🧱 CFC 201 / 211.0Mortars, site-mixed concretes and placement productsChapter 2 of 10 in the section

Concrete delivery note: what to check before unloading the truck

Unloading a concrete mixer truck without previously checking the delivery note poses a major risk to the structure. Within two minutes, the site manager or site foreman must verify the mix compliance, batching time, and the absence of uncontrolled water addition. These essential checks prevent costly disputes and guarantee compliance with contractual requirements.

Key takeaways

  • Checking the delivery note validates concrete conformity according to standard SN EN 206.
  • The maximum time between batching and the end of unloading must not exceed 90 minutes.
  • Any water addition on the construction site without the engineer's order severely alters final strength.
  • Refusal of the delivery requires a written, justified statement on the note, signed immediately.

Verification of SN EN 206 specifications and transport time

As soon as the truck mixer arrives on the construction site, the site foreman or gang leader obtains the delivery note from the driver before any unloading operation. This document constitutes the identity card of the fresh concrete and engages the responsibility of the plant. The first step consists of cross-referencing the identification details with the order requirements and the concreting plan prepared for the structure.

The second priority check concerns time management. The batching plant precisely indicates the loading time or the initial contact between cement and water (the batching time). As a general rule, the maximum tolerated delay between batching and the end of placement on the construction site is 90 minutes for standard concrete without set retarder, at an average ambient temperature of 20 °C.

Systematic inspection points on the delivery note
Delivery note sectionValue to checkRisk in case of non-conformity
Concrete designationStrength and exposure class according to SN EN 206Failure to achieve durability or load-bearing capacity of the structure
Batching timeTimestamp from the asphalt or concrete batching plantOnset of setting in the drum, loss of workability, and poor compaction
Delivered volumeQuantity in m³ matching the purchase orderCold joint during casting of a structural element
AdmixturesRequirement for plasticiser, superplasticiser, or retarderConcrete segregation or premature blockage during placement

If the truck arrives with a significant delay or faces prolonged waiting on the construction site area, the concrete risks having begun to set. Using concrete whose consistency has degraded severely impairs its cover around reinforcement and causes irreparable honeycombing.

Strict management of water addition and justified refusal procedure

A harmful practice consists of adding water into the mixer drum to facilitate pumping or screeding. Uncontrolled water addition alters the water/cement (w/c) ratio, which immediately reduces theoretical characteristic strength and increases drying shrinkage, promoting early cracking of the hardened concrete.

According to art. 365 CO, the contractor is required to notify the client or their representative immediately if supplied material has apparent defects that jeopardise the proper performance of the works. If the delivered concrete does not match the order (wrong class, consistency out of tolerance, critical overrun of transport time), the site management team must refuse the delivery before unloading.

  1. Record the anomalyIdentify the error on the delivery note or carry out a visual or standardised consistency test as soon as the chute is opened.
  2. Notify the driver and the batching plantImmediately inform the mixer truck driver and contact the dispatch manager at the concrete batching plant.
  3. Write the reservation or refusal on the noteClearly write in pen on the note 'Concrete refused', specifying the exact reason (e.g. 'batching time exceeded by 45 min', 'consistency S1 instead of prescribed S3').
  4. Have the parties signHave the annotated note countersigned by the truck driver, keep an original copy for the site logbook, and turn the truck away.

Rigorous tracking of this refusal protects the masonry contractor against financial claims from the supplier and prevents any subsequent disputes. In the event of a dispute over the quality of the hardened structure, the absence of reservations on the delivery note makes it very difficult to prove a defective delivery.

Visual and documentary check of the delivery note upon arrival of the mixer truck

As soon as the mixer truck arrives on the construction site, acceptance of the concrete begins with a systematic check of the delivery note before any unloading starts. The site foreman or gang leader verifies that the delivered concrete designation matches the order placed in accordance with standard SN EN 206 exactly. This documentary check guarantees that the compressive strength class, exposure class, consistency class (slump cone test), and maximum aggregate diameter meet the requirements of the concreting plan.

Mandatory check points on the ready-mix concrete delivery note
Delivery note sectionParameter to verifyConformity criterion / Tolerance
Concrete designationStrength and exposure classComplies with formwork plan and purchase order
TimestampBatching time (plant loading)Total transport and waiting time within prescribed limit
ConsistencySlump class (e.g. S3, S4)Slump measurement compliant without uncontrolled water addition
Water additions'Water added on site' fieldStrictly 0 litres unless formally requested and fully traced

The batching time written on the document constitutes the critical chronological factor. At standard ambient temperature (approx. 20 °C), the time between manufacturing at the plant and the end of unloading must not exceed 90 minutes. In hot weather, this time is significantly reduced, otherwise setting of the binder will initiate in the drum, resulting in loss of workability and a drop in subsequent mechanical performance.

Management of water additions and procedure for issuing a delivery refusal

If the concrete arrives with a consistency that is too stiff compared to the ordered class, no informal addition of water must be carried out by the driver. In accordance with the rules of good engineering practice, any consistency adjustment on the construction site requires the use of a plasticiser or superplasticiser under the plant's responsibility, or a measured addition of water, explicitly recorded and signed on the delivery note by the site representative.

In the event of a major non-conformity (critical overrun of transport time, consistency out of tolerance, concrete beginning to set, or failure to comply with the ordered mix design), the construction site must refuse the delivery. Under the Code of Obligations (CO), the contractor is required to examine the supplied material upon receipt and notify the supplier immediately in the event of defects. In accordance with art. 365 CO, a contractor who receives defective material must immediately inform the client or their representative to avoid bearing the consequences.

  1. 1. Immediate finding and halting of operationsProhibit unloading into the skip or pump as soon as the anomaly is detected on the note or during the visual inspection of the chute.
  2. 2. Written notification on the delivery noteClearly state the precise reason for refusal (e.g. 'Concrete refused: batching time exceeded by 45 min, consistency too stiff') on all copies of the note.
  3. 3. Signatures and collection of evidenceHave the refusal signed by the mixer truck driver, keep the duplicate of the annotated note, and immediately notify the site manager and the concrete plant.

Management of delivery disputes and traceability on the construction site

When the concrete delivered to the construction site does not meet the requirements of standard SN EN 206 or exceeds the permissible slump retention time, the site foreman or site manager must act immediately. A consistency defect, the start of setting in the mixer, or a formulation not compliant with the batching plan exposes the structure to structural strength losses or major durability issues.

  1. Immediate documentary and visual checkCheck the concrete designation (strength class, exposure class, Dmax, consistency) and compare the batching time written on the note with the arrival time of the truck. The maximum transport and unloading time must not be exceeded.
  2. Recording an anomaly and measuring consistencyIn case of doubt regarding workability, immediately carry out an Abrams cone slump test on the construction site. If the result falls outside the tolerances prescribed by standard SN EN 206, stop discharge.
  3. Justified refusal procedureNotify the driver of the refusal, clearly write the precise reason on all copies of the delivery note (e.g. time exceeded, non-compliant consistency, absence of required air-entraining agent), and refuse unloading. Immediately inform the concrete batching plant and site management.
  4. Notification under the duty to notifyIn accordance with art. 365 CO al. 3, the contractor immediately informs the client or their representative of any circumstance compromising the proper or timely execution of the work, such as a defective delivery or a supply disruption.

Frequently asked questions

What should be done if the mixer truck arrives late compared to the batching time?

The exact batching time must be checked on the delivery note. According to standard SN EN 206 and weather conditions, the maximum duration between initial water-cement contact and the end of unloading is generally 90 minutes. If this time is exceeded and setting has begun, you must refuse the truck and record the exact reason in writing on the delivery note.

Can the driver add water to the mixer drum to make the concrete more fluid?

Adding free water on the construction site directly alters the water/cement ratio and drops the mechanical strength of the hardened concrete. Any addition not planned by the batching plant is prohibited under standard SN EN 206. If the construction site requires an exceptional adjustment, the exact volume of water must be measured, approved by site management, and signed on the delivery note.

How is the refusal of a concrete truck legally formalised?

Write 'Delivery refused' in legible lettering on the delivery note, followed by the precise technical reason (slump out of tolerance, non-compliant mix, time limit exceeded). Sign the document, have the driver sign it, keep the duplicate, and immediately notify site management and the manufacturing plant to block invoicing.

What are the contractor's obligations in case of defective material according to the CO?

According to art. 365 CO, the contractor is required to notify the client immediately if the supplied material or circumstances compromise the proper performance of the work. By reporting the concrete defect upon delivery and refusing its placement, the contractor avoids bearing the costs of demolition and reconstruction of a non-compliant structure.

Texts and standards cited

  • SN EN 206Concrete - Specification, performance, production and conformity
  • Code des obligations art. 365Materials and ground: obligation of the contractor to notify the client immediately if any circumstance compromises the regular performance of the work (al. 3)