🧱 CFC 201 / 211.0Earthworks, excavations and temporary shoringChapter 10 of 10 in the section

Excavation setting out: batter boards, transfer of dimensions, and checks before the first bucket

This chapter details the essential geometric checks required before the first excavator starts on the construction site. The site manager or foreman learns how to carry out joint checks on batter boards, secure level transfers from the official datum, and formalise pre-execution notice to prevent any out-of-tolerance earthworks.

Key takeaways

  • The official surveyor sets out the main gridlines and establishes the absolute reference datum point.
  • The contractor transfers the excavation dimensions, accounting for the thickness of the foundation slab and subbase.
  • Joint checks of diagonals and levels are systematically carried out before the first bucket cut.
  • Formal notice to site management records any geometric discrepancies identified on site.

Erecting batter boards and joint alignment checks

On a Swiss building construction site, defining site boundaries strictly begins with the work of the licensed surveyor. The surveyor establishes legal boundary alignments, property lines, and the main gridlines of the structure, often using survey nails or marker stakes. Once this stage is complete, the operational setting out becomes the responsibility of the masonry and earthworks crew. Erecting batter boards—consisting of sturdy stakes driven outside the collapse zone and linked by planed horizontal timber rails—enables these primary gridlines to be transferred with millimetre precision.

setting-out batter board
A temporary frame made of stakes and rigid horizontal boards, erected outside the excavation area, used to secure string lines marking building gridlines and excavation limits.

Before authorising the plant operator to begin topsoil stripping or bulk excavation, the foreman must carry out a joint check in the presence of site management. This does not involve recalculating the civil engineering office's survey data, but physically verifying the consistency of the layout. Taking fifteen minutes to carry out this check prevents disastrous earthwork rectifications, over-depth excavation backfilled with mass concrete at the contractor's expense, or encroachments onto neighbouring plots.

  1. Tape checking of diagonalsMeasure the diagonals of the rectangles formed by the main gridlines to confirm perfect geometric squareness using the Pythagorean principle.
  2. Validating boundary setbacksCheck distances between string lines on batter boards and boundary markers to ensure strict compliance with minimum setback requirements defined in the building permit.
  3. Transferring excavation working widthsMark the crest line of slopes on the ground with chalk or spray paint, applying the extra widths needed for trench support or working benches.
  4. Mechanical protection of batter boardsRope off and visually mark batter boards to prevent any collision or displacement caused by the slew radius of excavators and dump trucks with skips.

Level transfer and formal notice prior to execution

Vertical setting out demands the same rigour as horizontal alignment. The surveyor provides a fixed benchmark tied to the federal levelling system, established outside the zone of influence of the construction site. The foreman transfers this datum level using an optical site level or a precisely calibrated rotating laser. From this absolute reference level, the crew establishes the raw excavation formation level. This must deduct the total thickness of the foundation build-up: granular subbase, blinding concrete, waterproofing membrane if required, and reinforced concrete slab.

The contractor checks the setting-out data provided by site management and promptly notifies any errors or discrepancies identified on site before starting execution of the corresponding works.

norme SIA 118

An excavation dug just a few centimetres too low incurs unremunerated costs for soil removal or gravel backfill. Conversely, an excavation formation that is too high forces the earthworks contractor to bring back a mini-excavator to shave disturbed ground, undermining subgrade stability. Level checks also include verifying groundwater presence against initial boreholes and checking for unidentified buried services.

Common tolerances for setting out and earthworks in Switzerland
Element to checkRecommended measuring toolPermitted execution toleranceCorrective action in case of discrepancy
Main gridlines on batter boardsLaser measure or steel tape± 5 mmImmediate repositioning of saw cut on rail
Transfer of level datumOptical site level± 3 mmClosed-loop levelling run to secondary benchmark
Unexcavated formation levelGrade laser with receiver staff+ 0 mm / - 30 mmAdjustment of ditching bucket level
Slope crest lineSurveyor's tape and plumb line± 50 mmRemarking line before excavation begins

If the check reveals a discrepancy between engineer drawings, installed batter boards, and the natural ground, works must not proceed blindly. According to art. 365 CO, if the ground designated by the client proves defective, or if any circumstance jeopardises regular execution of the work, the contractor must inform the client immediately or bear the consequences. This pre-execution notice, issued in writing to site management, logs geometric discrepancies and protects the contractor before the first cubic metre of spoil is loaded.

Transfer of benchmarks and guiding the excavator operator

As soon as the official surveyor and site management sign off the setting-out report, the responsibility for on-site physical marking falls to the foreman. Peripheral batter boards must never serve as direct references for the excavator operator: machine vibrations, truck traffic, and risk of bucket impact mean excavation lines must be offset immediately. The team leader marks slope crests and trench bottoms using reference stakes set back from the direct working zone, supplemented by chalk line or plaster marking directly on the stripped subsoil.

  1. Offsetting gridlines outside the excavation zoneDrive sturdy square-timber offset stakes at a minimum distance of 2 m behind the theoretical excavation crest. Transfer the reference datum level (absolute benchmark) using permanent marker tape and write the excavation depth relative to this level in grease pencil.
  2. Calibrating the machine guidance systemWhether the backhoe excavator operates with a dipper-mounted laser receiver or a 3D GNSS/total station system, verify the machine zero on a site benchmark before starting the main cut. The bucket tooth tip acts as the physical reference for checking.
  3. Marking formation level and working clearancesSystematically include clearances of at least 50 cm in ground markings for installing pad or raft formwork, along with the safety berm required at the toe of the slope to direct surface runoff to the temporary sump.
Execution tolerances for unsupported excavations according to Swiss practices
Excavation elementPermitted plan deviationPermitted level deviationConsequence for masonry package
Slope crest± 10 cm± 5 cmRisk of encroaching over boundary line or excess battered excavation
Slope toe / formation boundary± 5 cm± 3 cmInsufficient space for edge formwork or unnecessary over-excavation to backfill
Formation under blinding concrete± 3 cm+ 0 cm / - 3 cmExcess blinding concrete at contractor's expense or risk of insufficient cover

Managing geometric discrepancies and duty to notify before bulk excavation

Bulk excavation is an irreversible operation: uncontrolled over-excavation causes disproportionate costs for unremunerated ground replacement and mass concrete backfill. The contractor has a legal duty to act as soon as a geometric or geotechnical anomaly appears between the engineering drawings and exposed site conditions. Pursuant to art. 365 CO, if ground designated by the client proves defective, or if any other circumstance jeopardises regular or timely completion of the works, the contractor must inform the client or bear the consequences.

Before ordering soil haulage to regional disposal sites, the foreman records the initial condition of neighbouring structures, uncovered services, and slope conformity in the daily site report. SIA standards across structural and contractual series state that any discrepancy between construction drawings and official level datums must stop mechanical excavation in the area of doubt. The fifteen minutes spent checking the level benchmark with an optical or digital site level avoids costly disputes over removed muck volumes and reinforced concrete substructure thicknesses.

  • Systematic verification of formation level every two excavator passes using a telescopic staff held by a mason wearing appropriate PPE.
  • Verification of the actual presence of preliminary drainage runs and soakaways prior to running a vibrating roller over the formation.
  • Immediate stop of the bucket 20 cm above final formation level upon encountering groundwater or unexpected water ingress, with formal written notice to site management.
  • Joint recording of the nature of excavated ground (clean Class A spoil or materials requiring specific sorting) before trucks depart.

Handling identified discrepancies: stop protocol and traceability

When a joint check identifies a discrepancy between batter boards, engineering drawings, and natural ground, the site agent halts excavation on the affected section. Excavating to incorrect dimensions causes over-depths that must be filled with mass concrete, or boundary encroachments impossible to correct without underpinning.

  1. Site inspection and freezing the areaRecord the exact variance with an optical level or total station relative to the surveyor's fixed datum. Photograph the batter boards, string lines, and offset stakes without disturbing any markers.
  2. Formal notice to site managementNotify the discrepancy immediately in writing (email with delivery receipt or explicit entry in the site diary) to site management and the official surveyor, specifying the X, Y coordinates and measured delta Z.
  3. Awaiting written instructionsKeep the excavator out of the affected excavation area until a written instruction approved by the civil engineer or architect establishes the new formation level or slope profile.

According to art. 365 CO, if materials supplied by the client or ground designated by the client proves defective, or if any other circumstance compromises regular or timely execution of the work, the contractor must inform the client immediately or bear the consequences. In Swiss construction, issuing a discrepancy notice before bulk earthworks relieves the contractor of financial liability for corrective excavation works ordered by the surveyor.

Consequences of unreported geometric anomalies
Observed anomalyDirect site riskAction required before earthworks
Horizontal gridline shiftEncroachment beyond legal building envelope or boundary lineSuspension of excavation and realignment by the surveyor
Datum level (Z) errorRaft placed above frost depth or too low for drainage mainsCheck levelling against official benchmark and written notice
Damaged benchmark or batter boardComplete loss of excavation trench alignmentJoint re-establishment documented in the site minutes

Frequently asked questions

Who bears the cost of reinstating a batter board struck by plant?

If a contractor's machine operator or haulage truck knocks down the batter board, surveyor call-out costs to reset the gridlines fall squarely on the contractor. If the damage is caused by a third party outside the site or unexpected ground movement, the contractor immediately records the event in the site diary to claim costs from site management.

Can excavation begin without official surveyor sign-off on batter boards?

No. Even under programme pressure, the first bucket must not break ground for the permanent excavation without the excavation permit or official setting-out certificate. Digging without this joint check exposes the contractor to the full cost of soil removal, engineered backfill, or make-up concrete if the building's position fails to match approved planning drawings.

How can the operator maintain formation levels without a machine laser?

The foreman sets sight rails or fixed boning rods, transferred from the batter board outside the collapse zone. Two horizontal painted rails form a visual sightline, supplemented by a traveller rod held by the chargehand at the base of the excavation. This traditional method ensures strict compliance with the bed level for blinding concrete.

What action is required if the design raft level lies below an unindicated water table?

The site agent stops excavation at the water ingress level to avoid formation softening or hydraulic boiling. They issue a notice of geotechnical anomaly to the civil engineer and site management. Groundwater lowering or sealing measures require a contractual addendum before deep excavation can resume.

Texts and standards cited

  • norme SIA 414Dimensional tolerances in building construction for excavations and structural work
  • CO art. art. 365 COMaterials and ground: immediate notice to client if ground or circumstances jeopardise the work (para. 3)