Foundations, rafts and buried structure protection: the execution reference framework
Aimed at site leading hands, foremen and site managers, this section guides the transition from the bottom of the excavation to the basement load-bearing structures. It brings together the practical execution rules for setting out strip footings, pouring waterproof rafts according to standard SIA 272, installing peripheral drainage, constructing durable retaining walls and carrying out complex underpinning without compromising the stability of adjoining structures.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
1.50 m
Maximum depth of an unsupported vertical excavation without battering
50 cm
Minimum clear width free of any storage at the edge of a shored excavation
50 mm
Standard minimum thickness of blinding concrete on formation level
0.5%
Minimum fall recommended for gravity flow in the perimeter drain
Technical scope: from earthworks to buried walls
Successfully executing a structure's infrastructure demands absolute rigour as soon as earthworks are handed over. This section covers all masonry and buried structural work falling under codes CFC 201 and CFC 211.0. It systematically covers the execution phases where concrete, reinforcement and the ground interact directly: preparation of the subgrade using blinding concrete, reinforcement of ground-bearing foundation slabs, execution of integral tanking in concrete with limited permeability, as well as the installation of peripheral drainage networks with their inspection chambers.
It also addresses geotechnical and structural interface issues: gravity or reinforced concrete retaining walls fitted with weep holes, wall elevations built from vibrated concrete shuttering blocks, meticulous treatment of construction joints and integration of load-bearing thermal breaks at the base of the facade. Finally, making urban excavations safe, crack-width monitoring and underpinning existing foundations using micropiles complete this field of expertise.
On the construction site, the boundary between heavy earthworks and masonry requires constant vigilance regarding trench wall stability. Site supervisory staff must ensure that earthworks comply with regulatory clearances and that excavation edges remain clear of any unplanned loads before reinforcement work commences.
Execution workflow: progressing from virgin ground to the wind and watertight structural work
Foundation management follows a strict construction sequence dictated by the load path and groundwater management. The ten chapters of this section are structured to guide the team step by step, from opening the party excavation to final validated backfilling.
- Step 1: Preliminary assessment and foundation bedsBefore taking any excavator bucket near a third party, chapters M2-10 and M2-06 detail joint surveys, installing crack gauges and underpinning using micropiles. As soon as the formation level is reached, chapter M2-01 secures the pouring of blinding concrete and the setting out and levelling of strip footings.
- Step 2: Waterproof raft and construction nodesChapters M2-02, M2-09 and M2-05 cover the general raft slab forming a tanking system (standard SIA 272). They show how to manage concrete pours without cracks, scabble hydraulic construction joint surfaces and integrate thermal breaks at the base of walls without creating structural weaknesses.
- Step 3: Vertical walls and retaining structuresChapters M2-07 and M2-08 regulate the elevation of retaining structures and shuttering block walls, specifying lift heights, concrete vibration and the mandatory installation of drainage weep holes.
- Step 4: Peripheral water management and backfillingChapters M2-03 and M2-04 finalise the infrastructure. They determine the minimum fall for the drain pipe at the foot of the wall, the watertight connection of inspection chambers, the mechanical protection of wall coatings and the visual inspection protocol prior to backfilling.
| Structure / Phase | Execution requirement | Technical reference |
|---|---|---|
| Unsupported excavation > 1.50 m | Mandatory suitable battering or engineered trench shoring | art. 68 OTConst |
| Top edge of excavation | Minimum clear strip of 50 cm to 1 m depending on shoring | art. 71 OTConst |
| Waterproof raft (tanking) | Low-shrinkage mix design, careful curing, hydrophilic swellable strips | standard SIA 272 |
| Structural reinforced concrete | Precise concrete cover, continuous vibration, crack limitation | standard SIA 262 |
| Drainage at the foot of foundation | Rigid perforated collector pipe on concrete bedding, minimum fall of 0.5% | standard SIA 272 |
🧱 Chapters in this section 10
Strip footing: blinding concrete, formwork and rebar placement
Master blinding thicknesses, reinforcement spacers and the precise alignment of footings under heavy loads.
Foundations, rafts and protection of underground structuresRaft foundation and tanking: watertightness achieved by the concrete itself
Successfully complete the pour of the waterproof concrete raft without through-cracks using strict hydration control.
Foundations, rafts and protection of underground structuresPerimeter drainage: collector gradient, inspection chambers and connection
Ensure the durability of the drainage system by mastering gradients, filter gravel and cleaning rodding eyes.
Foundations, rafts and protection of underground structuresWaterproofing a buried wall: upstand, mechanical protection and pre-backfill inspection
Secure vertical waterproofing membranes applied against earth before the excavation is permanently closed.
Foundations, rafts and protection of underground structuresThermal break at wall base: installation, continuity, and common errors
Eliminate thermal bridges at the base of walls while maintaining full transfer of vertical loads.
Foundations, rafts and protection of underground structuresMicropiles and soil grouting: underpinning an existing foundation
Secure the transfer of existing loads by drilling micropiles and controlled grouting beneath footings.
Foundations, rafts and protection of underground structuresRetaining wall: footing, back-wall drainage and weep holes
Balance earth pressures and prevent hydrostatic head build-up using properly located weep holes.
Foundations, rafts and protection of underground structuresShuttering blocks: filling, compaction and tie continuity
Ensure homogenous filling and full concrete cover of rebar in shuttering blocks without blow-outs.
Foundations, rafts and protection of underground structuresStarter bars and construction joints: preparing the joint surface
Prepare roughened construction joint planes ensuring perfect force transfer and watertightness.
Foundations, rafts and protection of underground structuresExcavation against an adjoining building: pre-works record and crack monitoring
Document the condition of neighbouring buildings and monitor crack opening to prevent any party wall disputes.