Key takeaways
- Monitor the atmosphere prior to any descent using a calibrated multi-gas detector sampling from the bottom of the excavation.
- Breathable air must strictly contain between nineteen and twenty-one percent oxygen at the workstation.
- Continuously blow in fresh air towards the bottom without recycling engine exhaust fumes.
- Maintain a dedicated surface attendant equipped with a rescue tripod without ever descending to carry out a rescue.
Atmospheric detection and forced ventilation at the bottom of trenches
In narrow excavations, shafts or deep trenches, heavy gases accumulate by gravity while ambient air stagnates without natural circulation. Carbon monoxide from combustion engines positioned nearby, carbon dioxide released from organic soils, or hydrogen sulphide from defective sewer pipes create deadly invisible and odourless pockets. The risk of anoxia or sudden poisoning occurs without warning signs: descending a few ladder rungs is enough to lose consciousness.
Ambient air at workstations contains between 19 and 21% oxygen by volume and the limit values for hazardous substances are not exceeded (para. 1); hazardous substances are evacuated to the open air, filtered or diluted by artificial ventilation (para. 2); air quality is monitored regularly (para. 4).
art. 33 OTConst
- Prior measurement from the surfaceInsert a telescopic probe or sampling hose connected to a suction pump down to the lowest point of the excavation. Concentrations must strictly be recorded at different vertical levels before authorising access for bricklayers or pipelayers.
- Commissioning of the mechanical fanPosition the fresh air intake upwind of prevailing winds, well away from exhaust pipes of generators and excavators. Deploy a flexible spiral duct down to approximately 30 to 50 cm from the base slab to flush stagnant gases upwards towards the exit.
- Continuous monitoring at the workstationAttach an individual direct-reading multi-gas detector to each worker's harness, in the breathing zone (collar or chest), with audible, visual and vibrating alarms activated.
Role of the surface attendant and rapid extraction procedure
Working alone at the bottom of a deep excavation is strictly prohibited whenever a risk related to atmosphere or accessibility exists. A dedicated lookout, specifically trained in rescue manoeuvres, must be stationed permanently in the immediate vicinity of the excavation. This person takes part in no handling tasks, never leaves their observation post, and maintains uninterrupted visual or voice contact with the team working below.
| Configuration | Mandatory surface equipment | Immediate evacuation protocol |
|---|---|---|
| Vertical shaft or blind chamber | Aluminium tripod with certified rescue winch and retractable fall arrester | Direct hoisting of the worker strapped into their full body harness. |
| Shored trench with offset access | Caged ladder or fixed landings kept clear, basket stretcher ready at the top | Voice guidance for a conscious, mobile casualty or lifting via mobile davit. |
| Connecting tunnel or deep culvert | Lifeline installed with mobile fall arrester, remote horizontal pulling system | Horizontal evacuation towards the access shaft under continuous assistance. |
Continuous measurement protocols and ventilation instructions in narrow excavations
As soon as laying or pipe connection works take place below ground level, air is no longer naturally renewed. The stagnation of heavy gases such as carbon dioxide or hydrocarbon vapours creates an invisible asphyxiating layer at the bottom of the excavation. The obligation to maintain a breathable atmosphere relies on repeated instrument checks and constant mechanical ventilation, especially when legacy pipelines or disturbed ground are exposed.
Ambient air at workstations contains between 19 and 21% oxygen by volume and the limit values for hazardous substances are not exceeded (para. 1); hazardous substances are evacuated to the open air, filtered or diluted by artificial ventilation (para. 2); air quality is monitored regularly (para. 4); if technical or organisational measures are insufficient, respiratory protective equipment must be used (para. 5).
art. 33 OTConst
Monitoring is not limited to a one-off check before bricklayers or pipelayers descend. Gases can migrate through permeable backfill pockets or suddenly escape when penetrating an existing main. The use of a calibrated multi-gas detector is mandatory in the immediate breathing zone, combined with a sampling probe lowered to the base before any entry.
| Measured parameter | Alert threshold | Immediate hazard at the bottom | Required corrective action |
|---|---|---|---|
| Oxygen (O2) | Below 19% by volume | Depletion asphyxiation without warning signs | Immediate evacuation and start-up of forced ventilation |
| Carbon monoxide (CO) | Exceedance of occupational exposure limit value | Acute poisoning from neighbouring combustion engines | Shutdown of surface plant, directed blowing of fresh air |
| Hydrogen sulphide (H2S) | Exceedance of occupational exposure limit value | Instant loss of smell then respiratory paralysis | Extraction of operatives, remediation before re-entry |
| Explosivity (LEL) | Above 10% LEL | Explosion risk upon contact with power tools | Power shutoff, area cordon, explosion-proof ventilation |
For mechanical ventilation, blowing in clean air drawn well away from the exhaust gases of excavators or generators remains the only effective method. Flexible ducting must descend to within approximately fifty centimetres of the bottom to sweep the working area and force dense gases towards the surface, thereby avoiding mere closed-loop circulation.
Surface surveillance system, rescue and emergency lifting equipment
Working alone at the bottom of a narrow excavation represents a situation prohibited by SUVA safety rules. The continuous presence of an attendant posted at the crest of the slope or along the shoring constitutes the core element of the safety setup. This operative maintains uninterrupted visual or verbal contact with the team below and must under no circumstances abandon their post or be assigned secondary logistical duties.
- Positioning the tripod or davitInstall a certified extraction anchor at the head of the excavation, on stabilised ground or secured directly to the shoring head, equipped with a recovery rescue winch compliant with work equipment regulations.
- Permanent tethering of the workerEquip the descending worker with a full fall arrest harness permanently connected to a retractable fall arrester incorporating an emergency winching function.
- Active visual and voice monitoringThe surface attendant monitors the verticality of the wire rope to prevent friction against trench struts and ensures the portable detector remains active without audible or visual alarms.
- Emergency extraction procedureAs soon as an operative falls ill or a gas alarm sounds, operate the winch from outside to hoist the casualty without exposing additional personnel to the contaminated atmosphere.
The complete equipment set, including the regularly calibrated detector, mobile supply fan, and tripod lifting system represents a capital investment in the region of 4,500 to 8,500 CHF depending on the configurations selected. For a detailed breakdown of provision and depreciation costs for this equipment on your civil engineering construction sites, visit our dedicated section /soumissions/.
Procedure in the event of an atmospheric alarm and emergency rescue
As soon as a multi-gas detector triggers an audible and visual alarm or the flow of forced ventilation suddenly cuts out, immediate evacuation takes precedence over any other action. At the bottom of the excavation, pockets of heavy gases or oxidiser depletion leave no time for hesitation. Incident management requires strict discipline between the worker below and the attendant stationed at the surface.
- Alarm and spontaneous evacuationThe bricklayer puts down their tools without attempting to pack up equipment and immediately reaches the access ladder or exit cage. At the surface, the attendant visually confirms the evacuation and prohibits access to anyone else.
- Loss of consciousness and extraction without descendingIf the worker collapses at the bottom of the excavation, the surface attendant applies the absolute rule: never descend into the excavation. Extraction is carried out exclusively from the surface using the certified rescue winch mounted on a davit or tripod, permanently connected to the operative's harness via the lifeline wire rope.
- Calling professional emergency services and maintaining air supplyThe attendant immediately dials 118 (or 144 depending on the situation), explicitly stating a confined space accident and suspected presence of gas. The forced ventilation unit is kept at full output to continue diluting the toxic or anoxic pocket at the bottom of the excavation.
Once the operative is extracted and placed in the recovery position in the open air, first aid is administered while awaiting the ambulance. Resuming work in the excavation remains strictly prohibited until a technical investigation has determined the origin of the contamination (geological pocket, exhaust gases drawn into the duct, stagnant methane, or pipe leak) and verified that a safe atmosphere has been restored.
Frequently asked questions
What should be done if the atmospheric monitor alarms when the worker feels fine?
Evacuation must be immediate. Dangerous gases such as carbon monoxide or oxygen-depleted atmospheres are completely odourless and cause asphyxiation before the onset of physical symptoms. The worker never questions an alarm: they return to the surface without delay. The foreman inspects the device, checks calibration in clean air, and analyses air composition before contemplating any re-entry into the excavation.
Is the surface attendant allowed to carry out other tasks nearby?
No. The surface attendant is dedicated exclusively to continuous visual and auditory surveillance of the workers below. They may not receive concrete deliveries, banksman a crane, or handle materials on the edge protection berm. Their permanent presence at the edge of the trench, within reach of the lifting davit, ensures immediate engagement of the extraction winch and prompt emergency dispatch.
Where should the forced ventilation intake be positioned to avoid worsening the situation?
The fan's fresh air intake must be located several metres from the excavation, strictly upwind of prevailing winds and well away from any combustion engine (compressors, generators, concrete mixer trucks). Positioning the suction near an exhaust pipe would directly pump carbon monoxide down to the bottom of the excavation, creating an acute, lethal poisoning risk for the bricklayer working at the toe of the shoring.
What requirements govern air quality at earthwork workstations?
OTConst art. 33 specifies that ambient air at workstations must contain between 19 and 21% oxygen by volume, without exceeding occupational exposure limit values for hazardous substances. Pollutants must be evacuated, filtered or diluted through artificial ventilation, alongside regular atmospheric monitoring. In addition, art. 82 LAA requires the employer to implement all necessary preventive measures adapted to site conditions.
Texts and standards cited
- OTConst art. 33air quality: ambient air at workstations contains between 19 and 21% oxygen by volume and limit values for hazardous substances are not exceeded (para. 1); hazardous substances are evacuated to the open air, filtered or diluted by artificial ventilation (para. 2); air quality is regularly monitored (para. 4); if technical or organisational measures are insufficient, respiratory protective equipment must be used (para. 5).
- LAA art. 82general rules of prevention: to prevent occupational accidents and diseases, the employer shall take all measures shown by experience to be necessary, applicable according to the state of technology, and adapted to the prevailing conditions; workers shall assist them (in particular, they must use personal protective equipment).