🧱 CFC 201 / 211.0Mortars, site-mixed concretes and placement productsChapter 3 of 10 in the section

Concrete consistency: performing and interpreting the slump test on the construction site

This chapter provides site foremen and team leaders with the exact method to perform the Abrams cone slump test in five minutes. You will know how to check the compliance of the received batch, measure slump according to the recognised rules of the art, record the result on the delivery note and act without compromise when faced with an out-of-tolerance mix.

Key takeaways

  • The Abrams cone slump test immediately validates the workability of fresh concrete delivered to the construction site.
  • Sampling is carried out after the first half cubic metre discharged from the mixer truck to ensure it is representative.
  • Rigorous compaction is performed in three equal layers with twenty-five strokes of a standardised steel rod.
  • Any rejection of a mixer truck requires the immediate recording of the measured result and signature on the delivery note.

Performing the Abrams cone test according to the construction site procedure

On the construction site, the delivery of a truckload of ready-mixed concrete engages the responsibility of the masonry crew as soon as the chute is opened. The Abrams cone slump test remains the universal, fast and autonomous method to verify that the plasticity of the mix meets the pumping and vibration requirements of the element to be cast.

Slump
Measurement in millimetres of the vertical subsidence of a frustum of fresh concrete after the gradual and vertical removal of the Abrams mould.
  1. Equipment preparation and samplingPlace the metal base plate on flat, rigid and clean ground. Moisten the inside of the cone and the surface of the plate without leaving free standing water. Discharge approximately 0.3 to 0.5 m³ of concrete from the mixer truck before collecting the sample in a clean wheelbarrow.
  2. Filling and tamping in three layersHold the cone firmly clamped to the ground using the two foot lugs. Fill the mould in three layers of approximately equal volume (the first layer reaches approximately 70 mm in height, the second 160 mm). Tamp each layer with 25 strokes evenly distributed over the cross-section using the 16 mm diameter round steel rod with a hemispherical tip. Slightly penetrate the underlying layer on passes 2 and 3.
  3. Striking off the top surfaceFor the third layer, maintain a slight excess of material above the upper edge. After the 25 strokes of the tamping rod, strike off the surface level with the top rim using the steel rod in a sawing and rolling motion. Clean the area around the base plate.
  4. Steady demoulding and measurementDemould immediately by pulling the cone upwards in a steady, vertical motion without twisting or jerking, over a period of 2 to 5 seconds. Invert the empty cone next to the slumped concrete mass, place the steel rod across the top of the mould as a bridge and measure the distance between the underside of the rod and the highest point of the slumped concrete with a tape measure.

Interpreting consistency classes, tolerances and tracking non-conformities

The delivered concrete must strictly comply with the consistency class specified on the purchase order and the delivery note. Under the relevant SIA concrete standard, slump classes S1 to S5 define the workability ranges required for structural elements.

Slump consistency classes and permissible tolerances
ClassTarget slump (mm)Class range (mm)Compliance tolerance (mm)
S1 (stiff)10 to 4010 to 40± 10
S2 (plastic)50 to 9050 to 90± 20
S3 (very plastic)100 to 150100 to 150± 20
S4 (fluid)160 to 210160 to 210± 30
S5 (very fluid)≥ 220≥ 220± 30

For dense foundation rafts, reinforced shear walls or pumped elements, class S3 or S4 is the standard order for Swiss contractors. When the measured value exceeds the tolerance range, the concrete must under no circumstances be poured into the formwork without regulated corrective action.

  • Immediately write on the delivery note the statement "Rejected for consistency non-conformity".
  • Record the precise value measured in millimetres (e.g. "Measured slump: 240 mm for S3 ordered").
  • Have the delivery note countersigned by the mixer truck driver before their departure.
  • Record the event with the exact time and ambient temperature in the site journal.
  • Notify site management and the ready-mix plant without delay to dispatch a compliant delivery.

In accordance with art. 365 CO, the contractor is liable for the material it uses and must immediately report any defect that jeopardises the proper execution of the works. Written records of the test protect the construction company against any subsequent claims regarding drying shrinkage cracking or strength loss.

Course of action in the event of a consistency drift upon delivery

As soon as a slump test reveals a value outside the tolerance of the ordered class, the site foreman or team leader immediately applies the joint inspection procedure. No pouring into the formwork may proceed until the deviation is investigated. The mixer truck remains parked in the reception area, engine idling slowly to keep the drum rotating without prematurely altering the setting of the binder.

  1. Immediate re-testingIf the first sample yields an abnormal measurement, a second slump cone is performed without delay from a new representative sample taken from the truck, after re-homogenising the drum at nominal speed for at least one minute.
  2. Notification to the driver and ready-mix plantConfirmation of a drift requires alerting the batching plant dispatcher without delay. The volume remaining in the mixer, the exact arrival time and the magnitude of the deviation in millimetres must be communicated orally and then recorded.
  3. Controlled correction using admixturesFor concrete that is too stiff (slump below the range), only the addition of an approved plasticiser or superplasticiser, strictly supplied or approved by the concrete producer, is permitted. The operation requires vigorous mixing in the drum before a new slump check.
  4. Formal rejection and turning away the mixer truckIf the concrete proves too fluid (slump exceeding the upper limit) or if the workability retention time has elapsed, the load is purely and simply rejected. The delivery note must be endorsed before the driver leaves the construction site.

In accordance with art. 365 CO, the contractor is answerable for the material it uses and has a strict duty to notify the client or site management if a supply has a defect likely to compromise the conformity of the works. Tacitly approving an inadequate consistency shifts full liability for subsequent structural defects onto the masonry company.

Administrative recording and traceability in the site report

The result of each Abrams cone test, whether compliant, adjusted or rejected, provides conclusive evidence of the contractor's internal control. This record protects the site agent and site foreman in the event of subsequent disputes regarding 28-day strengths or the durability of fair-faced concrete.

Operational management matrix for consistency deviations at reception
Slump observationMeasured deviationImmediate action on the construction siteMandatory endorsement on the note
Concrete too dry (below tolerance)> 20 mm belowHalt pouring, potential adjustment with plasticiser by the plantVolume of admixture added, mixing time, re-test value
Concrete too fluid (exceeding tolerance)> 20 mm aboveImmediate rejection of delivery, no pouring into formworkReason for rejection, recorded slump value, refusal of standard signature
Compliant concrete within rangeWithin standard rangeDischarge or pumping authorised without modificationMeasured value in mm, testing time, operator's initials
Visible segregation upon demouldingAsymmetrical collapseImmediate re-test; rejection if separation recursVisual mix non-conformity, photo attached to site journal

Traceability is maintained on two distinct yet inseparable media. On the one hand, the supplier's physical or digital delivery note must include the exact value in millimetres, the sampling time and the legible signature of the qualified mason who carried out the test. On the other hand, the daily site report compiles the exact destination of the concrete (e.g. basement walls between grid lines 4 and 7, ground floor slab), ambient weather conditions and any incidents encountered.

With regard to structural risk management, strict compliance with the recognised rules of the art is essential both contractually and legally. Deliberate disregard of concrete specifications or unauthorised liquid additions reducing load-bearing capacity directly engage the liability of the parties involved, with art. 229 CP providing for penalties in the event of breaches of the rules of the art of construction endangering human life or limb.

Managing slump deviations and conducting truck rejections

When the Abrams cone measurement falls outside the tolerance of the ordered class, the site foreman must not improvise any blind adjustments. A non-compliant consistency compromises workability in the formwork, final density and the mechanical strength of the structure. When faced with an out-of-range value, the site protocol dictates a methodical and hierarchical response.

  1. Immediate re-testingPromptly take a second sample from the same truck after re-homogenising at high speed for two minutes. The test procedure must be scrupulously reapplied on a flat, rigid area.
  2. Analysis of the driftIf the concrete is too stiff compared to the consistency class, adding plasticiser at the plant or by the driver is only permitted under formal instruction from the ready-mix plant. Adding water on the construction site remains strictly prohibited.
  3. Rejection and turning away the loadIf the concrete remains outside tolerance or shows visible segregation, the delivery is purely and simply rejected. The delivery note must be endorsed before the truck leaves.

The recording of results acts as the crew's legal safeguard: every measured value, whether compliant or deviating, must be recorded on the delivery note and entered into the site journal with the exact time, mixer truck number and destination structural element. In the event of a subsequent dispute over honeycombing or inadequate compaction, this traceability proves the masonry contractor's strict adherence to the rules of the art.

Frequently asked questions

Can water be added to the mixer truck if the slump is too low?

No. Adding water on the construction site alters the water/cement ratio, lowers final compressive strength and increases drying shrinkage with high risks of cracking. If the required consistency class is not achieved, only a compatible plasticiser, dosed and recorded in formal agreement with the ready-mix plant, may be added to the mixer drum, followed by thorough mixing before a new verification test.

What tolerance applies to concrete ordered as class S3?

For consistency class S3, where the target slump is between 100 and 150 mm, standard SIA 262 and reference concrete standards permit a deviation of plus or minus 20 mm during compliance checks on the construction site. A reading below 80 mm or above 170 mm requires an immediate re-test and prohibits direct pouring.

What should be done if the concrete completely collapses upon demoulding the cone?

A complete collapse indicates a shear slump or non-cohesive fluid concrete, often caused by excess water or an overdose of admixture. This test is non-compliant. The test must be repeated immediately. If the phenomenon persists on the second sample, the delivery must be rejected: the risk of segregation, severe bleeding and porosity in the finished formwork renders the material unsuitable for casting.

How is a delivery rejection recorded on the delivery note?

The team leader clearly writes the statement "Concrete rejected for out-of-tolerance consistency" on the delivery note, together with the exact value measured in millimetres and the test time. They sign it, have it countersigned by the mixer truck driver, keep the company's carbon copy and immediately send a copy to the site agent for notification to the batching plant.

Texts and standards cited

  • CO art. 365Material and ground: contractor's liability for supplied material and duty to notify the client immediately if the material is defective (para. 3)
  • norme SIA 262Structural concrete: specification, properties, production and conformity for civil and building structures