Foundations, rafts and buried structure protection: the execution reference framework

Aimed at site leading hands, foremen and site managers, this section guides the transition from the bottom of the excavation to the basement load-bearing structures. It brings together the practical execution rules for setting out strip footings, pouring waterproof rafts according to standard SIA 272, installing peripheral drainage, constructing durable retaining walls and carrying out complex underpinning without compromising the stability of adjoining structures.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

art. 68 OTConst

1.50 m

Maximum depth of an unsupported vertical excavation without battering

art. 71 OTConst

50 cm

Minimum clear width free of any storage at the edge of a shored excavation

norme SIA 262

50 mm

Standard minimum thickness of blinding concrete on formation level

norme SIA 272

0.5%

Minimum fall recommended for gravity flow in the perimeter drain

Technical scope: from earthworks to buried walls

Successfully executing a structure's infrastructure demands absolute rigour as soon as earthworks are handed over. This section covers all masonry and buried structural work falling under codes CFC 201 and CFC 211.0. It systematically covers the execution phases where concrete, reinforcement and the ground interact directly: preparation of the subgrade using blinding concrete, reinforcement of ground-bearing foundation slabs, execution of integral tanking in concrete with limited permeability, as well as the installation of peripheral drainage networks with their inspection chambers.

It also addresses geotechnical and structural interface issues: gravity or reinforced concrete retaining walls fitted with weep holes, wall elevations built from vibrated concrete shuttering blocks, meticulous treatment of construction joints and integration of load-bearing thermal breaks at the base of the facade. Finally, making urban excavations safe, crack-width monitoring and underpinning existing foundations using micropiles complete this field of expertise.

On the construction site, the boundary between heavy earthworks and masonry requires constant vigilance regarding trench wall stability. Site supervisory staff must ensure that earthworks comply with regulatory clearances and that excavation edges remain clear of any unplanned loads before reinforcement work commences.

Execution workflow: progressing from virgin ground to the wind and watertight structural work

Foundation management follows a strict construction sequence dictated by the load path and groundwater management. The ten chapters of this section are structured to guide the team step by step, from opening the party excavation to final validated backfilling.

  1. Step 1: Preliminary assessment and foundation bedsBefore taking any excavator bucket near a third party, chapters M2-10 and M2-06 detail joint surveys, installing crack gauges and underpinning using micropiles. As soon as the formation level is reached, chapter M2-01 secures the pouring of blinding concrete and the setting out and levelling of strip footings.
  2. Step 2: Waterproof raft and construction nodesChapters M2-02, M2-09 and M2-05 cover the general raft slab forming a tanking system (standard SIA 272). They show how to manage concrete pours without cracks, scabble hydraulic construction joint surfaces and integrate thermal breaks at the base of walls without creating structural weaknesses.
  3. Step 3: Vertical walls and retaining structuresChapters M2-07 and M2-08 regulate the elevation of retaining structures and shuttering block walls, specifying lift heights, concrete vibration and the mandatory installation of drainage weep holes.
  4. Step 4: Peripheral water management and backfillingChapters M2-03 and M2-04 finalise the infrastructure. They determine the minimum fall for the drain pipe at the foot of the wall, the watertight connection of inspection chambers, the mechanical protection of wall coatings and the visual inspection protocol prior to backfilling.
Summary of critical execution requirements for infrastructure
Structure / PhaseExecution requirementTechnical reference
Unsupported excavation > 1.50 mMandatory suitable battering or engineered trench shoringart. 68 OTConst
Top edge of excavationMinimum clear strip of 50 cm to 1 m depending on shoringart. 71 OTConst
Waterproof raft (tanking)Low-shrinkage mix design, careful curing, hydrophilic swellable stripsstandard SIA 272
Structural reinforced concretePrecise concrete cover, continuous vibration, crack limitationstandard SIA 262
Drainage at the foot of foundationRigid perforated collector pipe on concrete bedding, minimum fall of 0.5%standard SIA 272

🧱 Chapters in this section 10

Foundations, rafts and protection of underground structures

Strip footing: blinding concrete, formwork and rebar placement

Master blinding thicknesses, reinforcement spacers and the precise alignment of footings under heavy loads.

Foundations, rafts and protection of underground structures

Raft foundation and tanking: watertightness achieved by the concrete itself

Successfully complete the pour of the waterproof concrete raft without through-cracks using strict hydration control.

Foundations, rafts and protection of underground structures

Perimeter drainage: collector gradient, inspection chambers and connection

Ensure the durability of the drainage system by mastering gradients, filter gravel and cleaning rodding eyes.

Foundations, rafts and protection of underground structures

Waterproofing a buried wall: upstand, mechanical protection and pre-backfill inspection

Secure vertical waterproofing membranes applied against earth before the excavation is permanently closed.

Foundations, rafts and protection of underground structures

Thermal break at wall base: installation, continuity, and common errors

Eliminate thermal bridges at the base of walls while maintaining full transfer of vertical loads.

Foundations, rafts and protection of underground structures

Micropiles and soil grouting: underpinning an existing foundation

Secure the transfer of existing loads by drilling micropiles and controlled grouting beneath footings.

Foundations, rafts and protection of underground structures

Retaining wall: footing, back-wall drainage and weep holes

Balance earth pressures and prevent hydrostatic head build-up using properly located weep holes.

Foundations, rafts and protection of underground structures

Shuttering blocks: filling, compaction and tie continuity

Ensure homogenous filling and full concrete cover of rebar in shuttering blocks without blow-outs.

Foundations, rafts and protection of underground structures

Starter bars and construction joints: preparing the joint surface

Prepare roughened construction joint planes ensuring perfect force transfer and watertightness.

Foundations, rafts and protection of underground structures

Excavation against an adjoining building: pre-works record and crack monitoring

Document the condition of neighbouring buildings and monitor crack opening to prevent any party wall disputes.