🧱 CFC 201 / 211.0Load-bearing masonry: bricks, blocks and structural elementsChapter 8 of 10 in the section

Raising an Existing Masonry Wall: Bonding, Load Transfer and Substrate Verification

Raising a building involves validating the load-bearing capacity of the underlying structural work before laying any units. This chapter details carrying out intrusive investigations, the critical review of load takedown drawings provided by the civil engineer, the technical choice between toothing and chemical dowelling, as well as formal notification of reservations regarding the existing substrate.

Key takeaways

  • Intrusive investigations identify the exact wall composition and the condition of the bedding mortars.
  • The civil engineer must validate the load takedown before any work to raise the wall begins.
  • Chemical dowelling with reinforcing bars replaces toothing when courses are incompatible.
  • The formal notice of defects protects the contractor if the substrate presents structural weaknesses.

Assessing the existing load-bearing wall and integrating the load takedown

Before adding a storey on old masonry, the site foreman cannot rely solely on archival drawings. Carrying out an intrusive inspection opening is essential to determine the exact nature of the structure: cellular clay units, solid clay bricks, calcium silicate or precast concrete blocks. The actual thickness of the finished wall without its renders, the compaction of the bed joints and any degradation of the original binder must be checked. Areas under concentrated bearings, narrow piers and wall heads must undergo meticulous inspection to detect possible settlement cracks, diagonal shear cracking or traces of rising damp.

  1. Localised hacking of rendersExpose the wall face over a minimum area of 50 by 50 centimetres using a light chisel to expose the courses without destabilising the masonry core.
  2. Core drilling or brick samplingExtract a complete unit or drill cores to measure the bed depth, check for internal voids and identify the material class.
  3. Inspection of the top leveling courseClear away the wall crest down to sound, level masonry free of degraded mortar or residual bituminous felt.
  4. Submission of findingsRecord the measured dimensions, horizontal joint thicknesses and substrate homogeneity in the daily report submitted to site management.
Visual and mechanical inspection criteria for the substrate prior to upward extension
Inspected itemObserved defectConsequence for the projectAction on the construction site
Pointing mortarCrumbles under the point, sandyReduced load-bearing capacityRake out and repoint or install a padstone
Existing wall headAbsence of concrete ring beamLack of transverse tieFormwork for a reinforced distribution ring beam
Masonry unitsThrough-thickness vertical cracksAbnormal stress concentrationWork stoppage and immediate notice to the engineer
Overall geometryOut-of-plumb exceeding tolerancesEccentricity of new loadsCompensation measures specified by the structural engineer

Bonding masonries and formalising the notice of reservation

The transfer of shear and normal forces between the old wall and the upward extension requires a zero-play anchoring system. Two assembly methods are commonly applied in French-speaking Switzerland: traditional toothing or dowelling by resin-anchoring steel reinforcement. Toothing consists of partially demolishing every other unit along the wall head to engage the new masonry in a staggered pattern. This solution, which is heavy and risky for fragile modular brick masonry, is advantageously replaced by a reinforced concrete ring beam cast on a cleaned leveling course, supplemented by vertical dowels drilled into the substrate without percussion.

For dowelling, holes are drilled to the diameter specified by the anchor resin manufacturer, then cleared of dust by compressed-air blowing and mechanical brushing repeated at least three times. Injecting an approved injection mortar or hybrid resin secures deformed reinforcing bars anchored to the depth defined by the engineer's drawing. The bars must have a minimum concrete cover of thirty millimetres when casting the tie beam, ensuring perfect rigidity at the base of the new storey.

Formal notice of defects of the structure
Mandatory written notification by which the contractor notifies the client or site management without delay that a substrate defect compromises the proper execution or stability of the upward extension.
  • Draft the notice of reservation in writing, dated, with a copy to site management as soon as an anomaly is detected.
  • Systematically attach a precise photographic survey with a graduated rule and location on the plan.
  • Propose temporary protective measures, such as propping beneath the slab, without prejudging the final solution.
  • Suspend the erection of new walls on the disputed section until a formal site instruction validated by the engineer is obtained.

Intrusive investigations and verification of the load takedown

Before embarking on the construction of an additional storey, superficial visual inspection is not enough. The masonry team conducts localised intrusive investigations to determine the exact composition of the supporting wall: nature of the bond (cellular clay units, calcium silicate brick, random rubble stone or concrete blocks), presence of internal voids, quality of the laying mortar and state of degradation of the bedding courses. These inspection openings are cut with a light chisel or by wet core drilling to avoid destabilising the preserved courses.

Data recorded on site are transmitted without delay to the appointed civil engineering consultancy. The engineer recalculates the load takedown by incorporating the self-weight of the new walls, composite or reinforced concrete slabs, updated live loads, as well as horizontal forces due to wind and seismic actions in accordance with current structural standards. If the permissible stress below the existing top course is exceeded, strengthening measures are required: reinforced jacketing, injection of non-shrink cement grout into cavities, or casting spreader beams under specific bearing points.

Evaluation parameters for the existing substrate prior to upward extension
Inspected itemInspection methodConformity criterionCorrective action if defective
Top leveling courseLaser level and aluminium straightedgeFlatness and cohesion of render or concreteMechanical clearance and structural levelling mortar
Pointing mortarScratch / pick testingAbsence of crumbling or loss of cohesionRaking out joints and repointing with gauged mortar
Masonry coreThrough core drilling / cameraAbsence of unkeyed internal voidsLow-pressure micro-cement injections
Underlying foundationsTargeted exploratory trenchBearing on frost-free load-bearing ground without settlementUnderpinning or expanding resin injection

Bonding mechanisms and notification of the notice of reservation

Mechanical continuity between the old wall and the new upward extension cannot rely on simple mortar bed laying. Depending on the geometry and the shear forces to be transferred, two main methods compete on the construction site: traditional toothing or chemical anchor dowelling.

  1. Clearing and preparation of the laying planeDemolish degraded top courses, eliminate any traces of gypsum, bitumen or cement laitance. Clean dust from the surface with an industrial vacuum, then thoroughly wet the substrate to saturation prior to application.
  2. Execution of dowelled anchorsDrill holes using a rotary hammer drill set to rotary-only mode in hollow bricks. Brush and blow out with compressed air three times. Inject the approved epoxy or vinylester resin, then insert the deformed rebar cut to the lengths defined on the engineer's drawings.
  3. Forming recesses for toothingWhere the new wall meets an existing shear wall, cut every other course with a diamond disc cutter to a depth of 10 to 15 cm to create clean recesses for keying in the new blocks.
  4. Casting a ring beam or distribution padstoneInstall continuous reinforcement tied to the starter dowels and cast C25/30 concrete vibrated with an internal poker vibrator to uniformise load transfer across the full load-bearing thickness.

If the site foreman or the site supervisor notices structural anomalies during opening-up operations that were not shown on the drawings (through-thickness cracking, rising damp breaking down the binder, mismatched masonry lacking original tie beams), they must immediately suspend erection of the upward extension in the affected area. In accordance with art. 365 CO, the contractor immediately informs the client in writing when the ground or the provided substrate jeopardises proper performance of the works. The formal notice of reservation relieves the contractor of liability and makes resuming work on the construction site conditional upon technical approval of a remediation protocol by site management.

Managing structural contingencies and suspending upward extension works

On an upward extension construction site, discovering an existing wall that is degraded or does not conform to initial assumptions requires an immediate, methodical response. When preliminary demolitions or openings reveal heterogeneous masonry, powdery lime mortars or unrecorded through-thickness cracks, the chargehand suspends laying operations. No new load-bearing elements must be erected on a base whose residual load-bearing capacity remains uncertain.

  1. Securing and immediate stoppage of the zoneHalt pallet unloading and the delivery of materials to the wall head. Install temporary relief propping beneath upper slabs if parasitic load transfers are detected.
  2. Joint inspection record and complementary investigationsConvene site management and the civil engineer on site. Locally clear the leveling courses and joints to allow direct visual inspection of the bedding course and wall composition.
  3. Formal issuance of the notice of reservationSend a written notice without delay reporting substrate defects to the client, pursuant to art. 365 CO. Record geometrical discrepancies and the actual nature of the materials encountered.
  4. Resumption of work upon site instructionOnly proceed with casting a reinforced ring beam, dowelling anchors or laying blocks after receiving signed revision details from the engineer and acceptance of the remedial technical specification.

Adapting ties sometimes requires abandoning traditional toothing in favour of a continuous reinforced concrete ring beam or resin-anchored rebar under inspection. The site manager records each stage in the site logbook and ensures that curing and setting times for repair mortars are respected before transferring loads.

Frequently asked questions

How should one react if the investigation reveals a cavity wall without internal ties?

Laying must be suspended and the actual condition recorded in minutes. An untied cavity wall cannot support the vertical loads designed for a solid wall. The civil engineer must recalculate the load takedown and specify either mechanical coupling using chemically anchored stainless steel cavity ties or a reinforced concrete bearing padstone tying both leaves together before any resumption of blocklaying.

What should be done when tensile pull-out tests on chemical dowels fail in the existing wall?

Pull-out failure indicates a deteriorated substrate or an unsuitable hollow brick. The contractor suspends anchoring and issues a notice of reservation in accordance with the Code of Obligations (CO). The fixing must be modified by increasing the embedment depth, using suitable injection sleeves for perforated masonry, or creating a peripheral reinforced concrete ring beam acting as an overall load-distributing leveling course.

What approach should be taken if the client insists on progressing despite reservations?

Art. 369 CO discharges the contractor of liability if the client gives orders contrary to formal warnings. However, in the event of a danger of structural element failure, the site manager must refuse to proceed to prevent personal injury. He confirms his reasoned reservations in writing, documents the risks with photos and requests a formal instruction from site management.

Is toothing new masonry into existing masonry always feasible?

No. Toothing by cutting indentations often weakens old rubble stone or poorly consolidated fired-clay masonry. Repeated impacts from chiselling disrupt the underlying courses. In such configurations, the civil engineer generally recommends substituting destructive toothing with a vertical joint featuring chemically anchored steel dowels, combined with a sealing strip or non-shrink bedding mortar.

Texts and standards cited

  • CO art. 365Materials and ground: the contractor is liable for the good quality of materials supplied; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance compromises the proper or punctual execution of the work, the contractor shall immediately inform the client, on pain of bearing the consequences (para. 3).
  • CO art. 369Exclusion of the client's rights for defects in the work when the defective execution is personally attributable to him (orders given contrary to the contractor's formal warnings or any other cause).