🧱 CFC 201 / 211.0SUVA safety, health and workstation requirementsChapter 2 of 10 in the section

Excavation access: ladder, head extension and mandatory securing

After this chapter, you will know how to size, set out, and lock off every temporary access point in an excavation in accordance with the construction work ordinance. You will master the head extension rule, top and bottom anchoring techniques to prevent any overturning, as well as the geometric distribution of flights to guarantee immediate evacuation without improvisation.

Key takeaways

  • Every access ladder in an excavation must extend past the upper support edge by at least one metre.
  • Base chocking and top securing prevent lateral slipping or accidental unhooking.
  • The spacing between two access flights must never force a retreat of more than twenty metres.
  • The emergency access must remain clear at all times, without material storage or plant traffic.

Securing the flight: one-metre head extension and mechanical anchors

Improvised access to the bottom of the excavation represents the most frequent cause of serious trauma on structural work construction sites. The practice of climbing down an unstable slope, jumping from a berm, or placing an unsecured aluminium ladder against a raw face creates a direct hazard of crushing and overturning. Access to the workstation must be an integral part of construction site planning from the start of earthworks, to comply with the general prevention rules set out in art. 82 LAA.

The most critical point remains the moment when the bricklayer or earthworker steps over the crest of the excavation to place their feet on the first rungs. Without rigid extension of the stiles, the worker loses handholds, pivots into the void, and risks free-falling into the trench. The minimum extension of one metre above the upper accessible level provides a firm grip during the transfer of body weight. Removable ladder extensions or integrated access handrails eliminate the need to search for an unstable point of balance at the edge of the excavation.

  • Setting angle of the leaning ladder maintained strictly between 65° and 75° to prevent base kick-out or excessive bowing under load.
  • Mandatory top fixing using a ratchet lashing strap or scaffolding coupler secured to a deadman, a shoring section, or an embedded anchor.
  • Bottom blocking using all-terrain articulated feet, steel pins driven into the formation level, or a rigid base plate on a clean platform.
  • Absolute elimination of makeshift ladders made of battens nailed to formwork rafters, which lack certified strength.

Organising routes: access centres and evacuation corridors

Access management is not limited to the compliance of an isolated ladder. It meets the requirements of art. 17 OTConst, which mandates preventive measures at passageways and workstations to protect personnel. In a linear trench for pipework or in a shaft excavation, the distance to reach an exit point directly dictates the survival of teams in the event of sudden water ingress, burst pipework, or partial collapse.

Setting out and operating rules for temporary access points in excavations
Excavation typeMaximum distance between access pointsRecommended access provisionSecuring requirement
Narrow linear trench20 m walking distanceLeaning ladder heavily clamped at the topRigid securing to trench sheeting and bottom sole plate
Wide excavation / Earthworks25 m linear wall lengthSite stair tower or access flightAnchoring onto concrete slab or mooring pins
Shaft or blind chamber1 dedicated permanent access pointCaged ladder or suspended systemCertified double mechanical anchor point
  1. Prepare the upper landingCreate a clear, level access area stripped of all loose earth, located outside the travel path of dumpers and earthmoving excavators.
  2. Erect edge protection guardrailsInterrupt the perimeter collective protection only at the exact location of the ladder opening, fitted with a self-closing swing gate or retaining chain.
  3. Check the lower landing surfaceEstablish a horizontal, sound base free of mud pools and starter bars to ensure stable footing when stepping off.
  4. Record access points in the site journalCheck daily that straps have not loosened, inspect the condition of rungs, and verify general stability after any severe weather.

Installation requirements and top and bottom anchoring devices

Improvised access to the bottom of an excavation is one of the major causes of serious accidents on earthworks and masonry construction sites. Slipping of the ladder base or lateral overturning as the worker steps over the top of the structure represents the most frequent fall scenario. Rigorous application of best practice and the requirements of the construction work ordinance strictly forbids a simple ladder left freely leaning against a face or trench sheeting.

Extending the ladder head by at least 1.00 metre allows the worker to maintain three points of contact at all times when transitioning between the flight and natural ground or the working platform. This extension serves as a handrail to step over the edge without losing hip balance. Where the configuration does not allow the ladder stiles to be raised to this height, installing rigid tubular extensions or access grab handles secured to the load-bearing structure is mandatory.

Recommended securing methods according to excavation type
Excavation contextDevice at ladder headDevice at ladder baseInstallation check
Steel box trench shoringPurpose-made welded or bolted hooks with retaining bracketsArticulated anti-slip feet chocked on raft slab or timber bearerCheck anti-uplift locking under load
Soldier pile wall or micropilesClamping brackets on HEB steel section or clamped scaffolding tubeSteel ground pins driven into footing head or hard groundAbsence of lateral play under firm manual pull
Battered excavation in soft groundHead secured by ratchet lashing strap to two spaced steel picketsHorizontal load-spreading board and pins driven into the trench bedMeasurement of the angle of inclination between 65° and 75° with a spirit level

Setting out, spacing of escape routes and maintaining clearance

In the event of a partial collapse, burst water pipe, or sudden ingress of water or gas, evacuation speed governs the survival of teams at the bottom of the excavation. According to OTConst, work must be planned so that the risk of accident is as low as possible, which requires sizing emergency routes from the site preparation phase. Providing only a single ladder at the end of a long trench traps bricklayers in a deadly dead end.

  • Distance between two access points: install a secured access point every 20 to 25 metres at most along a trench or linear excavation.
  • Maximum retreat distance: ensure that no worker is more than 12 to 15 linear metres away from an immediate exit provision.
  • Crest outlet: reserve an obstacle-free zone of at least 50 cm for a shored face, in accordance with OTConst.
  • Continuous maintenance: immediately clear earthwork spoil, rubble, or reinforcement that could clutter the exit landing.
  1. Ladder compliance inspection before descentCheck the straightness of the aluminium or hardwood stiles, the crimping of the rungs, and the presence of wraparound base feet.
  2. Positioning and pitch adjustmentPosition the component at an angle of approximately 70 degrees to the horizontal on a stable base cleared of mud.
  3. Deformation-resistant mechanical anchoringSecure both stiles at the top to the shoring walers or to pickets anchored set back from the crest.
  4. Daily clearance validationEnsure each morning that the boarding area at the bottom and the exit area at the surface are clear of any slippery or puncturing materials.

Managing access non-conformities and holding measures

On the construction site, improvised access remains the most insidious trap: an unfastened ship's ladder, a stile that does not extend beyond the crest, or an exit blocked by spoil turns a routine climb into a fatal overturning hazard. As soon as a site foreman or chargehand identifies a non-compliant access point, action must be immediate. In accordance with OTConst, safety organisation requires the competent person to issue clear instructions, up to and including a formal ban on using the defective flight. Descent to the bottom of the trench is immediately closed off with rigid physical barriers, directing personnel to retreat to the nearest compliant access point.

  1. Closure of the passagewayPlace a rail across the opening and hang a prohibition sign. Verbally warn bricklayers and earthworkers working in the trench bottom.
  2. Checking anchorage and seatingCheck the stability of the base foot on firm ground or timber planks, then rigidly secure the stiles at the head to the trench shoring or to anchor pickets driven set back.
  3. Checking dimensionsVerify that the stiles extend by at least 1.00 m above the upper exit level to guarantee a handhold when stepping over.

If the ground has slumped under the effects of weather or plant traffic, no makeshift fix is permitted. The employer applies art. 82 LAA to reinstate prevention suited to the actual constraints: stripping the crest, installing a metal foot shoe, and restoring safety clearances. In the event of a deliberate refusal to comply with elementary securing instructions, the non-compliant worker must be removed from the area. Securing excavation access directly engages site management: tolerating a slippery or unstable ladder constitutes gross negligence in the face of dynamic loads exerted by equipped operatives.

Frequently asked questions

What is the exact value of the mandatory extension at the ladder head?

Ladder stiles must extend at least 1.00 m above the upper access level or exit landing. This height allows operatives to maintain a firm handhold during the critical stepping-off phase, when the centre of gravity shifts outside the flight.

How can a ladder be effectively secured to steel trench sheeting?

Simply wedging the ladder between two trench struts is prohibited. Securing is carried out at the head using metal clamps bolted to the trench box or certified textile lashing straps wrapping around the stiles. At the base, non-slip feet rest on a clean surface or are chocked against a secured timber bearer.

What is the maximum distance to maintain between two access points in a long trench?

As a general rule on Swiss construction sites, the travel distance along the bottom of a trench to reach a means of escape must not exceed 20 to 25 metres. This means setting out ladders with a regular spacing of approximately 40 to 50 metres to guarantee rapid egress in an emergency.

Can a leaning ladder slip if the angle of inclination is incorrectly set?

Yes, an unsuitable angle causes the base to kick out or the ladder to tip backwards. The ladder must be positioned at an inclination between 65° and 75° (approximately 1 in 4). Even when correctly pitched, mechanical securing at the top and bottom remains essential to absorb dynamic jolts from workers carrying their tools.

Texts and standards cited

  • OTConstorganisation of occupational health and safety: appointment of a competent person able to give instructions (para. 1); removal from the construction site of any person endangering others (para. 2)
  • LAA art. 82general prevention rules: to prevent occupational accidents and diseases, the employer shall take all measures shown by experience to be necessary, applicable according to the state of the art, and suited to the prevailing conditions; the workers shall assist them