Key takeaways
- Obtain the communal authorisation for increased use of public land before any bucket strike.
- Delineate a continuous pedestrian corridor with rigid barriers and access bevels for pushchairs.
- Install retro-reflective demarcation and autonomous warning lights for night-time visibility.
- Equip every worker with fluorescent clothing with reflective strips in accordance with federal regulations.
Obtaining the authorisation for increased use and securing the pedestrian pathway
Any opening of an excavation on a pavement, carriageway or public square exceeds common use and constitutes an increased use of public land. Before starting the excavation, the contractor or supervising engineer must imperatively submit a formal application to the communal technical department or the local trade police. This application specifies the schedule, exact ground footprint, proposed traffic diversions and temporary signage plans. Working without this formal approval exposes the company to an immediate work stop order by local authorities and directly engages the liability of the executing contractor.
When the trench blocks a pavement, creating an alternative pedestrian pathway becomes the earthworks crew's absolute priority. The temporary passage must provide a minimum clear width of one metre twenty to allow pushchairs to pass each other and ensure easy transit for persons with reduced mobility. If the route diverts pedestrians onto the carriageway, it is mandatory to insert heavy physical barriers, such as concrete barriers or modular plastic units ballasted with water, in order to prevent any vehicle intrusion into the pedestrian zone.
- Crossing footplates laid flush without steps, secured against slipping and fitted with a non-slip surface.
- Access ramps with a maximum slope of six per cent to connect pavement levels to the carriageway.
- Rigid, continuous barriers guiding visually impaired persons by means of a low kickboard detectable with a white cane.
- Total ban on storing spoil, equipment or cables across the corridor reserved for pedestrians.
Managing night-time signage, high visibility and third-party liability
As soon as dusk falls or in foggy conditions, the earthworks zone on the road network must be perfectly legible to prevent collisions. Passive demarcation relies on site road signs and barriers equipped with retro-reflective films appropriate for the road speed limit. This setup is supplemented by active lighting comprising flashing amber lights upstream of the construction site to signal the hazard, followed by continuous amber lights along the diversion corridor to channel traffic flow without dazzling drivers.
| Period | Required device | Site check |
|---|---|---|
| Daytime activity | Rigid barriers and road work warning signs | Check clearance gauge and maintain sign cleanliness |
| Night and adverse weather | Autonomous flashing amber lights at the head and continuous lights | Check battery life and cleanliness of reflectors |
| Weekends and shutdowns | Complete enclosure of the excavation and locked crossing footbridges | Surveillance patrol to detect any external damage |
In the immediate vicinity of an active carriageway or transport machinery, site personnel protection depends directly on visual conspicuity. In accordance with art. 7 OTConst, workers must wear high-visibility warning clothing comprising fluorescent materials for the daytime and retro-reflective strips for the night. Wearing these jackets, harnesses or trousers is mandatory as soon as the worker steps outside the protected welfare facilities area.
High-visibility warning clothing must be worn during work near means of transport such as construction plant or transport machinery, or near public roads (fluorescent high-visibility colour, retro-reflective strips).
art. 7 OTConst
Opening an excavation on the carriageway directly incurs liability towards third parties in the event of personal injury or property damage. If a barrier overturns due to wind or if a hole remains open without night-time lighting, the site foreman and the company can be prosecuted. In particular, art. 229 CP punishes anyone who, when directing or executing a construction, intentionally or through negligence breaches recognised building standards and knowingly endangers the life or physical integrity of persons. A daily closing inspection of the construction site must verify every beacon before crews depart.
Physical diversion devices and crossing management
As soon as an intervention requires the temporary closure of a pavement or cycle lane, transit continuity must be ensured without creating a zone of direct conflict with motorised traffic. Setting up a protected corridor requires the placement of continuous separator elements capable of resisting lateral displacement or accidental impacts, while guiding the most vulnerable users.
| Situation encountered | Required protective device | Crossing requirements |
|---|---|---|
| Pavement diverted onto carriageway | Concrete lane separators or anchored steel barriers | Minimum clear width of 1 m 20, bevelled non-slip ramp |
| Direct crossing of the excavation | Pedestrian footbridge with ribbed decking and solid rigid guardrails | Guaranteed load capacity for heavy pedestrian traffic, gap-free |
| Maintaining access for residents / businesses | Adjusted footbridge with side kickplates and corner closures | Firmly bedded placement preventing any tipping or unpropped overhang |
| Open excavation in stabilised verge | Rigid mesh barriers assembled with metal clamps | Setback of at least 50 cm from the edge of the trench |
Access footbridges placed over trenches must be secured against all sliding using stops or mechanical ground fastenings. Any gap between the footbridge and the approach surfacing creates an immediate trip hazard for the public. Rainwater flow beneath the temporary structure must remain unobstructed to prevent ponding or ice formation during winter periods.
Workstation layout and road safety coordination
Carrying out an open excavation on public space places machine operators and pipelayers in a dual-constraint environment: vehicle traffic on one side, and construction plant manoeuvres on the other. Strict separation between the plant operating zone and the area reserved for third parties governs the overall safety of the intervention.
In accordance with art. 7 OTConst, each worker operating near public roads or moving machinery must wear high-visibility warning clothing containing fluorescent materials and retro-reflective strips. This individual measure complements physical barriers but does not replace them. Excavator slewing zones, bucket working radiuses and aggregate unloading zones must be entirely confined within the barriered perimeter.
- Checking access points and visibility at shift startCheck alignment of retro-reflective beacons, cleanliness of optical surfaces and stability of base plates after overnight traffic exposure.
- Managing encroachments during deliveriesDeploy an equipped banksman to control road traffic as soon as a tipper truck reverses on the carriageway or manoeuvres outside the authorised footprint.
- Continuous cleaning of approaches and carriagewaySystematically scrape and sweep tracks of soil, mud or gravel to prevent loss of grip for two-wheelers and light vehicles.
- Full securing during daily site shutdownCheck mechanical locking of all barriers, activation of flashing or continuous beacons, and cover open pits with engineered decking.
Managing the interface between the construction site and third parties requires rigorous record-keeping in the site log. Any change in traffic layout, alteration to temporary traffic light timings or placement of heavy road plates must be subject to a dated visual inspection. This traceability documents the installations' compliance with directives issued by highways departments or local police.
Managing demarcation incidents, equipment failures and official reports on public land
As soon as a trench encroaches on public land, the company assumes direct custody of the temporary works. In the event of night-time damage, signage blown over by the wind or an accident involving a pedestrian, the site foreman's response must be immediate, methodical and traceable to limit management's exposure towards third parties.
- Emergency securing and restoring guidanceImmediately stop high-risk manoeuvres. Re-erect overturned heavy barriers, close gaps in the pedestrian pathway with solid panels and reactivate autonomous beacon lighting before any other task.
- Freezing the scene and joint factual recordPhotograph the condition of the devices from multiple angles: remaining pavement width, condition of crossing plates, active lighting, masking of existing permanent signage and visibility of guiding lights.
- Written log entry and technical department notificationRecord the event in the site log with exact time and weather conditions. In the event of damage caused to a third party or a major failure by a utility concessionaire, immediately inform local police and the communal highways department.
If the temporary pedestrian crossing becomes impassable due to mud accumulation or cold-mix asphalt settlement, the footbridge must be cleaned or repositioned without delay. When the authorised layout can no longer be maintained, an application for modification of increased use of public land must be requested from the communal authority.
Frequently asked questions
What should be done if vandals move the protective barriers over the weekend?
The site manager commissions a surveillance patrol or engages a security firm if the communal permit requires it. Upon discovering damage, they immediately re-erect the ballasted mesh barriers on their bases, document the condition with dated photographs, record the incident in the site log, and send prompt notice to the communal technical office as well as the local police station.
A pedestrian trips against the site demarcation: what is the emergency procedure?
The absolute priority is to provide first aid and alert emergency medical services if necessary. The site foreman then immediately secures the area without moving the equipment involved, takes precise photographs of the pathway, ground flatness, lighting, and signage. They record the identity of any witnesses and promptly submit a detailed factual report to management for notification to the company's third-party liability insurance.
Can the municipality revoke the authorisation for increased use without notice during excavations?
Yes, if the company fails to comply with the conditions set out in the decree, particularly regarding the clear width for persons with reduced mobility or the cleanliness of the surrounds. The communal authority may order an immediate halt to road works and demand backfilling or the installation of temporary steel plates at the contractor's expense if road user safety is compromised.
When must workers wear high-visibility clothing on a trench?
Under art. 7 OTConst, wearing fluorescent clothing fitted with retro-reflective strips is mandatory for anyone working in the vicinity of public roads or transport machinery. This requirement applies from the moment machinery is unloaded, throughout earthworks and until complete removal of road signage, by day and by night, to ensure early detection of workers by motorists.
Texts and standards cited
- OTConst art. 7high-visibility warning clothing: to be worn during work near means of transport such as construction plant or transport machinery, or near public roads (fluorescent high-visibility colour, retro-reflective strips).
- CP art. 229breach of the recognised rules of construction: whoever, in directing or executing a construction or demolition, intentionally breaches the rules of construction and knowingly endangers the life or physical integrity of persons incurs a custodial sentence not exceeding five years or a monetary penalty; through negligence, not exceeding three years or a monetary penalty.