Skip to content
Website
🧱 CFC 201 / 211.0Foundations, rafts and protection of underground structuresChapter 8 of 10 in the section

Shuttering blocks: filling, compaction and tie continuity

After this chapter, you will be able to determine the height of each pour lift to prevent wall bursting, design a infill concrete with the appropriate rheology, ensure the correct lap of horizontal and vertical bars, and compact without causing segregation or honeycombing detrimental to the durability of the buried wall.

Key takeaways

  • Strictly limit the pour height per lift to one metre fifty to control lateral pressure.
  • Ban unnecessary mixing water by demanding a tight aggregate grading and a suitable plasticiser at the batching plant.
  • Ensure the continuity of reinforcement through meticulous lapping in accordance with the civil engineer's drawings.
  • Small-diameter vibrating poker mandatory to pass through cores without dislodging assembled blocks.

Pour height and mix design: controlling hydrostatic pressure

Precast concrete shuttering blocks constitute an economical permanent formwork, but they are structurally vulnerable during the concreting phase. Unlike rigid metal formwork panels equipped with through tie-rods, the dry-stacked assembly of precast units withstands the lateral pressure of fresh concrete solely through joint friction and the bond of the first bedding mortar layer. Any excess hydrostatic head inevitably causes cracking of the thin web walls, opening of vertical joints, or detachment of the top course, utterly destroying the future concrete cover to the reinforcement.

To reconcile construction site pace and structural safety, pouring must be carried out in successive lifts not exceeding 1.50 m in height, equivalent to six standard courses of twenty-five centimetres. The crew waits for the concrete of the first lift to begin setting before continuing filling, ensuring that hydrostatic pressure does not accumulate at the base. This staging prevents the formation of a shear plane while maintaining system stability.

Mix design governs the homogeneity of the load-bearing core. Infill concrete requires a fluid slump class of type S4, obtained strictly through the addition of plasticisers or superplasticisers and never by uncontrolled water addition on the construction site. A gap-graded mix with a maximum aggregate size Dmax of 12 to 16 mm is essential to flow freely between internal webs without blocking aggregate mass above horizontal reinforcement layers.

Mix design parameters for shuttering block infill concrete
Technical characteristicSpecified valueConsequence of a deviation on the construction site
Aggregate size (Dmax)8 to 16 mmMechanical blockage and honeycomb formation
Consistency classFluid (slump cone S4)Excessive pressure if too fluid, voids if too stiff
Water/Cement ratioLess than or equal to 0.50Loss of strength and shrinkage cracking upon thawing
Binder contentMinimum dosage according to engineerPaste segregation and poor stress transfer

Continuous reinforcement and compaction: ensuring monolithic behaviour without segregation

The structural role of the shuttering block only becomes effective if perfect mechanical continuity between the reinforcing bars and the poured matrix is ensured. Buried walls are subjected to earth pressures and potential pore water pressures that load the member in combined bending and compression. If the connection between the raft starter bars and the vertical reinforcement is defective, the structure separates at the construction joint and water infiltrates at the first frosts, causing block core bursting.

Lap length
Length over which two reinforcing bars overlap in order to transfer the full tensile force from one bar to the other through bond with the surrounding concrete, generally specified as fifty times the nominal bar diameter.

Placing horizontal reinforcement demands constant rigour: ribbed bars rest in the recesses provided in the internal webs of the blocks, spaced at mid-thickness to guarantee cover. At corners and wall ends, corner return bars must strictly comply with the civil engineer's reinforcement drawings. Reinforcement laps must under no circumstances be shortened to reduce scrap cuts, otherwise the wall risks opening under backfilled lateral thrust.

  1. Cleaning the bottom of coresRemove debris and excess mortar accumulated at the base of the wall using compressed air or a water jet prior to concreting to ensure direct contact with the raft.
  2. Checking lap lengthsVerify that vertical bars tied to starter bars project by the regulatory length specified by the civil engineer to transfer shear forces.
  3. Guided insertion of the vibrating pokerLower a small-diameter poker (30 to 40 mm) vertically to the bottom of each core without violently striking the reinforcement or rubbing against dry block walls.
  4. Slow, progressive withdrawalWithdraw the tool in successive stages of ten centimetres as soon as the surface glistens and air bubble release ceases, thereby avoiding laitance pockets.

The contractor remains liable for executing the work in accordance with recognized good practice; in the event of a serious failure endangering stability or safety, art. 229 CP recalls the criminal liability incurred when violating recognized rules of the building trade. In civil and contract law, pursuant to art. 365 CO, the contractor is liable for the proper application of materials and must immediately notify the client of any circumstance compromising proper execution, particularly if block geometry impedes the placement of specified rebars.

Concrete placing: consistency control and management of concreting lifts

The behaviour of concrete shuttering blocks during filling depends directly on hydrostatic head and the concrete's capacity to encapsulate reinforcement without forming air pockets. Inappropriate consistency or excessive rate of rise invariably leads to web wall bursting or inadequate cover. Infill concrete requires a strict balance between workability and cohesion: a Dmax limited to 16 mm, or even 8 to 10 mm depending on core width, and a fluid consistency class enabling uniform flow under moderate vibration.

To ensure the mechanical integrity of the wall before setting, concreting must strictly be organised in successive lifts. The filling rate must be adapted to the setting time of the binder to prevent unpredicted cold joints, while limiting lateral pressure on the precast concrete core walls.

Recommended pouring parameters according to block geometry
Block thickness (cm)Aggregate size Dmax (mm)Target consistencyMax lift height (m)
208 to 10Very plastic to fluid1.00 to 1.25
2510 to 16Plastic to fluid1.25 to 1.50
30 and above16Plastic1.50

Appropriate compaction and structural continuity of reinforcement

Monolithic performance relies on the transfer of tensile and shear forces between the foundation, horizontal reinforcement courses, and vertical ties. Shuttering blocks do not form a watertight structure on their own: the structure derives its stability from the continuous reinforcement cage and solidly placed in-situ concrete. Starter bars projecting from the raft must strictly comply with the anchorage and lap lengths specified in the engineering drawings.

  • Minimum lap length: strictly adhere to the minimum dimension defined by the project (generally around 40 to 50 times the bar diameter), without sharply bending starter bars to compensate for block setting-out misalignments.
  • Positioning horizontal rebars: secure bars in the notches provided on the internal webs of the blocks to ensure regulatory cover without risk of displacement when the skip passes or pump hose discharges.
  • Corner ties and T-junctions: systematically install closed corner return bars ensuring load transfer across structural nodes, prior to starting the pour.
  • Formwork bottom cleanliness: clean cores of all masonry debris, dust, or laitance before concreting, so as not to interrupt continuity between the infill concrete and the raft.

Compacting concrete inside block cavities requires dedicated equipment. Using a standard large-diameter vibrating poker (50 mm or more) dislodges blocks or wedges against rebars, causing immediate local segregation with paste pooling or honeycombing. A small-diameter poker, typically 25 to 38 mm, is required. Vibration must be brief, targeted, and vertical: the poker enters the fresh lift quickly, penetrates 10 cm into the underlying plastic layer to knit the joint, and is then slowly withdrawn without directly touching the internal block walls.

Insufficient compaction or over-vibration produces the same visible failure the following spring: frost shatters thin webs that have debonded from a porous or cavernous core. By adhering to slender pokers, phasing pours in lifts of 1.50 m maximum, and rigidly maintaining reinforcement laps, the wall fulfills its load-bearing role and provides the sound backing required for external waterproofing systems.

Delivery non-conformities: remediation of honeycombing and concreting defects

Identifying aggregate bridging or core blowouts when stripping forms at wall level demands an immediate halt to backfilling operations. The site foreman applies art. 365 CO para. 3 by notifying the site management without delay if an anomaly compromises structural soundness. Poorly filled cores expose steel bars to frost and create leakage paths under groundwater pressure. Any makeshift patch concealed with rich mortar is prohibited under penalty of sanctions under art. 229 CP in the event of endangering others through violation of recognized building rules.

  1. Chipping back and diagnosisScabble hollow areas using a light pneumatic chisel down to sound concrete to expose reinforcement by at least 20 mm on the underside. Clean off dust with compressed air, then saturate the substrate with clean water without leaving a shiny film.
  2. Structural repairInstall rigid, watertight formwork and pour a non-shrink micro-concrete or a fluid pressure-pumped structural grout to fully encapsulate rebars without trapping air.
  3. Treatment of discontinuitiesIn the event of a discontinuity in vertical ties, drill and install additional chemically anchored reinforcing bars in accordance with the specifications of the structural civil engineer.

Frequently asked questions

What maximum pour height per lift must be observed to avoid bursting blocks?

The pour height must not exceed 1.50 m per concreting lift, which equates to 6 to 7 courses of standard blocks. Pouring a greater height generates excessive hydrostatic pressure that fractures concrete aggregate webs and bursts unkeyed vertical joints. Concrete must be allowed to achieve its initial set before starting the next lift.

How should the vibrating poker diameter be selected for shuttering block cores?

Use a vibrating poker with a diameter of 25 to 40 mm at most. A wider vibrator systematically jams between vertical reinforcing bars and internal block webs. The poker must be lowered rapidly to the bottom of the lift and withdrawn slowly, in increments of 10 to 15 cm, to vent air bubbles without causing mix segregation.

Which consistency class should be preferred for shuttering block infill concrete?

Infill concrete requires a fluid S4 or very fluid S5 consistency class, with Dmax limited to 16 mm, or even 8 mm in heavily reinforced sections. Concrete with a plastic S2 or S3 consistency immediately causes honeycombing around horizontal tie bars, as it cannot pass through the notches in the internal webs without segregating under vibration.

What lap length should be provided for horizontal and vertical tie bars?

The standard lap length must reach at least 40 to 50 times the diameter of the bar used. For 12 mm diameter B500B reinforcing steel, the overlap must measure 50 to 60 cm minimum. Horizontal bars must rest at the bottom of the notches provided in the webs and be firmly tied to vertical starter bars to resist concrete displacement forces.

Texts and standards cited

  • CO art. 365materials and site: the contractor is liable for the quality of materials supplied; if materials supplied by the client or the building site designated by the client are found to be defective, or if any other circumstance compromises the regular or prompt execution of the work, the contractor must immediately inform the client, under penalty of bearing the consequences (para. 3).
  • CP art. 229breach of the rules of the building trade: whoever, in directing or executing a construction or demolition project, intentionally breaches the rules of the trade and knowingly endangers the life or limb of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; in the case of negligence, to a custodial sentence not exceeding three years or a monetary penalty.

In the same section