SUVA safety, hygiene, and workstation obligations: the execution standard
This section brings together all the legal, health, and safety obligations directly applicable to the workstation in masonry and special civil engineering works. Intended for team leaders, site foremen, and site managers, it addresses the daily risks that govern the continuation of operations: silica dust extraction, skin protection against cement, trench access, materials handling, and noise management. It also specifies the procedure to follow in the event of a SUVA inspection and a construction site shutdown.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
1 m 50
Minimum depth requiring sloping or shoring for unbraced excavations
1 m
Minimum ladder extension above the upper edge of the excavation
19 to 21%
Required proportion of oxygen by volume in ambient air at the workstation
50 cm
Minimum clear walkway to be maintained along a shored excavation
Scope and limits of the section
Safety management at the workstation is a core duty for construction site supervisors. In accordance with LAA, the employer is required to take all preventive measures necessary in the light of experience and the state of the art to protect workers' health. On the ground, this general obligation translates into strict rules aimed at eliminating the risks of accidents and occupational diseases.
Applying the rules of the art is essential to avoid exposing staff to serious hazards. Deliberate failure to implement protective measures can lead to criminal liability for supervisors under CP, which penalises breaches of the rules of the art of building when endangering others.
Reading pathway and construction site priorities
The ten chapters of this section provide practical answers to issues encountered during masonry and excavation works. The sequence follows the logic of anticipating major risks that could shut down the construction site or harm health over the long term.
- Workstation health: source extraction of crystalline silica and prevention of cement burns during concreting operations.
- Access and confined spaces: securing trench descents with fixed ladders and monitoring deep atmospheres.
- Plant and lifting: compliance with safety clearances around dumpers and visual inspection of formwork panel slings before every manoeuvre.
- Environment and noise: regulatory demarcation of trenches on public roads and selection of appropriate hearing protection.
- SUVA compliance: managing inspection procedures and lifting work stop orders.
🦺 Chapters in this section 10
Respirable crystalline silica in masonry: limit value and source extraction
Master the extraction and vacuum systems required to protect your masons from silicosis risks.
SUVA safety, health and workstation requirementsExcavation access: ladder, head extension and mandatory securing
Discover the fixing and extension requirements for access ladders to prevent falls into excavations.
SUVA safety, health and workstation requirementsSafety clearance from machinery: slewing radius, blind spots and dumper traffic
Demarcate working zones for construction site plant to safeguard masons against crushing risks.
SUVA safety, health and workstation requirementsManual Handling in Masonry: Reasonable Limits and Lifting Aids
Reduce the strain of manual handling by incorporating lifting aids suited to masonry blocks.
SUVA safety, health and workstation requirementsCement burn: why cement burns, how to protect against it and immediate steps
Adopt sound hygiene and equipment practices to neutralise the corrosive action of fresh cement on the skin.
SUVA safety, health and workstation requirementsSlinging wall formwork panels and forms: inspecting lifting accessories before each use
Apply the check protocol for slings and accessories before each lift of a formwork panel.
SUVA safety, health and workstation requirementsDemarcating an excavation on public land: signage, pedestrian protection and authorisation
Secure your trench footprints on public roads in accordance with cantonal road signage rules.
SUVA safety, health and workstation requirementsWork in deep excavations: atmosphere, ventilation and surface monitoring
Organise forced ventilation and surface monitoring during interventions in deep excavations.
SUVA safety, health and workstation requirementsNoise in masonry: highest-exposure tasks, thresholds and hearing protection selection
Select effective hearing protectors for concrete chasing, cutting, and vibrating phases.
SUVA safety, health and workstation requirementsSUVA work stoppage on a non-compliant excavation: procedure, consequences and resumption
Manage the remediation procedure and reopen your construction site following a SUVA shutdown decision.