Key takeaways
- Masonry work is formally stopped as soon as the temperature drops below the 5-degree threshold.
- Using warm water and frost-free storage of bricks prevents destructive thermal bridging.
- Immediate sheeting with thermal insulation retains the heat of hydration generated by the hydraulic binder.
- Every weather interruption must be recorded in the site journal to preserve your rights as a contractor.
Thermal thresholds, mortar preparation and protection of wall faces
On Swiss construction sites exposed to winter weather, load-bearing clay brick or calcium-silicate masonry undergoes major stresses as temperatures approach zero degrees. The mixing water essential for the cement hydration reaction must not crystallise. If frost strikes fresh mortar before it has achieved minimum compressive strength, the volume of water expands, destroys the internal crystalline structure and completely eliminates bond with the block. Art. 37 OTConst stipulates that when carrying out work in the sun, in intense heat or in the cold, the necessary measures must be taken to protect workers. This crew protection is directly linked to the technical mastery of materials at exposed workstations.
- Systematic monitoring of the substrate and ambient air temperature before supplying materials.
- Absolute refusal to lay masonry on beds covered with frost, residual snow or ice.
- Use of masonry units previously stored under dry shelter and at temperatures above freezing.
- Heating of mixing water without exceeding fifty degrees to prevent flash setting of the cement.
- Formal ban on using antifreeze products not approved by the site management.
Mortar management in cold weather requires thorough mixing and limited batches. Mortar tubs must be protected from draughts that accelerate surface cooling. At shift end or during breaks, freshly laid wall heads must be sealed immediately. Thermal insulation made of foam or mineral wool, protected by a weatherproof sheet secured against the wind, is placed to retain the binder's natural exothermicity.
Decision to stop work on the construction site, duty to notify and formal recording
When the thermometer drops below freezing or weather forecasts predict severe night frost without full enclosure heating under a tent, the site foreman must halt wall construction. Continuing erection exposes the structure to an irremediable loss of load-bearing capacity and to rejection upon inspection by the structural engineer. Under art. 365 CO, if any circumstance arises that compromises the proper or punctual completion of the work, the contractor must inform the client immediately, failing which the contractor bears the consequences. Persistent cold typically constitutes a physical obstacle requiring formal notice.
- Temperature recordingMeasure and record on-site temperatures at 07:00, 11:30 and 16:00 using a calibrated thermometer positioned away from direct wind.
- Securing the workstationProtect wall heads with weighted, insulated waterproof sheets to prevent any ingress of rainwater or melting snow.
- Formal notice to managementForward an interruption notice due to severe weather to the client or their designated representative in writing without delay.
- Entry in the site journalDraft a detailed entry in the daily site journal, signed by the site foreman and submitted for approval by the site management.
| Temperature range | Technical action | Site journal status |
|---|---|---|
| +5 °C and above | Standard work, moderate wetting of porous bricks. | Normal activity, routine weather recording. |
| Between 0 °C and +5 °C | Immediate sheeting, warm water, protection of mortar tubs. | Record of winter protection measures. |
| Below 0 °C (continuous frost) | Stoppage of traditional mortars without an enclosed heated shelter. | Entry for stoppage due to severe weather and frost. |
Sheeting systems, heat input and performance of fresh mortar
As soon as the thermometer drops across the Swiss plateau or in Alpine valley bottoms, preserving the heat of hydration becomes the critical factor in the mechanical strength of load-bearing masonry. Site-mixed mortar or factory-made mortar exposed to frost before reaching minimum strength will see its crystalline structure destroyed by the expansion of interstitial water. Protection is not limited to covering the work at the end of the shift: it requires a continuous thermal barrier capable of preventing the rapid cooling of wall heads and faces exposed to the wind.
Thermal enclosure of a storey under construction requires a rigorous methodology. Multi-layer air-bubble or polyethylene foam thermal insulation sheets must cover the fresh wall completely, extending at least 60 centimetres on either side of the wall faces. Draughts beneath the sheets accelerate evaporation and surface freezing: every edge must be weighted down with timber battens, wall clamps or sandbags, strictly avoiding loose dry bricks that could be blown over by gusting bise winds.
| Temperature range (in the shade) | Condition of materials and substrates | Mortar application | Required protection arrangement |
|---|---|---|---|
| +5 °C to 0 °C | Dry bricks, free of frost, stored on raised pallets | Heated mixing water (max. 40 °C), mixing under enclosed shelter | Covering wall heads with insulating sheets as soon as laying ends |
| 0 °C to -5 °C | Sheeted materials under tempered shelter, thermal purging of substrates | Heated silo or hot pre-mix, accelerated setting under monitoring | Complete closure of openings, doubled insulating blankets, bottom sealing |
| Below -5 °C | Substrates potentially frozen through, capillary water frozen solid | Risk of immediate failure of hydraulic setting | Mandatory stoppage of unenclosed load-bearing wall construction |
The use of indirect-fired space heaters allows above-freezing temperatures to be maintained under storey sheeting. Combustion gases must imperatively be vented outside: direct-fired space heaters release significant amounts of water vapour and carbon dioxide that saturate rooms, causing uncontrolled premature carbonation and heavy condensation on fresh bedding layers. Heat distribution must be uniform and directed toward the base of the walls to prevent any thermal shock that would crack fresh mortar joints.
Workstation safety obligations and evidentiary recording in the site journal
Working in winter conditions engages the operational liability of site management on two inseparable fronts: the physical safety of bricklaying personnel and the legal traceability of stoppages dictated by severe weather. In terms of health at the workstation, art. 37 OTConst requires taking the necessary measures to protect workers during operations carried out in the cold. In practice, this means providing a site welfare unit heated to 20 °C, supplying hot drinks and adapting personal protective equipment against digital numbness.
- Bilateral thermohygrometric recordingRecord the sheltered temperature at 07:00, 11:30 and 16:30 using a calibrated station fixed to the facade most exposed to the prevailing wind, then record the relative humidity and wind speed.
- Physical inspection of masonry substratesCheck for the total absence of ice films or frost on concrete slab edges and blocks before spreading any mortar. Using hot water to de-ice a porous substrate is prohibited because residual water refreezes immediately.
- Notification of technical impossibilityAs soon as the critical temperature threshold is crossed or heating equipment is no longer sufficient to guarantee binder integrity, formalise the stoppage of work pursuant to art. 365 CO in order to alert the site management without delay.
- Detailed entry in the site journalRecord the exact time work was suspended, workforce redeployed to sheltered areas, masonry quantities sheeted and the joint signatures of the site foreman and the site management representative.
The legal value of the site journal rests on the surgical precision of its entries. A simple line indicating 'cold stoppage' in no way protects the contractor against future contractual delay penalties under standard SIA 118. The entry must detail the physical impossibility of complying with recognised structural work standards: temperature measured on the bed joint, condition of aggregates in hoppers, easterly wind increasing wind chill and risks of permanent degradation of compressive strength in load-bearing structures.
Management of frost damage and resumption protocol
When frost strikes freshly built masonry, binder setting is interrupted by the formation of ice lenses within the mortar joints. The chargehand or site foreman must act methodically as soon as thawing begins. The temptation to conceal a deteriorated joint or await hypothetical hardening leads directly to rejection of the work during final inspection.
- Systematic sounding of the masonryAfter temperatures return above freezing, test the hardness of the bedding mortar with a steel point and strike the bricks or blocks with a bricklayer's hammer. A hollow sound, a debonded brick or a joint crumbling into dust reveals the destruction of the cement matrix by frost.
- Raking out and demolition of affected areasImmediately dismantle frozen courses. Merely repointing the surface is prohibited: destroyed mortar must be completely raked out down to a sound, bonded bed unaffected by frost.
- Cleaning and moderate re-wettingRemove debris and brush the load-bearing surface to eliminate all residual traces of powdery mortar. Warm the substrate slightly with a space heater if the unit temperature remains below freezing before resuming bricklaying.
- Formal recording and notification to the supervising consultantDraft a raking-out report in the site journal. Record the demolished heights, affected courses, date of intervention and approval from the site management to resume work.
To protect crews during winter raking-out and rebuilding, art. 37 OTConst requires taking the necessary measures to protect workers against cold. In severe weather that makes work hazardous or compromises quality, the duty to notify set out in art. 365 CO obliges the contractor to inform the site management immediately in writing to discharge liability regarding deadlines and technical defects.
Frequently asked questions
How can you immediately verify whether a mortar joint has set or frozen?
As soon as milder weather returns, scratch the joint with the point of a trowel or a screwdriver. A mortar that has set resists firmly, leaving only a faint white surface mark. If the mortar crumbles into fine sand under light pressure or breaks down into a damp paste lacking mechanical strength, the binder was destroyed by the freezing of mixing water. The course must be raked out.
Can de-icing salts be used to thaw blocks before laying?
No, using road salt on bare masonry materials is strictly prohibited. Sodium or calcium chloride penetrates porous bricks and terracotta units. It subsequently triggers heavy efflorescence, prematurely corrodes tying reinforcement or metal tie bars, and impairs the chemical bond of fresh mortar when subsequent courses are laid.
What minimum substrate temperature must be guaranteed before bricklaying?
Masonry units, whether clay bricks, calcium-silicate blocks or concrete blocks, must have a surface temperature of at least zero degrees, ideally above five degrees. Laying on a surface covered with frost, snow or an ice film causes an immediate, complete bond failure between the course and the bedding mortar.
Who bears the cost of dismantling frozen masonry courses?
If the contractor continued bricklaying below the critical temperature threshold without implementing appropriate thermal protection measures or serving prior notice of stoppage to the site management, the costs of raking out, demolition and rebuilding remain entirely at their expense. Conversely, a written order to proceed despite technical notification transfers the risk to the client.
Texts and standards cited
- OTConst art. 37sun, intense heat and cold: when carrying out work in the sun, in intense heat or in the cold, the necessary measures must be taken to protect workers.
- CO art. 365materials and ground: the contractor is liable for the sound quality of the materials they supply; if the materials supplied by the client or the ground designated by the client are found to be defective, or if any other circumstance compromises the proper or punctual completion of the work, the contractor must inform the client immediately, failing which the contractor bears the consequences (para. 3).