull-out behaviour remains uncertain without in situ testing. Standard SN EN 12811 requires ensuring the overall stability of the temporary works, which entails validating the connection between the standards and the structural work.

Anchor fixings must be able to withstand the calculated tensile and compressive forces, taking into account the actual characteristics of the substrate material.

norme SN EN 12811

The scaffolding erector carries out non-destructive tests using a mechanical or hydraulic pull-out tester fitted with a calibrated pressure gauge. The proof load is maintained for a sufficient hold period to ensure there is no slippage or failure of the anchor breakout cone. When allowable wind loads and the scaffolding configuration require a specific load transfer, the proof load incorporates the safety factor specific to temporary fixings.

Indicative sampling rates depending on the type of substrate
Type of façade substrateMinimum proportion testedObjective of the tensile test
Sound, regular reinforced concreteFive percent of the pointsCheck torque and proper anchorage
Solid brick or dressed hard stoneTen percent of the pointsVerify the cohesion of mortar beds
Old masonry, rubble stone or hollow brickTwenty percent of the pointsIdentify failing adhesion pockets

If a single fixing fails or shows measurable displacement before reaching the target value, the affected zone is immediately rejected. The crew then adapts the method: using a through-bolt fixing, injecting a chemical anchor with a sieve sleeve suited to hollow materials, or increasing the overall density of the tie grid on the bay.

Conducting the pull-out test and recording the test report

The pull-out test is performed right at the start of erection on the first rows of ties installed. Waiting until the scaffolding reaches the eaves to check mechanical performance creates an immediate hazard for the workers assembling it and compromises construction site organisation.

  1. Setting up the pull-out testerPosition the pull-out tester perfectly in line with the eye bolt. The tripod load distribution plate must bear on a hard, stable surface, far enough from the hole so as not to restrain the potential breakout cone of the stone.
  2. Gradual tensioningOperate the screw or hydraulic cylinder to gradually increase pressure up to the specified pull-out value, without dynamic shocks or torsion on the threaded rod.
  3. Maintaining the load holdMaintain the required tension for at least sixty seconds. Simultaneously monitor the pressure gauge needle and the dial indicator to detect any potential creep.
  4. Depressurisation and visual inspectionRelease the hydraulic pressure. Check the condition of the eye screw, the absence of spalling in the receiving material and that the original tightening is maintained.

Each measurement is precisely recorded. The pull-out test report certifies the conformity of the temporary works under art. 3 OPA, which requires the provision of installations that comply with recognised technical rules. By documenting the actual strength of the fixing points, the erector demonstrates that the scaffolding can withstand wind pressure and suction.

This test report is systematically incorporated into the erection file and appended to the scaffolding handover inspection. It is kept until the structure is completely dismantled and held available for site management and safety inspectors. For the hire or calibration cost of the dynamometric pull-out tester, allow an outlay of around CHF 350 to 600 per operation, to be included in work preparation according to the principles presented on /soumissions/.

Interpreting results and managing anchor non-conformities

On-site pull-out testing is not a mere administrative formality: it validates the effective transmission of tensile and compressive forces between the tube framework and the receiving substrate, in compliance with the requirements of standard SN EN 12811. When the dynamometer applies the specified load to the eye bolt, no noticeable slippage or detachment of the expansion cone or injection sieve must be observed. The measured resistance must cover the design action multiplied by the partial safety factor adopted during the design of the tie layout.

If a single anchor point fails or slips under the proof load, the entire associated batch is declared non-compliant. The erector cannot simply relocate the failing fixing a few centimetres away: the failure reveals a structural weakness in the substrate (weathered hollow masonry, degraded mortar joint, carbonated concrete) or an unsuitable choice of anchor plug.

  • Immediate stoppage of erection progress in the affected zone until the tie principle has been re-qualified.
  • Systematic doubling of the inspection rate on adjacent points to determine the extent of the deficient zone.
  • Change of fixing technology: switching from a mechanical expansion plug to a chemical anchor with a longer injection sieve, or using heavy-duty concrete screws.
  • Increasing the density of the tie grid to reduce the unit load transferred per anchor, in agreement with the structural calculations.

Documentary traceability: archiving test reports and handover of works

The validity of the tests depends on the rigour of the tensile test report, which accompanies the inspection report before putting the scaffolding into service. The Construction Works Ordinance governs the obligation to deliver a stable, secure installation. The pull-out test report certifies that the fixing assumptions adopted during the design phase match the actual performance of the masonry or concrete façade.

Minimum data required on the pull-out test report
Item to be recordedTechnical detail requiredPurpose of inspection
Spatial referenceStandard number, deck level and façade concernedExact location on the layout plan
Substrate typeReinforced concrete, clay brick, calcareous sandstone, molasseVerification of tie method compatibility
Type of fixingBrand, drill hole diameter, effective embedment depthCheck on compliance with manufacturer recommendations
Target pull-out valueProof load defined from wind calculations (kN)Validation of the permissible threshold according to standard SN EN 12811
Behaviour under loadLoad maintained during the hold period (no play)Proof of absence of creep or substrate failure
Measuring deviceDynamometer serial number and calibration dateMetrological guarantee of the applied force

Once signed by the foreman or erection supervisor, the test report is appended to the construction site logbook and submitted to site management during formal handover. Traceability protects the scaffolding company should third parties subsequently intervene and modify or remove anchors without consultation. Under art. 365 CO, the contractor must notify the client of any circumstances that could jeopardise the proper performance of the works, which includes an anchoring substrate whose strength proves insufficient during preliminary measurements.

Corrective measures in the event of failure and escalation protocol

An anchor point that fails during tensile loading with the mechanical pull-out tester indicates a local weakness in the substrate or improper installation. When the strength required by standard SN EN 12811 is not achieved, the anchor is immediately deemed non-compliant. The scaffolding erector halts erection on the bay concerned. No attempt is made to retighten an expansion anchor that has slipped: any element that has moved in its borehole is permanently decommissioned.

  1. Decommissioning and doubling of testsDecommission the failing anchor and perform two additional tests on the immediately adjacent fixings located to the right and left along the same horizontal line.
  2. Installing a replacement fixingDrill a new hole at a minimum distance equal to twice the anchor depth, in order to remain outside the breakout cone of the substrate material.
  3. Adapting the anchoring principleIn the event of repeated failures in hollow brick or weathered rubble stone, replace the mechanical fixing with a chemical anchor using an injection sieve, or switch to a through-bolt anchor with an internal backing plate.
  4. Reporting to site managementNotify site management in writing if the building structure exhibits widespread weaknesses preventing the transfer of the wind loads specified in the erection plan.

Each observed failure, the identified cause and the location of the replacement anchor must be recorded on the test report kept in the construction site technical file. According to art. 365 CO, if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance arises which endangers the proper or timely execution of the work, the contractor must inform the client. The scaffolding cannot be released for use by other trades until all inspected points have successfully validated the allowable test load.

Frequently asked questions

What is the minimum proportion of anchors that must be tested for pull-out?

On homogeneous reinforced concrete masonry, an inspection rate of 5% of the anchor points is standard practice. On older masonry, hollow clay bricks or natural stone of varying density, this rate is increased to at least 10%. Sampling must cover all façades, imperatively including heavily loaded zones such as roof eaves, building corners and bottom-row ties.

What pull-out value must the dynamometer achieve during testing?

The test tension applied by the pull-out tester generally corresponds to 1.2 times the allowable working load defined in the scaffolding structural calculations, without exceeding the elastic limit of the eyebolt. For standard anchors on enclosed façades, the test force is typically between 3 and 5 kN. The load must be held for a minimum observation period to verify the complete absence of mechanical slippage of the anchor plug.

How should results be recorded on the inspection report?

The test report lists the date, the precise identification of the construction site, the type of plug and the drill hole diameter. Each tested point is located on a façade drawing with its identification number, the force in kilonewtons measured on the pressure gauge and visual validation of the substrate. The document also states the date of the last calibration of the pull-out tester. It is signed by the inspector and attached to the safety file.

What should be done when a wall provides no pull-out resistance at all?

If chemical anchors and expansion plugs fail due to cavities or friable mortar, the erector must resort to through-wall ties secured with threaded rods and spreader plates on the inside face of the walls. Where through-drilling is rejected by site management, the scaffolding structure must be modified: erecting free-standing towers, installing transom buttresses within window reveals, or dead-weighting the base.

Texts and standards cited

  • SN EN 12811Temporary works equipment - Scaffolding: performance requirements and general design
  • CO art. 365materials and ground: notice to the client if the ground or materials jeopardise execution