Load-bearing masonry: bricks, blocks, and structural elements: the execution reference
Aimed at team leaders, site foremen, and site managers, this section compiles the recognised good practices for constructing load-bearing masonry in compliance with Swiss requirements. From the bed joint to the storey ring beam, it details the static behaviour of walls, load-path management, execution tolerances, and the tying interfaces essential to ensure the lasting stability of structural shells.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 5
0.4 x h
Minimum bonding overlap for bricks in load-bearing masonry (at least 40 mm)
150 mm
Minimum bearing length on masonry for a prefabricated lintel of standard span
5 / m²
Minimum density of stainless steel wall ties for cavity walls
+5 °C
Minimum ambient and substrate temperature without special measures for cement mortar
8 mm
Maximum permissible out-of-plumb tolerance over the height of a standard storey
Technical scope of the load-bearing wall and boundaries of intervention
Erecting a load-bearing wall requires uncompromising execution rigour regarding the transfer of vertical and horizontal forces. This section deals exclusively with load-bearing masonry designed to support the permanent and live loads of the building: calibrated clay bricks, concrete masonry units, reinforced masonry, dressed natural stone rubble, and load-transfer walls beneath slabs. Every laid element contributes to the overall stability of the structure in accordance with the principles of the SIA 266 standard.
- Works covered: internal and external load-bearing walls, vertical and horizontal ring beams, lintel padstones, cavity walls with stainless steel wall ties, heavy dividing walls, and openings under propping.
- Building physics and geometry: compliance with plumb and flatness tolerances in accordance with the SIA 414 standard, management of structural thermal bridges, and airtightness in accordance with the SIA 180 standard.
- Construction site safety: rigorous application of collective protective measures against collapse and falling objects, in compliance with the provisions of the Construction Work Ordinance.
The stability of a wall does not rely solely on the intrinsic compressive strength of the block or brick, but on the consistency of the mortar, compliance with bonding overlaps, and mechanical tying to the floor slabs. A defect in the toothing or an interruption in a ring beam compromises the entire structural scheme established by the civil engineer.
Execution method and sequencing logic on the construction site
The organisation of a structural masonry construction site follows a sequential building logic. Standard manufactured components must be mastered first before addressing reinforced interfaces, composite structures, and sensitive interventions on existing buildings.
- Manufactured elements and standard bondingModules [M3-01] and [M3-02] establish the geometric fundamentals: thin-bed joint laying with an applicator roller for rectified bricks, and the execution of iron-struck joints on fair-faced concrete blocks, ensuring regularity and resistance to compressive stresses.
- Structural continuity and spansChapters [M3-03] and [M3-04] cover wall confinement: tying of reinforcement bars in corner blocks, concreting without segregation, and precise calculation of the bearing length of prefabricated lintels with their temporary propping.
- Complex walls, stone, and decouplingGuides [M3-05] to [M3-07] address building envelope physics: installing inclined stainless steel ties in cavity walls, laying natural stone with suitable bastard mortar, and flexible connections at the head of non-load-bearing partitions to accommodate slab deflection.
- Alterations, structural openings, and climatic conditionsBooklets [M3-08] to [M3-10] govern high-risk work: assessing existing structural substrates prior to adding storeys, needle underpinning under the scrutiny of art. 229 CP, and managing thermal thresholds to preserve cement hydration during morning frost.
🏗️ Chapters in this section 10
Load-bearing clay block: thin-joint laying and bonding rules
Master roller gluing and millimetric levelling of the base course to guarantee load-bearing capacity.
Load-bearing masonry: bricks, blocks and structural elementsFair-faced concrete blockwork: struck joint, pointing and bond regularity
Achieve flawless fair-faced surfaces thanks to consistent tooling of bed and head joints with a jointer.
Load-bearing masonry: bricks, blocks and structural elementsRing beams in load-bearing masonry: vertical and horizontal continuity and laps
Ensure continuous tying between shear walls and floor slabs through rigorous positioning of ring beam steels.
Load-bearing masonry: bricks, blocks and structural elementsPrecast lintel: bearing length, permissible span and shimming
Prevent crushing at wall heads by correctly dimensioning bearing areas beneath padstones.
Load-bearing masonry: bricks, blocks and structural elementsCavity wall: insulation, stainless steel ties and cavity ventilation
Protect insulation from damp while ensuring wind resistance with compliant stainless steel fixings.
Load-bearing masonry: bricks, blocks and structural elementsNatural stone masonry: bond, quarry stone cutting, and mortar
Succeed in rubble stone wedging and selecting hydraulic binders suited to quarried stone.
Load-bearing masonry: bricks, blocks and structural elementsNon-load-bearing masonry partition: uncoupling and head-of-wall detailing
Prevent cracks beneath slabs by applying flexible joint techniques and slip strips.
Load-bearing masonry: bricks, blocks and structural elementsRaising an Existing Masonry Wall: Bonding, Load Transfer and Substrate Verification
Verify the strength of existing masonry before starting vertical extensions and introducing new loads.
Load-bearing masonry: bricks, blocks and structural elementsCutting an opening in a load-bearing wall: propping, lintel installation and safe removal
Install needles and structural steel reinforcements without risk of settlement during opening works.
Load-bearing masonry: bricks, blocks and structural elementsBricklaying in cold weather: frost threshold, mortar protection and site stoppage
Organise sheeting, hot water, and space heating to lay masonry without loss of ultimate strength.