Key takeaways
- An excessively thick layer creates a deep soft mattress that causes subsidence after a few months.
- Compaction energy depends directly on the operating weight and frequency of the machine.
- The plate load test or dynamic penetrometer validates bearing capacity before the next layer.
- The compaction report serves as proof of compliant execution against subsequent settlement claims.
Adapt pass thickness to the plant and the nature of the run-of-quarry material
The classic subsidence of a trench backfill or earthworks formation after eight months of use almost always originates from spreading passes that are too thick. When a plant operator pushes 60 centimetres of gravelly material in one go, the shock wave generated by the machine only penetrates the first twenty centimetres. Below this, intergranular voids remain. With rainwater infiltration and traffic vibrations, the fine particles migrate, the mineral skeleton reorganises, and differential settlement appears beneath the asphalt or floor slabs.
| Compaction plant | Indicative operating weight | Maximum loose thickness | Minimum number of cross passes |
|---|---|---|---|
| Vibrating rammer | 60 to 80 kg | 15 to 20 cm | 4 to 6 passes |
| Single-direction vibrating plate | 100 to 200 kg | 15 to 25 cm | 4 to 6 passes |
| Heavy reversible vibrating plate | 400 to 600 kg | 30 to 40 cm | 6 to 8 passes |
| Vibrating tandem roller | 1.5 to 3 tonnes | 25 to 35 cm | 6 passes |
| Heavy single-drum roller | 7 to 12 tonnes | 40 to 50 cm | 6 to 8 passes |
On the construction site, the foreman visually checks the volume reduction with each pass. If the soil begins to heave laterally beneath the roller's path or under the rammer's foot, the mechanical saturation limit has been reached or the initial thickness was excessive. The plant then merely disrupts the surface layer without transferring stress at depth.
Measure in situ bearing capacity and record the compaction report
Visual assessment when a lorry wheel passes over in no way constitutes admissible technical proof. The bearing capacity of a formation level or technical backfill must be quantified using standardised geotechnical methods. Static plate load testing enables measurement of the deformation modulus during initial loading as well as the compaction ratio between the second and first cycles. For narrow trenches and the immediate vicinity of civil engineering structures, the light dynamic penetrometer provides a continuous resistance profile across the entire backfilled height.
- Preparation of the testing platformLevel the surface of the compacted layer perfectly flat. Remove protruding rock fragments and spread a thin layer of calibrated sand to ensure full contact with the load disc.
- Installation of the reaction loadPosition a heavy piece of construction plant (excavator or loaded lorry) directly above the plate to act as a reaction mass for the hydraulic jack, maintaining sufficient distance so as not to skew the stresses.
- Loading cycles and settlement readingsApply the pressure increase in regular stages. Record settlement using the dial gauge to establish the stress-strain curve and calculate the ME1 and ME2 moduli.
- Verification of the acceptance criterionImmediately compare the resulting modulus and the ME2 to ME1 ratio with the requirements of the engineer's specifications. Any non-compliant result requires an immediate re-working of the pass.
The mechanism of delayed settlement: thick layers and lack of energy
The classic defect observed eight months after the laying of asphalt or a floor slab almost always originates at the trench bottom: linear subsidence along a facade or a depression under an access road. This phenomenon does not result from spontaneous deterioration of the material, but from the settlement of over-thick backfill layers. When an excavator operator unloads recycled run-of-quarry or gravelly material in thicknesses of 70 or 80 centimetres to speed up perimeter backfilling, the energy of surface plant never reaches the lower third of the pass.
Under the action of a heavy vibrating plate or a tandem roller, the top twenty centimetres undergo intense densification, creating an optical illusion of a rigid crust. Beneath it, the void ratio remains high and the granular skeleton stays unstable. From the first autumn rains and infiltration cycles, water dissolves the suction bonds between the uncompacted fines. Gravity and traffic loads then reorganise the grains, causing an underground loss of volume that reflects on the surface several months after the completion of structural work.
| Plant category | Operating weight | Maximum layer thickness | Number of cross passes |
|---|---|---|---|
| Vibrating rammer | 60 to 80 kg | 15 to 20 cm | 3 to 4 passes |
| Single-direction vibrating plate | 100 to 200 kg | 15 to 20 cm | 4 to 6 passes |
| Heavy reversible vibrating plate | 400 to 600 kg | 30 to 40 cm | 4 to 6 passes |
| Walk-behind vibrating tandem roller | 800 to 1,500 kg | 25 to 35 cm | 4 to 6 passes |
| Articulated earthmoving compactor roller | 5 to 12 tonnes | 40 to 50 cm | 6 to 8 passes |
Validation of bearing capacity and traceability through the compaction report
The compliance of a backfill cannot be presumed by eye: it is established by in situ tests before any authorisation to lay second-level utility pipes or road infrastructure. The rigid plate test (according to the Swiss standardised geometry) determines the initial modulus of elasticity and the reloading modulus, as well as their ratio which reflects residual compactness. For narrow trenches or the immediate vicinity of buried walls where positioning a reaction lorry for the plate is impossible, the light dynamic penetrometer provides the alternative for continuous driving control over the full backfill height.
- Definition of the test gridEstablish test points every 20 to 30 linear metres in trenches or on a 100 to 200 m² grid on open formations, paying particular attention to connection zones against concrete walls.
- Execution of the deformation testCarry out staged loading using a hydraulic jack braced under the chassis of a machine with sufficient mass, or perform sets of dynamic penetrometer drive tests down to trench-bottom level.
- Comparison against contractual requirementsVerify the achievement of deformation moduli defined in the technical specifications (for instance, the deformation ratio between the second and first loading cycles, certifying the absence of underlying settlement).
- Drafting and signing the reportRecord on the document the raw results, the batch number of the imported material, the recorded moisture content, the plant used, theoretical pass thickness, and formal countersignature by site management.
In the event of a subsequent dispute over raft foundation cracks or kerb settlement, the contractor is liable for the proper execution of their work in accordance with the Code of Obligations (CO). Without a time-stamped compaction report linked to as-built drawings, the company finds itself without any defence against an expert legal assessment. The compaction report is not merely an administrative formality: it forms the material proof that recognised trade standards were respected pass by pass.
Management of bearing capacity non-conformities and subsidence disputes
When a bearing capacity test reveals an insufficient value or when differential settlement appears beneath a raft foundation or roadway, backfilling must be stopped immediately. The common error is to intensify the passes of heavy plant over an excessively thick layer: this surface surcharge creates destructive sponginess without compacting the base. In accordance with the Code of Obligations (CO), the contractor reports geotechnical anomalies encountered without delay in order to protect their rights.
- Inspection and delimitation of the deficient zoneMark out the non-compliant area using stakes and measure the exact footprint. Carry out supplementary soundings with a light dynamic penetrometer to determine the actual depth of compaction deficiency.
- Removal and excavation of uncompacted materialFully excavate the defective pass using a backhoe excavator. It is technically impossible to recover a soft base by vibrating the surface: sheared or waterlogged material must be extracted down to a stable level.
- Reinstatement in thin layers and controlled re-moisteningReintroduce clean 0/45 mm gravel in passes not exceeding 20 to 30 cm loose thickness. Adjust the moisture content by light spraying to achieve optimum density before running the vibrating plate.
- Joint test and acceptance reportHave a new plate test carried out by an independent laboratory in the presence of site management. Prepare the compaction report explicitly mentioning the excavation of defective material and the final measured value.
In the event of subsidence after eight months accompanied by cracks on the superstructure, the investigation of the claim is based exclusively on written documents. The compaction report, accompanied by the pass location plan and test tickets, constitutes the sole exonerating technical proof against the requirements of art. 368 CO regarding defects in the work.
Frequently asked questions
How should one react immediately if the plate test gives a value below the requirements beneath a floor slab?
Stop backfilling and mark out the zone. Do not run a heavier roller: on poorly graded or water-saturated gravel, this causes internal shearing. Excavate the non-compliant layer over its entire thickness. Reintroduce non-frost-susceptible 0/45 mm gravel in 20 cm compacted passes, then repeat the plate test before allowing the blinding concrete to be cast.
What maximum layer thickness should be applied for a 400 kg vibrating plate at the bottom of a narrow trench?
For a 400 kg reversible vibrating plate, the maximum loose material thickness is 30 cm per pass, reduced to 20 cm in silty or slightly moist soil. In a narrow trench, lateral confinement requires carrying out 4 to 6 cross passes to achieve the required compactness. Beyond this thickness, impact energy does not travel through the layer.
Can the client require the use of clayey excavated materials to backfill around the basement?
The client can request it, but the contractor must verify their compactibility. If the soil contains too many fines or too much water, delayed settlement is inevitable. The contractor exercises their duty to notify in writing to flag the soil's unsuitability. If the order is maintained, the company disclaims liability for future subsidence of utility pipes and perimeter works.
What essential elements must appear on the compaction report to serve as proof in a dispute?
The document records the date, weather conditions, the exact zone plotted on a plan, the nature of the material used, and the type of plant along with its weight. It details the actual thickness of placed layers, the number of completed passes, as well as the raw bearing capacity test readings. The report must be signed jointly by the foreman and site management.
Texts and standards cited
- CO art. 365materials and ground: the contractor is liable for the sound quality of the materials they provide; if the materials provided by the client or the ground designated by the client are found to be defective, or if any other circumstance jeopardises the regular or prompt execution of the work, the contractor shall immediately inform the client thereof, under penalty of bearing the consequences (para. 3).
- CO art. 368client's rights in case of defects in the work: rejection, price reduction, rectification, damages; any clause agreed in advance that restricts or excludes the right to rectification of defects is null and void if the defect concerns a construction (para. 2bis, since 1 January 2026).