Key takeaways
- Drilling diameter and depth must scrupulously comply with the mortar technical data sheets.
- Insufficient cleaning reduces mechanical adhesion and leads to premature failure of the anchor under load.
- The temperature of the substrate and resin directly determines the usable working time.
- On-site pull-out testing verifies the actual anchorage without exceeding the yield point of the steel.
Substrate drilling and mechanical preparation of the cavity
Grouting reinforcing bars into existing concrete creates a load transfer node that is invisible once cast. A geometrical error or lack of cleanliness cannot be detected visually after the bar is inserted. Successful anchorage relies primarily on strict compliance with the drilling diameter and depth specified by the technical design office. A hole that is too narrow prevents complete encasement of the ribbed bar by the mortar, creating air voids that eliminate the required friction. Conversely, an oversized hole increases the binder film thickness, leading to excessive shrinkage and premature bar slip under axial load.
- Drilling and locating existing rebarsDrill using rotary percussion or diamond coring according to the injection mortar manufacturer's instructions. Use a mechanical depth gauge to ensure the exact depth specified on the execution drawings without striking the load-bearing rebars of the substrate.
- Initial blowing with compressed airInsert a nozzle to the bottom of the cavity. Inject oil-free air to expel most of the debris and drill dust outwards.
- Mechanical brushing of the wallsUse a cylindrical steel-wire or stiff nylon brush matching the exact diameter of the hole, moving it back and forth with a twisting motion to dislodge embedded particles.
- Final finish blowingResume blowing compressed air from the bottom to the opening until the exhaust jet no longer discharges any visible dust against a witness surface.
Managing dust on the construction site also complies with occupational hygiene regulations set out in the construction work ordinance (OTConst), which mandates source extraction using industrial vacuum cleaners of the appropriate class to protect the health of operators during intensive drilling sequences.
Binder injection, thermal influence, and validation by tensile testing
Mineral-based or synthetic resin injection mortars react critically to temperature fluctuations. On Swiss construction sites, climatic variations between winter and summer alter working times and curing periods. A product stored in cold conditions becomes too viscous to ensure void-free filling at the bottom of the hole, whereas an overheated cartridge initiates flash setting in the mixing nozzle, preventing the full insertion of the rebar to the required embedment depth.
| Concrete substrate temperature | Product consistency | Open working time | Time before loading |
|---|---|---|---|
| From -5 °C to +5 °C | Very viscous, difficult injection | Extended (often > 20 min) | Very long (several hours to 24 h) |
| From +10 °C to +20 °C | Fluid, optimal mixing | Nominal (approx. 6 to 10 min) | Standard according to technical data sheet |
| > +30 °C | Very fluid, risk of running | Extremely short (< 3 min) | Accelerated setting, risk of blockage |
Injection must always start from the bottom of the drilled hole using an extension tube to displace air towards the surface. The rebar is inserted with a slight manual twisting motion. Any readjustment or repositioning of a bar once curing has started permanently damages the mortar matrix and requires drilling a new anchor point.
The performance of post-installed rebars directly affects the overall stability of the structure. When managing or executing these sensitive operations, site supervisors must ensure strict compliance with recognised technical standards, as art. 229 CP penalises endangering the life or physical integrity of persons through breach of the recognised rules of construction.
Checks on hole geometry and cavity cleanliness
On a reinforced concrete construction site, anchoring an additional rebar using chemical grouting governs the overall transfer of tensile or shear forces. Unlike insufficient cover or surface honeycombing, poor adhesion of the injection binder remains completely invisible after curing. If the drill diameter is too tight, the grout film thickness is insufficient to ensure bond; if it is too wide, the mortar undergoes excessive shrinkage and loses its stiffness under axial load. Scrupulous compliance with the dimensions specified by the civil engineer is therefore the first technical safeguard.
The anchorage depth must be measured using a mechanical depth stop fitted to the hammer drill or systematically checked with a steel rule prior to injection. Any incomplete hole directly reduces the bond length calculated to transfer the tensile force. However, even a perfectly dimensioned hole becomes useless if drilling dust coats the concrete walls. Drilling slurry or dust acts as a bond breaker between the mineral substrate and the synthetic or cementitious mortar.
- First blow-out with dry compressed airInsert an extension nozzle right to the bottom of the drilled hole to expel the loose fraction of rock dust outwards.
- Mechanical brushing of the wallsUse a steel-wire brush strictly adapted to the diameter of the drilled hole to dislodge laitance particles embedded in the concrete micro-roughness.
- Second purge blow-outRepeat the injection of oil-free compressed air from the bottom of the hole until the expelled air contains no visible dust.
- Visual inspection and temporary cappingInspect the internal roughness with an inspection light and temporarily cap the opening to prevent water infiltration or debris entry prior to injection.
Temperature effects and tensile testing protocol
The temperature of the concrete substrate and that of the injection cartridges govern the polymerisation rate of epoxy, vinylester, or hybrid resins. In cold weather, chemical kinetics slow down considerably: working time is extended, but full curing time can increase fourfold. Conversely, under direct sunlight or severe summer heat, open time can drop below three minutes, risking rebar seizure halfway through insertion.
| Concrete substrate temperature | Maximum working time | Waiting time before loading | Construction site recommendation |
|---|---|---|---|
| +5 °C to +10 °C | 60 to 90 minutes | 48 to 72 hours | Store cartridges in a warm place before dispensing |
| +10 °C to +20 °C | 20 to 30 minutes | 12 to 24 hours | Optimal mixing and injection conditions |
| +20 °C to +30 °C | 10 to 15 minutes | 6 to 8 hours | Work progressively, bar by bar |
| > +30 °C | Less than 5 minutes | 4 to 6 hours | Protect substrate from direct sunlight |
To formally validate the installation, an axial tensile pull-out test is carried out on a representative sample of grouted bars, generally defined by the civil engineer. This non-destructive test consists of applying a proof load held at a defined level without exceeding the yield point of the rebar. The apparatus comprises a hollow hydraulic ram, a bearing ring positioned far enough from the hole so as not to restrain the concrete pull-out cone, and a calibrated pressure gauge.
- Verification of ram stroke and maintenance of the proof pressure for a stabilised duration.
- Measurement of residual bar slip using a dial gauge reading to hundredths of a millimetre.
- Confirmation of the absence of radial cracking or surface spalling around the injection collar.
- Systematic recording of the obtained values on an inspection report submitted to site management.
If abnormal slip occurs under the proof load, the anchor is declared non-compliant. The failed bar must be abandoned and cut flush, and a new anchor drilled at a minimum distance equal to three times the drill diameter, subject to formal approval by the engineering office. The contractor remains responsible for the conformity of the installed materials and must immediately notify site management of any unforeseen issue in accordance with CO.
Grouting non-conformities: failure diagnosis and corrective measures
On a construction site, the failure of an anchor during tensile testing or the detection of a dimensional anomaly requires immediate cessation of loading. A defective anchor compromises the stability of the construction joint or precast element. According to CO, the contractor must promptly inform site management and the civil engineer of any circumstance jeopardising the works, or bear the consequences.
| Site observation | Probable cause | Immediate corrective action |
|---|---|---|
| Bar slip during pull-out test | Insufficient dust removal (powdery walls) or grout contaminated by standing water | Decommission the hole with a full grout pour. Drill a new offset hole according to engineer's directives. |
| Grout soft or friable after theoretical curing period | Substrate temperature below manufacturer limits or incomplete mixing | Core out the area, completely remove residues, dry, and re-inject under thermal monitoring. |
| Insufficient drilling depth (striking rebar) | Premature stoppage without site management agreement | Use diamond coring subject to engineer approval to cut through the encountered rebar. |
When an axis offset is specified, the new bar must comply with the minimum centre-to-centre and edge distances set by the engineering office. For personnel, safety takes precedence: evacuating drill dust and using respiratory protection prevent the inhalation of hazardous particles, pursuant to LAA which mandates the implementation of all necessary preventive measures.
Frequently asked questions
What should be done if the compressor discharges oil during blowing?
Compressed air contaminated with hydrocarbons deposits a greasy film on the rough surface of the hole, destroying the chemical adhesion of the grout. Work must stop immediately, the air line fitted with a high-performance oil separator, and the cavity mechanically degreased using a suitable stiff brush and a volatile solvent approved by the mortar manufacturer, followed by complete drying.
Can injection mortar be grouted into a water-filled hole?
Most common resins lose mechanical cohesion in contact with non-drained standing water, unless expressly specified for special hydraulic mortars or underwater formulations. If water infiltration is present, free water must be pumped out, the cavity dried using hot compressed air or absorbent swabs, and the moisture state of the concrete recorded before injecting any binder on the construction site.
What load should be applied during the proof tensile test?
The on-site pull-out test does not aim to break the rebar, but verifies proper installation under a proof load specified by the civil engineer. This non-destructive check generally mobilises a precise fraction of the yield strength of the reinforcing steel. The load is held for a set duration using a calibrated hollow ram to verify the total absence of measurable axial slip.
What should be done when concrete temperature drops below the required threshold?
Cold conditions slow down or stop the exothermic reaction of resins and halt the setting of cementitious grouts. Work should be suspended or the concrete mass locally preheated using heating cables or forced-air heaters. Grout cartridges must be stored in a temperature-controlled room until mixing to guarantee the specified fluidity and nominal curing.
Texts and standards cited
- COmaterials and ground: the contractor is liable for the sound quality of the materials supplied; if the material provided by the employer or the ground designated by him is found to be defective, or if any other circumstance jeopardises the proper or punctual execution of the work, he shall immediately notify the employer, or bear the consequences (para. 3).
- LAAgeneral safety principles: to prevent occupational accidents and illnesses, the employer shall take all measures shown by experience to be necessary, applicable according to the state of technology, and adapted to the prevailing conditions; employees shall assist the employer (they shall in particular use personal protective equipment).