Key takeaways
- Check the condition of the safety latch, the absence of deformation, and the load capacity tag before any attachment.
- A sling angle greater than 60 degrees from the vertical is strictly prohibited.
- The damaged lifting accessory must be destroyed immediately to prevent any reuse on the construction site.
- Any scrapping and periodic inspection must be entered without delay in the lifting gear register.
SUVA directives and immediate visual inspection before each attachment
On a building construction site, steel wall formwork panels and heavy formwork components generate extreme pull-out and friction stresses. A lifting accessory must never be regarded as a permanent tool, but as a safety consumable subject to constant wear. In accordance with SUVA directives on lifting gear, the slinger or mason carries out a systematic visual check of the two- or four-leg chain sling, shackles, and hooks before latching any connection onto the formwork lifting lugs.
- Inspection of identification and working load limitCheck the presence, legibility, and secure attachment of the metal identification tag on the master link. It specifies the working load limit (WLL) according to authorized opening angles and the nominal link diameter.
- Examination of the chain and mechanical connectorsVisually inspect each leg along its entire length. Look out for plastic deformations: visible link elongation, crushing, twisting, deep nicks, or impact marks caused by collisions with formwork stiffeners.
- Inspection of the hook and its latchCheck the throat opening of the hook: any deformation exceeding original tolerances requires immediate withdrawal. The safety latch must be present, undistorted, and close fully under its spring action without excessive lateral play.
- Verification of pins and shacklesEnsure that assembly shackles retain their original split cotter pin or have their bolt fully tightened down. The use of bent reinforcing steel or twisted wire to replace a calibrated pin constitutes an immediate, mortal danger.
Calculation of sling angles, scrapping criteria, and register keeping
The inclination of sling legs radically alters internal mechanical stresses. The wider the angle from the vertical becomes, the more the tensile force imposed on each chain increases exponentially. According to recognized lifting practice and safety regulations, the included angle formed by two opposing legs must under no circumstances exceed 120 degrees, which corresponds to an inclination angle of 60 degrees from the vertical. Beyond this, the load multiplication factor destroys the safety margin of the gear.
| Angle to the vertical (β) | Total included angle | Load factor on the leg | Residual capacity of a 2-leg sling (10 t base) |
|---|---|---|---|
| 0° to 45° | Up to 90° | 1.40 | 10.0 tonnes (100%) |
| 46° to 60° | 91° to 120° | 1.00 | 7.1 tonnes (71%) |
| > 60° | > 120° | Prohibited | Use strictly prohibited |
The team leader or site foreman orders scrapping without concession as soon as a critical wear criterion appears. For a lifting chain, this includes: average wear on link thickness exceeding 10% of the nominal diameter measured with a vernier calliper, pitch elongation exceeding 5% on a single link or 2% along the leg, a gouge, a fatigue crack, or accidental exposure to a blowtorch flame. For textile slings or auxiliary webbings, any stitch breakage, clear cut on a sheet metal edge, or deep impregnation with aggressive cement grout results in immediate withdrawal from service.
To ensure that scrapping is effective and to satisfy the general prevention provisions of art. 3 OPA, any decommissioned accessory must not simply be set aside: it must be made permanently unusable on the spot by cutting through the hook or master link with an angle grinder. Every inspection, annual visual check by a competent person, and equipment destruction is immediately entered in the construction site lifting accessories register, noting the serial number of the gear, the inspection date, the reason for decommissioning, and the signature of the person in charge.
Mechanical behaviour of slings under asymmetric loads and friction
On a building construction site, the rigging of a wall formwork panel or a stack of man-portable units very rarely represents a homogeneous, symmetrical load. Initial striking of formwork mobilises a breakaway force that alters the theoretical distribution of tensions across the sling legs. When the centre of gravity of the load does not align with the crane hook's vertical axis, two out of four legs absorb the entire dead weight combined with the suction effect of laitance residues. Assuming that a four-leg chain sling distributes the load equally leads to severe undersizing of the gripping accessory.
The opening of sling legs generates a geometric compounding of tensile stresses. As soon as the included angle between two opposite legs exceeds recommended tolerances, the axial tensile force in each link or wire rope quickly surpasses the actual weight of the suspended panel. If a stop-end panel is lifted with legs that are too short, the angle opens excessively, creating horizontal shear forces capable of deflecting the top waler of the wall panel or shearing off the pin of proprietary lifting lugs.
| Angle to the vertical (β) | Total included angle (α) | Tension multiplier factor | Effective residual capacity |
|---|---|---|---|
| 0° to 45° | 0° to 90° | 1.00 to 1.41 | 100% of working load limit |
| 46° to 60° | 91° to 120° | 1.42 to 2.00 | 70% of working load limit |
| > 60° | > 120° | > 2.00 | Prohibited for lifting wall formwork panels |
Direct contact between chains or synthetic slings and the sharp steel edges of a formwork panel is the primary cause of premature failure. Choke hitching without protective sleeves severs the fibres of a webbing sling or subjects chain links to bending stresses. Using suitable edge protectors or certified straight shackles, properly inserted into the anchor plates provided by the formwork manufacturer, prevents the onset of shear failure.
Traceability, workshop inspection, and systematic scrapping
A lifting accessory is a wearable component subject to harsh environmental conditions: impacts against reinforced concrete, grout splatters, adverse weather, and abrasive friction. Under recognized best practice and art. 3 OPA, the employer must maintain work equipment in a condition that ensures worker safety. Every chain sling, textile sling, lifting beam, or lifting clamp must carry permanent marking indicating its working load limit (WLL) and individual identification number.
- Chain slings: scrap if nominal link diameter wear exceeds 10%, in case of single link elongation exceeding 5%, or visible deformations (twisting, crushing, severe nicks).
- Textile slings: immediate withdrawal if the protective sleeve is torn exposing the load-bearing core, in case of chemical burns from release agents, or if the identification tag is torn off or illegible.
- Assembly components: rejection of hooks whose throat opening has increased by more than 10%, shackles with distorted pins or loose threads, and broken or seized safety latches.
- Identification tags: any chain whose round or dodecagonal metal tag certifying its grade rating is missing must be taken out of service immediately.
The internal organisation of the masonry contractor relies on a register of lifting appliances and accessories managed jointly by the site foreman and the yard manager. This register documents the commissioning date, records of annual periodic inspections performed by a competent person, and decommissioning reports. The Ordinance on Machine Safety requires declarations of conformity and inspection certificates to be retained throughout the entire service life of the lifting gear.
Lifting incident and sling failure: procedure to follow on the construction site
When a slinging accessory fails, undergoes sudden deformation, or the load tilts during formwork handling, immediate action on the construction site dictates the physical safety of the teams. In accordance with OTConst, the obligation to protect work areas against falling materials requires the immediate stoppage of the lift. The crane operator locks slewing and trolley movements, lowers the load to the ground or onto a stabilised area if kinematics allow without aggravating the failure, and refuses any further handling.
- Immediate cordon and securingEvacuate personnel from the crane slewing radius and cordon off the potential impact zone on the ground. No worker must approach a suspended load in an unstable balance or held by a single remaining leg under tension.
- Equipment isolation and seizureAs soon as the load is set down, immediately withdraw the entire set of affected slings, along with associated shackles, hooks, and lifting lugs. Lock this equipment away under key to prevent any clandestine reuse by another team.
- Technical joint inspectionThe site foreman examines the geometry of the failure: crushed link, hook opening without latch, shear across a sharp edge without sleeve, or pull-out of an anchor point on the steel formwork. Photograph the condition of the components and record markings on the load tag.
- Notification and removal from inventoryRecord the incident in the site logbook and in the lifting gear inventory register. Order the permanent scrapping of the defective equipment by physically neutralising it with a cutting torch or angle grinder.
The employer and their representatives on the construction site remain required, pursuant to art. 82 LAA, to take all preventive measures adapted to operating conditions. Following a near-miss or accessory failure, root cause analysis determines whether the force exceeded the working load limit due to underestimating the adhesion of fresh concrete or an excessive included angle. Damaged equipment is struck from the inspection register, and teams receive a formal refresher on operating limits before any resumption of wall formwork panel cycles.
Frequently asked questions
What should be done if the identification tag of a four-leg chain sling is torn off?
The absence of an identification tag makes the chain sling immediately non-compliant and prohibits its use on the construction site. Even if the links appear intact, the working load limit and annual inspection traceability can no longer be guaranteed. The sling must be taken out of service, tagged as defective, and sent to the central workshop or an inspection agency for proof testing, recalibration, and fitting of a new official marking tag.
How should a scrapped textile sling be physically neutralised?
Simply tossing a worn webbing sling into a skip exposes it to the risk of a worker retrieving it for improvised lifting. Scrapping requires immediate, visible physical destruction: cut the legs into several sections using a utility knife or shears, and imperatively slice through the sewn end loops. The pieces are then disposed of with the appropriate construction waste.
Can the bent safety latch of a formwork hook be cold-straightened?
It is strictly forbidden to straighten a distorted latch or tamper with its return spring. A distorted latch often indicates an impact or improper seating of the lifting point during a previous lift. The hook loses its anti-unhooking latching function. The complete assembly must be replaced with an original manufacturer-certified repair kit, fitted by a competent person according to maintenance instructions.
Who must record scrapping in the lifting accessories register?
The site manager or the competent person designated for safety records the decommissioning in the equipment register. The entry specifies the serial number of the accessory, the exact date of withdrawal, the observed technical defect (such as a sheared edge or deformation), and the disposal method applied. This update guarantees full traceability of equipment assets during company safety audits.
Texts and standards cited
- OTConstprotection against collapse of structural elements or falling objects and materials: at workstations and access routes, measures must be taken so that workers are not endangered.
- LAA art. 82general prevention rules: to prevent occupational accidents and occupational diseases, the employer shall take all measures shown by experience to be necessary, which the state of technology allows to be applied and which are adapted to the given conditions; workers shall assist the employer (in particular, they must use personal protective equipment).