🧱 CFC 201 / 211.0Earthworks, excavations and temporary shoringChapter 6 of 10 in the section

Contaminated soil on a Swiss construction site: material classification and landfill disposal route

This chapter details the procedure for managing suspicious soil on an earthworks construction site. You will learn how to apply material classification according to the Waste Ordinance, plan the prior analysis, and immediately draft the notice of discovery to protect your company legally and financially.

Key takeaways

  • Sorting of materials is carried out directly on the construction site according to the Waste Ordinance.
  • The recovery of unpolluted excavation materials is a priority under federal law.
  • Each transport of contaminated soil requires a duly completed tracking form.
  • The notice of discovery immediately signals the pollution to the client to avoid additional costs.

Identify contaminated soils and master the legal classification of materials

During earthworks or excavation operations, the discovery of contaminated soil radically alters the evacuation logistics procedure. Federal legislation establishes a strict framework for handling these excavated materials. Art. 17 OLED requires the sorting of waste on the construction site itself. Residual earthy materials, excavated material, and hazardous waste must be strictly separated in order to direct each fraction to the appropriate disposal route.

The framework for recovery and landfilling is based on art. 19 OLED, which requires unpolluted excavation materials to be extracted and reused as a priority. When the ground shows signs of contamination (hydrocarbon odour, colour change, presence of clinker or residues from old backfill), a prior analysis by a specialist laboratory is mandatory before the removal by lorries. This chemical characterisation determines the acceptability class of the material.

Traceability of contaminated materials to the landfill disposal route is ensured by means of a tracking form for hazardous waste or waste subject to control. This official document accompanies every lorry trip. It records the exact volume, the type of pollutant identified, the name of the carrier, and the final recipient landfill. Keeping this form guarantees that the company has proof of compliance with legal disposal routes.

Notify the client by a notice of discovery to reject additional costs

The discovery of suspicious soil not listed in the tender documents constitutes an unforeseen modification of ground conditions. To avoid bearing the costs of special landfill disposal, additional transport, or construction site stoppages, the prompt response of the site manager is decisive. In accordance with the Code of Obligations (CO), the contractor is required to report without delay any defect identified in the ground designated by the client.

If the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor shall immediately inform the client, failing which he shall bear the consequences.

art. 365 CO
  1. Immediate stoppage of stripping on the suspicious zoneIsolate the contaminated zone by means of demarcations and stop earthworks at that location to prevent the mixing of clean and contaminated soil.
  2. Sampling and prior analysisEngage a geologist or an environmental engineer to take samples and carry out laboratory analyses.
  3. Drafting and sending the notice of discoveryImmediately send a formal written notice to the client and site management detailing the finding, the risks, and the partial stoppage of the construction site.
  4. Preparation of the form and evacuation trackingAs soon as the routes are validated by the client, organise loading under a tracking form and record the quantities for billing on daywork or via an addendum.

Sorting on the construction site and segregation of excavation batches

As soon as an excavation uncovers suspicious materials (hydrocarbon odours, soot stains, heterogeneous backfill containing clinkers or demolition fragments), general earthworks must be reorganised immediately. The fundamental rule laid down by OLED requires the sorting of materials directly on the construction site in order to separate unpolluted fractions from contaminated or hazardous soil. Mixing clean excavated materials with contaminated soil constitutes a major logistical error: the entire relocated volume would assume the status of the most contaminated fraction, drastically multiplying landfill costs.

On site, segregation is carried out by selective excavation using an excavator. The site manager and team leader demarcate the zones on the ground with paint markings and isolate the batches on an impermeable, covered platform or on ballasted HDPE liners to prevent any percolation into the water table or stormwater networks.

Disposal and acceptance routes according to the classification of excavated materials
Material classificationVisual / chemical characteristicsAuthorised destination route
Unpolluted materialsClean topsoil, raw sediments below the VBBo/OSol guide valueFull recovery (backfilling, agricultural reinstatement, or type A landfill)
Low-level contaminated materialsMinor threshold exceedances (PAH, heavy metals), historical fillType B controlled landfill or mineral treatment facility
Heavily contaminated / hazardous materialsPresence of heavy hydrocarbons, PCBs, solvents, or industrial residuesType E landfill, soil washing centre, or dedicated incineration

Prior analysis, transport tracking, and management of additional costs

Evacuation to an approved route requires rigorous chemical characterisation. The prior analysis is carried out by taking representative samples from the excavator bucket or directly from isolated stockpiles. The parameters tested in a certified laboratory cover the hydrocarbon index, PAHs, heavy metals, and total hydrocarbons. In accordance with OLED art. 19, excavated materials that do not meet safety requirements cannot be recovered without prior treatment or a specific destination.

Logistical tracking is ensured by the tracking form (or waste tracking document). Every lorry leaving the construction site to transport contaminated soil must be accompanied by this document specifying the waste code, volume, consignor (the client), carrier, and authorised receiving facility. The masonry contractor retains a signed copy upon acceptance to prove the transfer of liability.

From a contractual and financial point of view, the company must protect its margins. The discovery of suspicious soil not mentioned in the specifications constitutes an unforeseen modification of ground conditions. Under art. 365 CO, an contractor who finds that the ground supplied by the client is defective or jeopardises the regular execution of the work must inform the client immediately via a written notice of discovery.

  1. Localised stoppage and securingHalt excavation in the contaminated zone, cordon off the area, and secure the stockpile under a tarpaulin.
  2. Drafting of the notice of discoveryImmediately notify site management in writing, describing the nature of the discovery and reserving the right to price supplements and site downtime.
  3. Sampling and analysisHave sampling carried out by the project geologist or the appointed laboratory in order to determine the exact waste code.
  4. Preparation of the form and evacuationOrganise transport to the appropriate landfill accompanied by the completed tracking form and record the quantities for final measurement under the bill of quantities.

If the contractor fails to issue this immediate notice and continues earthworks by mixing soils or sending them to a lower-class landfill without authorization, it risks bearing the entire difference in landfill taxes and subsequent remediation costs alone.

Route blockage and dispute over additional costs: emergency procedure

On an earthworks site in French-speaking Switzerland, faulty management of contaminated soil quickly paralyses the construction site: rejection of a lorry at the weighbridge of a type B or E landfill, dispute by site management over invoices for temporary impermeable stockpiling, or disagreement regarding excavator downtime costs. As soon as a batch is turned away or chemical suspicion blocks evacuation, the site manager must neutralise the risk of financial liability.

  1. Immediate containment and ongoing sortingStop extraction in the disputed zone without disrupting adjacent clean earthworks. According to OLED, excavated materials must be sorted on the construction site to prevent mixing with clean excavation material. Place the questionable volume in a berm on an impermeable geomembrane covered with a ballasted tarpaulin to contain runoff.
  2. Written notification of hindrances and waiting costsSend a notice of discovery or blockage to site management and the client without delay. According to art. 365 CO, the contractor must report defects in the ground immediately, under penalty of bearing the consequences. The letter must state the closure of the disposal route, disrupted production rates, and driver waiting times, expressly reserving rights to additional transport and temporary storage costs and extensions of time.
  3. Joint sampling and traceabilityDemand the immediate intervention of the environmental specialist appointed by the client to perform a prior analysis on the quarantined stockpile. Draw up a joint sampling record prior to any redispatch to a soil washing centre or approved landfill.
  4. Documentary lockdown of material flowsDo not let any lorry depart without a waste tracking form duly countersigned by the driver, detailing the waste code, the authorised receiving facility, and the official weight. File weighbridge dockets in the daily site report as supporting evidence for earthworks account settlements.

Frequently asked questions

A landfill refuses a lorry due to hydrocarbon odour: what does the driver do?

The driver never unloads without authorisation and does not return the lorry to the construction site without instructions. He immediately notifies the foreman or site manager. The vehicle is diverted to a declared temporary impermeable storage area or quarantined on site pending prior analysis. A formal notice is submitted to site management for formal record of the blockage and coverage of the haulier's waiting time.

Who orders and pays for the chemical analysis of suspicious excavated material found in a trench?

Chemical characterisation is exclusively the responsibility of the client, who is liable for the quality of their subsoil and is the waste holder under environmental legislation. The contractor immediately notifies the discovery of an abnormal pocket. It requests the intervention of the geotechnical engineer or environmental expert appointed by site management to carry out sampling. The company does not order any laboratory analysis on its own initiative without a written daywork voucher approved by the client.

How do you justify invoicing for temporary buffer storage of contaminated soil on the construction site?

Justification is based on the signed daily report, joint measurements of the quarantined stockpile, and the formal notice letter regarding defective ground. The contractor details the laying of the bottom impermeable membrane, peripheral containment bunds, weather protection sheeting, and machine time required for double handling. These specific services are billed on daywork or via a new price agreed by addendum prior to redispatch to the final disposal route.

Can low-level contaminated soil be evacuated to a landfill for unpolluted excavation materials?

No. According to federal waste regulations, materials that do not meet the recovery criteria or the clean excavation threshold limits cannot enter a type A landfill for unpolluted materials. Any unlawful delivery incurs the liability of the consignor and the carrier. These volumes must be routed, based on complete analyses and with an official tracking form, to a type B or E landfill or a specialised treatment facility.

Texts and standards cited

  • OLEDsorting of construction waste: hazardous waste is separated from other waste and disposed of separately; the remainder is sorted on the construction site (earthy materials, excavation materials, demolition materials, recoverable materials such as glass, metals, wood, and plastics, combustible waste, other waste); if on-site sorting is impossible, it is carried out in appropriate facilities (para. 2).
  • CO art. 365materials and ground: the contractor is liable for the good quality of the materials he supplies; if the material supplied by the client or the ground designated by him is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, he shall immediately inform the client, failing which he shall bear the consequences (para. 3).