🧱 CFC 201 / 211.0Foundations, rafts and protection of underground structuresChapter 6 of 10 in the section

Micropiles and soil grouting: underpinning an existing foundation

This chapter details the underpinning of failing foundations using bored micropiles and consolidation grouting. You will learn how to structure hit-and-miss bay excavation, lock in the interaction with the existing structure in accordance with standard SIA 267, interpret tensile load tests, and define immediate hold thresholds during topographic monitoring.

Key takeaways

  • Excavation beneath footings must strictly be carried out in alternating bays not exceeding two metres in width.
  • Standard SIA 267 governs geotechnical design and the formal validation of bearing capacities.
  • The preliminary tensile load test confirms the bond and validates the unit skin friction assumptions.
  • Continuous millimetre-accuracy topographic monitoring governs the continuation of drilling and triggers emergency stops.

Hit-and-miss bay excavation and drilling: execution method beneath existing footings

Underpinning degraded masonry or concrete requires that a continuous foundation is never undermined along its entire length. The hit-and-miss bay method consists of dividing the layout into sequentially numbered sections, most often in three or four passes. Only a strictly limited length is excavated beneath the structure, generally between one metre and one and a half metres per pass. The intermediate ground is left in place to maintain sufficient skin friction and passive earth pressure while the active bay is drilled and concreted. This principle prevents sudden decompression of the bearing soil and shear failure of the old footing.

  1. Inspection and manual excavation of the bayCareful excavation using a mini-excavator or by hand beneath the underside of the existing footing, installation of vertical trench support if the depth exceeds one metre fifty in accordance with the construction works ordinance, and removal of deteriorated concrete.
  2. Drilling and installation of tubular reinforcementSet-up of a compact drill rig inside or outside the trench. Execution of drilling to the specified diameter, installation of steel tubes fitted with sleeved grout pipes (manchettes) or self-drilling bars anchored into the competent bearing stratum.
  3. Grout injection and mechanical connectionGrouting the reinforcement with low-pressure cement grout, followed by targeted re-injection via sleeved grout pipes if necessary. After curing, shuttering a reinforced transfer block or dry packing with non-shrink mortar beneath the scabbled footing.

Geotechnical design and sizing of deep foundations, including small-diameter bored elements acting in skin friction, must verify ultimate and serviceability limit states while taking into account the allowable settlement of the existing structure.

norme SIA 267

The connection between the micropile and the retained foundation requires rigorous care. It is generally achieved by constructing a reinforced concrete capping beam that covers the pile head and keys into the old footing via connecting boreholes fitted with resin-anchored steel rebar. Final pinning under the footing is carried out using expansive mortar to guarantee immediate load transfer before any excavation of the adjacent bay begins.

Validation by tensile load testing and hold criteria based on topographic monitoring

The compliance of a micropile does not rely solely on adhering to drilled depths or injected grout volumes. In accordance with accepted geotechnical practice recognised by standard SIA 267, tensile tests on sacrificial or working piles are essential to verify the ultimate skin friction value in the ground layers penetrated. The test consists of applying measured tensile load increments using a calibrated hydraulic jack reacting against a spreader beam or an independent reaction block, while recording micropile head displacement using dial gauges.

Intervention thresholds and site actions during topographic monitoring
Displacement thresholdObserved behaviourOperational measure on the construction site
Less than 1 mmNormal stabilisation of the structure during excavation stages.Continuation of excavation and drilling according to the phasing schedule.
Between 1 mm and 3 mmLocal decompression detected or initiation of footing rotation.Notice to the geotechnical engineer, suspension of adjacent drilling, mechanical propping.
Greater than 3 mm or rate > 1 mm/dayCritical structural movement, onset of ground failure.Immediate work stoppage, evacuation of the trench, emergency shoring beneath the structure.

Topographic monitoring is established as soon as site installation begins by placing prism targets or high-frequency automatic sensors on the facades, wall corners and floors of the underpinned building. Readings are levelled relative to fixed datum points located outside the zone of influence of the works. Alert and absolute hold criteria are recorded in writing before the first bucket strikes the ground. If the hold threshold is reached, the team suspends earth removal, activates temporary bracing, and performs emergency grouting to stabilise the underlying voids.

Pinning micropile heads and bonding beneath existing footings

The load transfer between the degraded footing and the bored micropiles constitutes the critical phase of underpinning. Once the tubular reinforcement or bars are bonded into the bearing stratum in accordance with the requirements of standard SIA 267, the mechanical connection to the existing concrete requires careful dowelling and non-shrink concreting beneath the prepared underside.

  1. Scabbling and preparation of the undersideChipping away deteriorated concrete with a light needle scaler or low-pressure hydrodemolition to avoid shaking the residual mass. Exposing sound aggregates and washing thoroughly with pressurised water to ensure bonding.
  2. Drilling and installation of connecting reinforcementInstallation of anchor dowels drilled into the core of the existing footing. Blowing out holes, fixing with epoxy resin or thixotropic mortar according to the civil engineer's drawings, then tying to the bay reinforcement cages.
  3. Shuttering and pouring the pinning beamInstallation of watertight stop-ends forming a hopper on one side to provide sufficient hydrostatic head during pouring. Use of self-compacting or shrinkage-compensated concrete, carefully vibrated.
  4. Dry packing beneath the footing and contact groutingFinal tight packing of the top joint by dry ramming a special non-shrink mortar or injecting an expansive grout through pipes previously installed beneath the old concrete.

Supplementary consolidation grouting and defect management

When the granular condition of the loose ground beneath the footing exhibits significant voids or a risk of fines being washed out by groundwater flow, micropile drilling must be preceded or supplemented by bonding and compaction grouting. These operations use pressure-regulated grout pumps to prevent uncontrolled heave of the structure or uncontrolled hydrofracturing.

Grouting parameters according to ground conditions and geotechnical target
Encountered groundRecommended grout mixTypical injection pressureTarget effect on the structure
Clean sandy alluviumMicrofine cement grout or silica gel0.2 to 0.8 MPaPore permeation without ground displacement
Heterogeneous gravels and ballastStandard bentonite-cement grout0.5 to 1.5 MPaFilling coarse voids and bonding
Fractured clayey siltsQuick-setting cement grout (hydrofracturing)1.5 to 3.0 MPaCreation of a dense grout vein network
Footing underside interfaceNon-shrink expansive microfine cement0.1 to 0.4 MPaIntimate pinning and restoration of direct contact

The execution of access trenches and underpinning drilling alcoves demands absolute rigour regarding the safety of personnel working in confined spaces. In accordance with art. 68 OTConst, earthworks and trenches must be arranged so that falling or sliding materials do not endanger any workers. In the event of unexpected water ingress destabilising the excavation walls or footing movement detected during grouting, the site manager immediately initiates an evacuation and applies the planned consolidation measures.

In the event of verified collateral damage or rapid widening of cracks during grouting works, CO requires the contractor to notify the client without delay of any circumstance compromising the proper execution of the works. Continuous records of injected volumes and delivery pressures are systematically appended to the geotechnical site log.

Settlement crisis management, topographic alerts and stop protocol

In underpinning work, the appearance of unforeseen movement or the exceedance of a deformation threshold demands an immediate response from the foreman. The rigorous application of standard SIA 267 requires prior definition of alert and emergency stop thresholds coupled with topographic monitoring using motorised total stations or high-precision levelling staves.

  • Immediately stop any excavation of new bays and suspend ongoing drilling or grouting beneath the bay in question.
  • Install millimetre telltales or electronic crack gauges across visible defects in the superstructure to determine the failure dynamics.
  • Install heavy mechanical shoring under the toe of the undermined footing or perform emergency backfilling with compacted gravel if the overall stability of the masonry is threatened.
  • Formally notify the client of the situation pursuant to CO to report that ground conditions and structural behaviour compromise the normal execution of the works.
Action plan according to topographic deformation levels
Alert levelMonitoring observationImmediate site actions
Green (nominal)Deformation less than one millimetre per 24 hContinuation of hit-and-miss bay excavation according to the phasing schedule.
Amber (vigilance)Cumulative settlement reaching 70% of the allowable limitDoubling total station sightings, holding the next bay, checking grouts.
Red (critical)Threshold exceeded or acceleration of rotationTotal stoppage, personnel evacuation, heavy propping or emergency expansive resin injection.

Lifting the site hold may only take place after formal consultation between the geotechnical engineering office and the site management. Subsequent technical adjustments routinely involve tightening the micropile grid, reducing the width of excavation bays, or reinforcing the pinning joint.

Frequently asked questions

How should you react immediately if an excavated bay begins to cave in beneath the footing?

Evacuate the workers from the alcove immediately in accordance with OTConst. Never attempt to rush shuttering under a destabilised footing. Immediately backfill the void with run-of-crusher gravel or pumped lean-mix concrete to recompress the subgrade, then inform site management immediately to recalculate the sequence using narrower bays.

Why is a tensile load test carried out rather than a compressive load test?

On an underpinning construction site, basement clearance prevents the installation of the massive reaction frames and kentledge blocks required for a standard compression test. Carrying out a micropile tensile test in accordance with standard SIA 267 directly mobilises the soil-to-grout skin friction along the bonded length using a compact hollow cylinder jack reacting against a rigid bearing plate.

How often should topographic monitoring be recorded during excavation?

During the critical excavation phase of a bay beneath a load-bearing wall, optical prisms must be surveyed at least twice daily: before starting excavation in the morning and at the end of the shift after temporary shoring. If suspicious movements appear or if the ground exhibits soft pockets, continuous monitoring using a motorised total station with automatic alert messaging is required.

What risk does excessive grout injection pressure pose?

A sudden pressure spike during micropile grouting can fracture the foundation soil uncontrollably or cause hydrofracturing. This phenomenon risks heaving the existing footing, which is not reinforced for these uplift forces, shearing the masonry above, or causing complete loss of grout into undetected voids without consolidating the intended ground volume beneath the structure.

Texts and standards cited

  • SIA 267Swiss standard for geotechnics and the design of foundation structures and underground works.
  • OTConstProtection against the collapse of building components or falling objects and materials.
  • COContractor's obligation to immediately inform the client if designated ground is defective or if any circumstance compromises execution.