🧱 CFC 201 / 211.0Earthworks, excavations and temporary shoringChapter 1 of 10 in the section

Plate bearing test on excavation base: ME target values and recording procedure

On building construction sites, checking the bearing capacity of the excavation base is an often-overlooked hold point. This chapter explains how to interpret the ME1 and ME2 deformation moduli from the geotechnical report, who is responsible for ordering the static plate bearing test, and what wording to enter into the minutes if values are not achieved.

Key takeaways

  • Standard SIA 267 governs the verification of ground bearing capacity prior to any concreting.
  • The geotechnical report contractually sets the target value for the deformation modulus ME.
  • Approval of the excavation base is a mandatory hold point for the bricklayer/mason.
  • Any insufficient bearing capacity requires an immediate notice of defects recorded in the formal minutes.

Geotechnical requirements, ME values, and responsibilities for ordering tests

The excavation base directly receives the blinding concrete and subsequently the foundation slab or footings. Before starting these masonry works, the bearing capacity of the natural ground or replacement fill must be verified in accordance with the civil engineer's design assumptions. This check is part of recognised best practice governed by standard SIA 267 (Geotechnics). The static plate bearing test remains the reference method for measuring ground deformability under a specified load.

Static plate bearing test (ME1 / ME2)
A setup applying a stepped circular load to the ground by means of a hydraulic jack bearing against a heavy lorry. The first loading cycle measures the initial deformation modulus ME1. The second cycle, following unloading, measures the deformation modulus ME2. The ME2/ME1 ratio indicates compaction quality and the potential for residual settlement of the excavation base.

Identifying who orders and pays for the test depends on the contractual setup of the construction site. As a general rule, the geotechnical testing campaign falls under site management or the civil engineer appointed by the client, carried out via an independent specialist testing laboratory. However, in certain tender specifications (CFC 211), the static plate bearing test item is included directly within the earthworks or structural work contractor's package. The site manager must verify this allocation right from site preparation to avoid missing the order for the reaction lorry and accredited operator.

Indicative target values according to ground type and structure
Excavation base ground typeTarget ME1 modulusRequired ME2 modulusTolerated ME2 / ME1 ratio
Untreated loose silty or clayey soil15 to 25 MN/m²30 to 45 MN/m²Less than 2.5
Well-compacted run-of-quarry replacement gravel40 to 60 MN/m²80 to 100 MN/m²Less than 2.2
Foundation sub-base for heavy foundation slab60 to 80 MN/m²120 to 150 MN/m²Less than 2.0

Managing the hold point, drafting reservations, and recording remedial measures in the minutes

Approval of the excavation base is a critical contractual hold point. The site foreman or chargehand must never authorise pouring the blinding concrete without formal approval from the geotechnical engineer or site management. Pouring concrete on an unapproved base transfers liability for subsequent differential settlement to the executing contractor. The plate bearing test report must be handed over immediately on site or be the subject of prompt written confirmation in the construction site site instruction log.

If the measured ME2 modulus is lower than the value specified in the geotechnical report, or if the ME2/ME1 ratio exceeds the contractual limit (indicating under-compaction or the presence of pore water), the ground is deemed defective. In accordance with art. 365 CO, the contractor must immediately notify any defect in the ground made available to them, failing which they will bear the damaging consequences.

  1. Notification of refusal to approveImmediately record the failure of the plate test in the construction site minutes, specifying the exact coordinates of the measurement point, the base level, and the measured ME values.
  2. Formal drafting of reservationsFormally record in writing the suspension of concreting works and state that the proper execution of the works is compromised given the condition of the ground provided.
  3. Request for instructions from site managementIssue a formal request to the civil engineer and site management to specify remedial measures (local soft-spot excavation, stabilisation, or imported fill).

Procedure of the static test and interpretation on the construction site

On the construction site, carrying out the static plate bearing test according to the requirements of standard SIA 267 requires rigorous logistics. The geotechnical laboratory technician sets up a rigid circular plate, generally 300 mm in diameter for standard building excavation bases, connected to a hydraulic jack and a dial gauge micrometer. The setup requires a stable and heavy reaction mass, usually a backhoe excavator or a lorry loaded to at least 10 to 15 tonnes. The machine must remain completely stationary throughout the entire load increment to avoid falsifying settlement readings through vibrations or spurious load transfers onto the surrounding ground.

Deformation modulus ME
Quantity expressed in meganewtons per square metre (MN/m²), calculated from the slope of the load-settlement curve during a static plate bearing test. A distinction is made between the modulus from the first loading cycle (ME1) and that from the second cycle after complete unloading (ME2).

The test consists of two complete loading and unloading cycles. The first cycle determines the ME1 modulus, which measures the initial stiffness of the ground while incorporating the rearrangement of surface particles and mechanical interlocking. The second cycle, applied after stepped unloading, provides the ME2 value. This second measurement reflects the quasi-elastic behaviour of the stabilised bearing ground. The contractual geotechnical report specifies two mandatory criteria: the minimum threshold value for ME2 required under the footing or foundation slab, and the ME2/ME1 ratio.

Interpretation chart for static test results at excavation base
Measured configurationGeotechnical diagnosisDirect impact on hold point
ME2 compliant, ME2/ME1 ratio lower than or equal to thresholdBearing capacity and compaction validated according to design assumptionsImmediate release of the hold point; authorisation to pour blinding concrete
ME2 sufficient, but ME2/ME1 ratio significantly above thresholdSubsoil firm but loosened at the surface or poorly compacted during the trimming passHold point maintained; supplementary surface compaction and retesting
ME2 lower than value in geotechnical reportBearing ground not reached, presence of soft pockets or excessive moistureRejection of excavation base; specification of soft-spot removal or replacement by engineer

Remediation protocols, soft-spot removal, and daily site log traceability

When measured values remain below the requirements set by the civil engineer or geotechnical specialist, the contractual hold point has full legal and technical effect. Under no circumstances may the masonry contractor have blinding concrete delivered or poured. If the ground provided by the client proves unsuitable or defective compared to initial assumptions, the contractor must report the situation in writing immediately pursuant to the duty to notify under art. 365 CO, failing which they will bear the consequences of subsequent delays or defects.

  1. Immediate joint inspection recordRecord the test failure report signed jointly by the laboratory technician, the site foreman, and site management.
  2. Notification of reservations and work stoppageRecord the freezing of the affected area, the suspension of formwork, and expected delays to concrete deliveries in the daily site log pursuant to the Code of Obligations (CO).
  3. Technical definition of remediationWait for the civil engineer's written site instruction ordering either local soft-spot removal with layer-by-layer compacted quarry run material or the installation of a non-woven separation geotextile.
  4. Approval check of remedial worksPerform a new plate bearing test on the compacted replacement layer in order to issue the final sign-off lifting the hold point.

All remedial work (extra excavation quantities, carting away to an approved tip, supply and placement of non-frost-susceptible replacement gravel) must be recorded on daywork sheets or agreed daily joint measurements. This rigorous tracking ensures the financial recovery of unforeseen works according to recognised building rules, whilst absolving the contractor of liability regarding the foundation assumptions of standard SIA 267.

Rejection of bearing capacity and ME non-compliance: managing contractual standstills

When the static plate bearing test indicates an ME2 modulus lower than the value set by the geotechnical report or the ME2/ME1 ratio reveals insufficient compaction, the excavation base cannot be handed over. The site foreman and site manager must immediately formalise this refusal of approval. Pouring blinding concrete onto a non-compliant subgrade directly exposes the masonry contractor to liability for subsequent differential settlement.

Faced with an unsatisfactory result, the contractor exercises their duty to notify under art. 365 CO by informing site management without delay that the designated ground is defective. The construction site minutes record the values obtained, the exact location of the test points, and the cessation of formwork or concreting operations. The civil engineer and geotechnical specialist must then formally specify the required remediation measures: local soft-spot excavation of compressible pockets, replacement with non-frost-susceptible gravels, or stabilisation using hydraulic binders.

  • Record the ME1, ME2 values, and the ME2/ME1 ratio in the daily site log accompanied by the laboratory test certificate.
  • Issue the notice of defects in writing to site management in accordance with the contract rules and standard SIA 118.
  • Require a written variation order prior to starting additional earthworks or ground replacement operations.
  • Repeat the static plate bearing test following remediation to formally release the hold point in accordance with standard SIA 267.

The costs of over-depth excavation, carting away unsuitable soils, and placing replacement materials are subject to an immediate joint measurement. A second geotechnical inspection after remediation is mandatory before restarting any reinforced concrete operations.

Frequently asked questions

Who must order and pay for the plate bearing test on the excavation base?

Unless stipulated otherwise in the tender specifications, the static plate bearing test forms part of the geotechnical testing services instructed by site management or the client according to standard SIA 267. The masonry or earthworks contractor supplies the heavy plant used as reaction ballast for the hydraulic jack. If the test fails due to poor compaction attributable to the contractor, the costs of retesting are back-charged to them.

What is the difference in interpretation between ME1 and ME2 during testing?

The ME1 modulus measures soil deformation during the first loading cycle, incorporating initial settlement and particle rearrangement. The ME2 modulus measures behaviour during the second loading cycle after unloading. An ME2 value meeting the geotechnical report requirements confirms the required bearing capacity. An excessively high ME2/ME1 ratio indicates under-compaction requiring additional passes of the roller before approval.

What should be done if site management demands concreting despite an unmet ME target?

The contractor must immediately submit a written notice of defects under art. 365 CO and standard SIA 118, pointing out the defective ground and disclaiming all liability for future structural defects. If site management formally upholds its instruction in writing despite the warning, the contractor carries out the work under the exclusive liability of the client, having recorded these instructions in the daily site log.

How is the release of a contractual hold point formalised on site?

The release of the hold point occurs via the joint signing of an excavation base acceptance form or the construction site minutes by the geotechnical specialist, the civil engineer, and the site manager. This document appends the raw test sheets from the static plate bearing test confirming that target values were reached. Only after this formal sign-off may the masonry team proceed with pouring the foundation slab.

Texts and standards cited

  • norme SIA 118General conditions for construction works, management of notices, and contractor's duties.
  • norme SIA 267Standard for geotechnics, design and verification of foundation structures, and bearing capacity checks.
  • CO art. 365Materials and ground: the contractor must immediately notify the client if the ground provided by the latter is defective or compromises proper execution.