Key takeaways
- Systematically observe the minimum bearing length specified by the manufacturer or civil engineer.
- Check the permissible span and locate reinforcement markings to avoid any inverted installation.
- Lay the element on a continuous fresh mortar bed to eliminate point-load stresses.
- Maintain rigid temporary propping under composite lintels until the upper concrete has hardened completely.
Calculate the seating and check the permissible span according to the product data sheet
The top corner of a masonry opening constitutes a shear stress concentration zone. Installing a precast lintel that is too short concentrates excessive vertical loads onto the inner edge of the reveal, inevitably causing diagonal cracks in the load-bearing masonry. The bricklayer must check that the finished opening between reveals matches the overall length of the precast element before any lifting operation.
| Clear span between reveals | Minimum bearing length | Type of element | Device under bearing |
|---|---|---|---|
| Up to 1.25 m | 15 cm to 20 cm | Reinforced clay lintel | Continuous M15 mortar bed |
| From 1.26 m to 2.50 m | 20 cm to 25 cm | Prestressed joist / reinforced concrete | Solid brick or reinforced levelling course |
| Over 2.50 m | According to product sheet / engineer | Heavy precast beam | Cast-in-place concrete padstone |
The permissible span stated in Swiss technical documentation must never be evaluated by eye. Certain slender lintels act purely as tension reinforcement in the final stage: they require an upper compression zone, made of masonry with fully filled vertical joints or a cast-in-place concrete upstand, to carry the total load. According to art. 365 CO, the contractor verifies the installed components and ensures that the design span of the profile corresponds to the dead and imposed loads of the project.
Ensure laying orientation, temporary shimming, and load distribution
The laying orientation is a critical point that is often overlooked during fast-paced installation. Prestressed or asymmetrically reinforced lintels contain tension reinforcement concentrated in the bottom part. Installing an element upside down eliminates its tensile strength and leads to brittle failure as soon as the upper slab is loaded. The foreman checks directional arrows, "HAUT / OBEN" markings, and the condition of anchoring stirrups before shimming.
- Preparation of the seatingClean and wet the tops of the reveal walls. Lay an uninterrupted mortar bed to avoid hard point bearings.
- Positioning and inspectionBring the element in using the crane or telehandler, adjust the seating level, and check the symmetry of both end bearings.
- Mid-span proppingPlace one or two adjustable props with a timber spreader plank under the centre of the span before any upper loading, in accordance with the technical data sheets.
- Laying of upper coursesLay the upper masonry courses or cast the levelling concrete, ensuring joints are fully filled to guarantee cohesion of the compression zone.
Shimming beneath the lintel must never be carried out dry with plastic wedge shims or brick scraps. A rigid, point bearing generates a stress peak and shatters the seating brick. Contact must be fully provided by a fresh levelling mortar bed of regular thickness between 10 and 20 mm. According to art. 17 OTConst, measures must be taken so that construction elements do not threaten worker safety: the intermediate support prop remains locked and wedged as long as the floor slab concrete or the upper course mortar has not reached its minimum design strength.
Prevention of corner cracking and management of bearing stresses
Cracking at 45 degrees starting from the top corners of an opening almost always indicates an excessive concentration of shear stresses and diagonal compression. When the bearing length proves insufficient relative to the load path, the underlying brick or block undergoes localised crushing. This local failure leads to lintel rotation and debonding of the bed joint, cracking interior plasters and masonry linings. To mitigate this risk on hollow clay or autoclaved aerated concrete masonry, incorporating a cast-in-place or precast reinforced concrete padstone becomes essential whenever concentrated slab loads exceed the permissible bearing capacity of the block.
| Masonry support | Main risk at the corner | Required distribution device | Alignment tolerance |
|---|---|---|---|
| Standard clay brick | Shattering of cell walls under point load | Mortar bed of specified class with joint reinforcement | ± 5 mm relative to the datum line |
| Autoclaved aerated concrete | Punching shear under the inner edge of the lintel | Rigid shimming plate or padstone cast over at least 25 cm | ± 3 mm on thin-bed mortar |
| Solid or lightweight concrete block | Vertical shear of the first head joint | Fully filled mortar joint levelled without voids under the element | ± 5 mm at reference level |
The mechanical behaviour of the bearing depends directly on the preparation of the mortar bed. Dry-laying a lintel with temporary wooden wedges creates destructive hard spots: the wood deforms under moisture from subsequent mortar or rots, while the load transfer occurs over a surface reduced to a few square centimetres. The seating mortar must imperatively be fully bedded, compacted with a trowel, and exhibit a firm plastic consistency to ensure perfect contact without sagging under the self-weight of the precast unit and the first upper courses.
Application of upper loads and decentring sequence
The transfer of loads above an opening functions according to the composite beam or relieving arch model only if the upper masonry is bonded according to recognised trade rules. When the precast lintel acts solely as a tension chord — frequently the case with thin clay or prestressed concrete plank lintels —, the compression zone is formed by the block courses laid above. This requires full filling of both vertical and horizontal joints over the entire height of the compression zone defined by the civil engineer's structural drawings.
- Installation of intermediate proppingPosition propping towers or adjustable steel props fitted with timber spreader beams beneath the lintel before any loading, observing a maximum spacing in accordance with technical data sheets, generally between 1.00 m and 1.20 m.
- Execution of the compression zoneErect the overlying masonry, ensuring strict bonding of the blocks (overlap of at least 40% of block height) and perfect filling of mortar joints to prevent any cross-section-reducing voids.
- Casting of the slab or ring beamConcreted elements above must be poured avoiding direct skip impacts onto fresh masonry directly above the opening, thereby ensuring the monolithic continuity required by the engineer.
- Progressive decentring under controlRelease the prop jacks only after the upper concrete has hardened completely, proceeding from the centre of the opening outwards towards the bearings to transfer the load without shocks.
In accordance with art. 17 OTConst, measures must be taken at workstations and traffic routes so that workers are not endangered by the collapse of building components or falling materials. During assembly phases above open openings, maintaining props and cordoning off the area below prevents accidents related to premature failure of an element that is not yet structurally tied. Furthermore, according to art. 365 CO, if the contractor identifies an anomaly in the installation drawings, a precast element cracked during offloading, or a non-compliant seating support likely to compromise the structural integrity of the works, they must immediately inform site management.
Bearing non-conformities and defects: remediation measures on the construction site
A setting-out error or an unexpected opening cut frequently leads to a non-compliant minimum bearing length. When the bearing of the precast lintel on the reveal proves to be less than the requirements of the technical data sheet or the civil engineer's drawings, the stress concentration at the top of the masonry risks causing localised crushing of the material and the appearance of diagonal cracks at 45 degrees at the opening corners. Discovering an insufficient bearing or a structural defect requires an immediate halt to upper surcharges and strict compliance with the duty to notify stipulated in art. 365 CO.
- Immediate safeguarding and load reliefInstall adjustable steel props beneath the precast lintel without delay using timber spreader sole plates at least 50 mm thick on the ground, supplemented by locked wedge shims.
- Formal notice to site managementNotify the civil engineer and site management immediately in writing of the insufficient bearing or the onset of cracking below the opening corner before continuing any upper masonry.
- Remediation under technical supervisionExecute the engineer-approved variant: precise sawing to insert a cast-in-place concrete padstone, addition of a bolted steel angle beneath, or complete replacement of the unit with one of suitable length.
If the laying orientation has been reversed (tension reinforcement positioned upwards) or if the permissible span is exceeded due to the concreting of a floor slab, the element loses its bending strength. Pure and simple removal remains the professional standard. The load distribution above must imperatively be halted until the rectified bearing bed has fully cured.
Frequently asked questions
How should you react if the actual bearing length is half that specified in the technical data sheet?
Stop laying the upper blocks and relieve the element with two props and a timber spreader beam. Alert site management in writing according to your contractual obligation. The solution usually requires forming an underpinned reinforced concrete padstone or replacing the lintel with a longer unit. Do not attempt any remedial action by merely adding mortar under the insufficient bearing zone.
What must be done when a precast lintel has been installed upside down on the construction site?
Prestressed or reinforced lintels feature a top face identified by factory markings to ensure the bottom reinforcement works correctly in tension. If the element has been bedded upside down, its mechanical behaviour is invalidated and the permissible span is no longer guaranteed. Prop beneath the opening immediately, carefully dismantle the fresh upper masonry, and turn the lintel the right way up before the mortar sets.
Why does a diagonal crack appear at the corner of the lintel after pouring the floor slab?
This defect indicates an excessive concentration of shear stresses due to an overly short bearing or a hollow bearing masonry not filled with mortar. The shear force tears the corner of the opening. The remedial measure consists of urgently propping beneath the opening to halt movement, then having the cracking inspected by the civil engineer to determine whether steel jacketing or an underpinning beam is required.
Can temporary propping at mid-span of the lintel be removed as soon as the element is laid?
No. Slender or composite lintels require central propping throughout the erection phase of the overlying masonry. The ultimate load capacity depends on the arching action and the strength of the upper compression zone. Removing wedges or props prematurely generates an instantaneous, irremediable deflection and destabilises load distribution above the opening before the binders have fully set.
Texts and standards cited
- CO art. 365materials and ground: the contractor is liable for the sound quality of the materials they supply; if the materials supplied by the client or the ground designated by the client are found to be defective, or if any other circumstance compromises the proper or punctual execution of the work, the contractor shall immediately inform the client thereof, under penalty of bearing the consequences (para. 3)
- CPbreach of the rules of the art of construction: whoever, intentionally, when directing or executing a construction or demolition project, breaches the recognised rules of the art and thereby knowingly endangers the life or physical integrity of people shall be liable to a custodial sentence not exceeding five years or to a monetary penalty; if committed through negligence, the penalty shall be a custodial sentence not exceeding three years or a monetary penalty
