Key takeaways
- The cantonal discharge permit sets the maximum flow rate and the discharge location for dewatering water.
- Lowering using wellpoints is suitable for loose silty-sandy soils with low permeability.
- Lowering the water table alters effective stresses and risks creating differential settlement.
- Continuous measurement of the pumped flow rate ensures compliance with administrative constraints and the integrity of the excavation.
Administrative procedures and management of dewatering water discharge
Pumping groundwater from an excavation trench constitutes a temporary interference with the water regime. In French-speaking Switzerland, the contractor cannot start dewatering without having first obtained the cantonal discharge permit issued by the cantonal environment department (for example the DGE in Vaud or the OEV in Geneva). The analysis file must specify the impact on the water resource, the estimated infiltration flow rate, and the planned duration of operations.
The choice of receiving environment (clean water network, watercourse, or reinjection into the aquifer) depends on the receiving capacity of the channel and the physico-chemical quality of the pumped water. In the event of infiltration within a protected area, reinjection via recharge wells may be required by the cantonal geologist to prevent excessive unwatering of the aquifer.
| Receiving environment | Mandatory treatment | Monitoring parameters |
|---|---|---|
| Clean water (CW) network | Sedimentation in a baffled settling tank | Suspended solids (SS), pH |
| Watercourse / River | Advanced sedimentation and oil separator | Turbidity, SS, temperature, pH |
| Aquifer reinjection | Fine filtration without air entrainment | Chemical compatibility, dissolved oxygen |
Lowering techniques, flow rate monitoring and settlement prevention
Lowering of the water table is generally carried out using wellpoints or deep filter wells equipped with submersible pumps. The suction wellpoint technique (a network of pipes driven at close centres and connected to a vacuum header) is particularly suitable for silty-sandy ground where the permeability coefficient is medium to low. For highly permeable gravelly deposits, large-diameter wells fitted with screens are preferred.
Lowering the hydrostatic pressure increases the effective stress in the soil, which generates induced settlement under the foundations of adjacent buildings. Before starting dewatering, the contractor must verify that the project includes a monitoring network (piezometers and precision levelling markers on adjacent properties). In accordance with good geotechnical engineering practice and art. 76 OTConst, the proof of slope safety and the stability analysis must take into account water ingress and surrounding loads.
- 1. Deployment of the measuring systemFit a volumetric water meter or an electromagnetic flow meter to the main discharge pipe before any commissioning.
- 2. Preliminary pumping testRecord initial flow rates and the development of piezometric levels in control wells to validate the hydrogeological model.
- 3. Daily monitoring and loggingRecord the extracted volumes daily in the site log and check that there is no turbidity at the settling tank outlet.
- 4. Monitoring of neighbouring propertiesCarry out optical levelling measurements on targets fixed to neighbouring structures to detect the slightest differential settlement.
In the event of a sudden pump stoppage (power failure), the water table rises quickly and can destabilise the excavation faces. A backup power supply via an automatically switched generator is essential on any construction site where trench shoring stability relies on temporary lowering.
Regulatory procedures and discharge permit process
Dewatering a groundwater table during earthworks temporarily alters the local hydrogeological balance. Pumping water from the excavation and discharging it cannot be carried out without a legal framework. In French-speaking Switzerland, groundwater extraction and its discharge into the environment or the sewer network systematically require a cantonal discharge permit, issued by the competent cantonal environmental protection department (for example SENEVE in Geneva, DGE in the canton of Vaud, or SDGE in Valais).
The pumping permit application file must be submitted well ahead of the construction site by the client or their geotechnical engineer. The submitted documents must define the estimated total volume, the maximum pumping flow rate (expressed in litres per minute or cubic metres per hour), the expected duration of drawdown, and the dewatering water treatment concept prior to discharge. Excavation water is often laden with suspended solids (SS) or has an altered pH due to contact with hydraulic binders.
In the event of non-compliance with the criteria set out in the cantonal decision or unauthorised discharge of polluted water, the authorities may order the immediate shutdown of pumping operations. The site manager must keep the dewatering permit on the construction site and maintain the monitoring log up to date.
Implementation of wellpoints, flow rate monitoring and settlement prevention
To lower the water table in loose ground with low to medium permeability (sands, silts, fine gravels), the wellpoints system is preferred. This system consists of driving or drilling a network of vertical screens spaced 1 to 2 metres apart around the excavation perimeter. The wellpoints are connected to a common vacuum header, linked to a vacuum pumping station.
Lowering the water table level causes a change in effective stresses in the surrounding ground. Removing the water uplift pressure increases the self-weight of the dewatered ground, causing induced settlement beneath the foundations of adjacent buildings or existing infrastructure. According to art. 76 OTConst, a safety and stability assessment for the excavation must be drawn up by a geotechnical specialist whenever water ingress or additional loads affect the ground.
| Lowering technique | Suitable soil types | Flow rate profile | Risk of settlement to surroundings |
|---|---|---|---|
| Direct sump pumping | Coarse gravels, fractured rock | High and intermittent | High (washout of fines / piping) |
| Vacuum wellpoints | Fine sands, silts, gravelly sands | Moderate and continuous | Medium to high (consolidation settlement) |
| Deep filter wells | Deep, highly permeable aquifers | Very high | Localised around the cone of depression |
To ensure execution in compliance with the cantonal permit and control the geotechnical impact, permanent flow rate measurement is mandatory. A volumetric water meter or an electromagnetic flow meter must be installed on the main discharge pipe. The foreman records the instantaneous and cumulative flow rates daily on the monitoring sheet.
Alongside monitoring the volumetric flow rate, supervising the neighbourhood requires installing piezometers and precision levelling markers on adjoining structures. Any unexpected increase in extraction flow rate associated with the presence of sand in the settling tank signals a risk of ground scour. In this case, pumping operations must be adjusted immediately by reducing the vacuum or carrying out peripheral water recharge to stabilise the cone of depression.
Incident management and deviation control during excavation dewatering
Water table lowering in an excavation does not always progress according to the initial hydrogeological model. The emergence of water laden with fines, a sudden drop in the measured flow rate, or abnormal settlement on neighbouring structures requires immediate, structured construction site responses before irreversible damage occurs.
- Detection and emergency shutdownIn the event of a settlement alarm (elevation threshold reached on levelling targets) or a sudden pump shutdown, isolate the affected line. Switch pumping to the backup dewatering unit to prevent water from rising in the bottom of the excavation.
- Parameter monitoring and adjustmentMeasure the instantaneous flow rate using a water meter or an electromagnetic flow meter. Compare the value with the maximum flow rate specified in the cantonal discharge permit. If turbidity exceeds environmental requirements, divert the water to the settling tank or the pH neutralisation unit.
- Formal notification to the clientIf the ground encounters unforeseen hydrogeological conditions (art. 365 CO), immediately issue a notice of suspension or technical modification to the client and the geotechnical engineer to resize the dewatering system.
| Observed symptom | Geotechnical / equipment cause | Immediate action by foreman |
|---|---|---|
| Discharge water turbid or laden | Damaged screen or inadequate filter | Reduce flow rate, adjust valve, add a settling tank. |
| Slight drop in water table level | Insufficient mass flow rate or clogging | Flush the wellpoint with clean water (backwashing). |
| Settlement on neighbouring building | Drawdown too deep or too rapid | Limit vacuum, pump in stages, notify the engineer. |
The construction site's responsibility lies in the traceability of extracted water volumes and strict compliance with the permit issued by the cantonal environment department. The pumping instructions must be revised as soon as a measurement discrepancy is identified.
Frequently asked questions
How should one react if the cantonal permit sets a maximum flow rate lower than the actual requirement?
Pumps must never be forced beyond the flow rate limit granted by the cantonal discharge permit. If the flow rate required to dewater the excavation exceeds the authorised volume, contact the civil engineer and the cantonal authority. The earthworks schedule should be adapted, or an additional cut-off wall installed to reduce overall water ingress into the excavation area.
How frequently should the discharge flow rate be measured on the construction site?
Flow rate measurement is carried out daily at the start of dewatering work, then on a weekly basis once the water table has stabilised. The data recorded from the water meter or in-line flow meter must be entered in the site log. In the event of an inspection by the water police or the cantonal department, this register serves as proof of compliance with the granted volumes.
What should be done if the wellpoints suck air instead of dewatering the ground?
Air intake often results from a faulty coupling on the header pipe or excessive vacuum relative to the depth of the water table. Check the tightness of the quick-release couplings on the wellpoints, bleed the vacuum pump, and isolate any wellpoints that are too close to the surface. If the ground permeability is low, adjust the vacuum control valve.
Who monitors the settlement of neighbouring structures during pumping?
Settlement monitoring is the responsibility of the contractor under the direction of the geotechnical engineer. Levelling markers are fixed to the facades of neighbouring structures before lowering commences. The foreman ensures that the surveyor carries out regular precision surveys at key pumping stages to detect immediately any movement or induced settlement.
Texts and standards cited
- CO art. 365materials and site: the contractor is liable for the good quality of the materials he supplies; if materials supplied by the client or the site designated by him are found to be defective, or if any other circumstance arises which compromises the regular or punctual execution of the work, he must immediately notify the client, failing which he shall bear the consequences (para. 3).