Key takeaways
- Early desiccation degrades surface compactness and reduces the durability of the concrete cover.
- Curing duration depends on strength development and ambient meteorological conditions.
- Tarpaulins, curing compounds and wet burlap constitute reference physical protections.
- Accurate recording of measures in the site journal guarantees proof of compliant execution.
Desiccation mechanisms and dimensioning of the protection duration
As soon as floating or trowelling ends, free water present in the fresh concrete evaporates under the combined action of wind, temperature and low relative humidity. When the surface evaporation rate exceeds the bleeding rate, negative capillary tension develops in the still plastic cement paste. Without an immediate physical barrier, this water loss generates tensile stresses exceeding the material's low initial cohesion, causing plastic shrinkage cracking. These microcracks or open tears, often aligned with the upper reinforcement layers, degrade watertightness and open infiltration paths for aggressive agents.
Maintaining a saturated or sealed environment must continue until the surface skin layer reaches at least 50% of the required characteristic compressive strength. This duration varies significantly depending on the binder's hardening rate (rapid, medium or slow) and environmental exposure classes. During summer periods with dry north-easterly winds (bise), the minimum requirement is several continuous days to ensure the absence of detrimental water loss.
| Ambient conditions | Rapid strength development | Medium strength development | Slow strength development |
|---|---|---|---|
| Mild temperatures (> 15 °C), humid weather, no wind | 1 to 2 days | 2 to 3 days | 3 to 5 days |
| Moderate temperatures (10 to 15 °C), overcast sky | 2 to 3 days | 3 to 5 days | 5 to 7 days |
| Strong sunlight, drying bise or cold (5 to 10 °C) | 3 to 5 days | 5 to 8 days | 7 to 10 days |
Selection of curing methods and traceability in the site journal
The choice of curing system adapts to the geometry of the component and subsequent finishing constraints. On raft foundations and large-area slabs, applying a film-forming curing compound by mechanised spraying is the fastest method. This product must be sprayed uniformly as soon as the bleeding water sheen disappears. However, beware of its compatibility with future bonded coverings (bonded screeds, resin waterproofing): in the event of incompatibility, mechanical stripping by shot blasting or planing becomes mandatory before work resumes.
- Maintaining watertight formwork: leaving steel or timber formwork panels in place provides excellent protection against desiccation of vertical walls.
- Moistened geotextile mats: sheets kept continuously moist to the core, covered with polyethylene film to prevent evaporation of the sprinkling water.
- Watertight plastic sheeting: polyethylene sheets at least 150 micrometres thick, carefully ballasted along edges and overlaps to block out wind.
- Wax-based or synthetic curing compounds: uninterrupted cross-spraying onto fresh concrete that is dehydrated at the surface.
In accordance with art. 365 CO, the contractor is liable for the sound quality of execution of the materials used and must report any circumstance likely to compromise the work. Likewise, art. 364 CO reiterates the diligence required in conducting operations. The absence of curing constitutes direct technical misconduct in the event of a dispute over cracking or surface wear with the client.
Consequences of early desiccation and plastic cracking
Premature cessation or absence of protection against evaporation destroys the mechanical characteristics and compactness of the cover. When the surface water evaporation rate exceeds the bleeding rate of the fresh mix, the capillary network undergoes considerable internal stresses. Concrete, lacking tensile strength during its initial hours of setting, tears: this phenomenon generates plastic shrinkage cracking.
- Plastic shrinkage cracking
- Through-cracks or surface cracks, randomly oriented or aligned above top reinforcement, appearing in the first hours after concrete placement and screeding under the effect of sudden water loss through surface evaporation exceeding bleeding.
| Observed pathology | Underlying physical mechanism | Consequence on the finished work | Impact on conformity classes |
|---|---|---|---|
| Surface dusting | Local interruption of clinker hydration due to lack of water. | Powdery surface, total loss of abrasion resistance under traffic. | Loss of performance equivalence of the effective water/binder ratio. |
| Crazing and microcracking | Sharp differential shrinkage gradient between outer skin and core mass. | Opening of preferential capillary paths into the internal matrix. | Immediate vulnerability to freeze-thaw cycles without de-icing salts. |
| Microcracking over reinforcement | Plastic settlement restrained by upper slab reinforcement. | Direct linear cracks along top rebar at the surface. | Drastic drop in carbonation resistance and loss of cover integrity. |
| Increased gas permeability | Open capillary porosity retained due to lack of C-S-H gel formation. | Accelerated carbon dioxide penetration and premature depassivation of steel. | Non-compliance with watertightness requirements specified by the civil engineer. |
Paying for a mix design to meet severe exposure requirements is pointless if hydration of the surface zone is halted after a few hours. The concrete skin becomes porous, absorbent and friable. The concrete thus loses over a few surface millimetres all the mechanical benefit and durability ordered from the batching plant.
Application protocols, curing duration and site traceability
The choice of curing methods depends on the geometry of the component, progress constraints and local atmospheric conditions. The three reference methods on Swiss construction sites remain the retention of watertight formwork, hermetic coverage using moistened geotextile under polyethylene, and uniform spraying of a film-forming curing compound.
- Retaining or closing formworkKeep watertight steel or timber formwork panels in place without premature loosening of tie rods. Exposed upper edges must be immediately protected against wind with ballasted plastic sheeting.
- Hermetic wet coveringLay a soaked non-woven felt as soon as the concrete resists finger indentation. Cover without delay with a polyethylene film of at least 0.15 mm, overlapping sheets by at least 30 cm and ballasting them with timber battens.
- Application of curing compoundSpray paraffinic or acrylic curing compound in regular cross-passes using a knapsack sprayer immediately after the bleed water sheen disappears, ensuring a continuous membrane without gaps is formed.
- Continuation after striking formworkIf formwork striking occurs before the end of the period required by climatic conditions, immediately continue protection by spraying or moistening the exposed vertical faces.
Managing curing duration must adapt to ambient parameters (air temperature, relative humidity, wind) and the hardening kinetics of the cement used. According to recognised codes of practice in Switzerland, an exposed slab in strong wind and dry weather requires absolute vigilance within the first thirty minutes following pouring.
Towards the client and the site management, the material proof of compliant execution of the protection lies entirely with the contractor. In the event of subsequent cracking or dusting, the lack of tangible evidence directly engages the contractor's liability under art. 365 CO al. 3, as the contractor is liable for circumstances compromising the proper execution of the work if site management was not duly notified.
- Twice-daily recording of minimum and maximum temperatures and wind conditions on the construction site.
- Exact logging of the pouring completion time and the precise time protection was installed.
- Statement of the technical method applied: commercial reference of the curing compound, observed coverage rate, or type of sheeting.
- Recording of any periodic re-moistening of geotextiles during hot spells.
- Time-stamped overall and detail photographs illustrating the rigorous maintenance of the protection system.
Management of curing non-conformities and traceability of remedial work
Absence or premature interruption of thermal and moisture curing directly compromises the cover zone. When the evaporation front outpaces the bleeding rate, plastic shrinkage cracking begins before final set. The surface dusts, degrades under friction and loses its impermeability to aggressive agents. According to art. 365 CO, the contractor immediately reports to the site management any climatic anomaly or unforeseen constraint compromising the proper setting of the work, in order to preserve the parties' rights.
- Immediate inspection and joint assessmentAs soon as crazing or linear openings appear, map the defects. Measure crack widths using an optical crack gauge and assess surface hardness to determine the thickness of the desiccated skin.
- Formal entry in the site journalRecord surface temperature, wind, ambient humidity, exact time of concreting, curing method deployed (polyethylene sheeting, curing compound, moistened felt) and the precise moment of its application.
- Emergency protective measuresRe-establish continuous moistening under saturated geotextile without delay or apply watertight sheeting to halt desiccation of underlying layers, preventing aggravation of the shrinkage gradient.
- Definition of repair protocolFor non-through plastic microcracks, agree with the engineer on impregnation with a surface hardener or bridging resin. In case of deep dusting, plan for surface planing followed by a shrinkage-compensating micro-mortar.
The cost of remedial treatment by crack bridging or technical patching ranges from roughly 40 to 110 CHF per treated square metre, depending on accessibility and the required resins. Strict adherence to durations of maintenance under wet protection remains the only guarantee against costly remedial works borne by the executing contractor.
Frequently asked questions
How should one react immediately to plastic shrinkage cracks on a freshly poured slab?
If the concrete is still workable, close the cracks by vigorous manual floating to restore material continuity. Immediately cover the area with watertight sheeting or a geotextile previously saturated with water to stop evaporation. Log the incident, meteorological conditions and time of remedial work in the site journal, then notify site management without delay to arrange monitoring of the hardening process.
Can a curing compound be sprayed directly onto a bleed water surface?
No. Applying a curing compound onto a pool of free bleed water dilutes the emulsion, disrupts the continuous protective film and creates areas of premature desiccation. You must wait for the bleed water sheen to completely disappear, as soon as the surface turns matt, before spraying the product uniformly using a calibrated lance, in accordance with the manufacturer's technical specifications and Swiss application standards.
What should be done if wind dries the concrete surface before the start of setting?
Erect mobile windbreaks urgently around the working area and apply a very fine water mist using an atomizer without washing out the cement paste. You can also roll out lightweight plastic sheeting in gentle contact with the surface without marking the concrete. These measures prevent early cracking while awaiting the application of the definitive curing method planned for the construction site.
What entries regarding curing must the site foreman record in the site journal?
Enter the exact time concrete compaction finished, the minimum and maximum sheltered temperatures, relative humidity and wind force. Specify the protection method applied: geotextile kept moist, ballasted polyethylene sheeting or the reference of the curing compound sprayed with its actual application rate. Finally, note the total duration during which the system was maintained continuously in place.
Texts and standards cited
- CO art. 365material and site: the contractor is liable for the sound quality of the material provided; if the material provided by the client or the ground designated by the client is recognised as defective, or if any other circumstance compromises the proper or punctual execution of the work, the contractor shall immediately inform the client, failing which the contractor shall bear the consequences (al. 3).