🧱 CFC 201 / 211.0Load-bearing masonry: bricks, blocks and structural elementsChapter 9 of 10 in the section

Cutting an opening in a load-bearing wall: propping, lintel installation and safe removal

Cutting an opening in load-bearing masonry demands absolute discipline in the sequence of steps. This chapter details load transfer according to the civil engineer's plans, vibration-free cutting techniques, lintel installation with expansive mortar packing, and the protocol for progressive propping removal.

Key takeaways

  • The civil engineer must imperatively dimension the load rundown and propping scheme prior to any intervention.
  • The first chase is never started before the complete locking of the shoring towers or steel props.
  • Packing with expansive mortar guarantees flawless load transfer without settlement beneath the retained masonry.
  • Removal of props is carried out in successive stages only after complete curing of the underpinning mortar.

Dimensioning load transfer and installing props

Opening load-bearing masonry alters the building's static equilibrium by interrupting vertical compression lines. Before bringing any cut-off saw onto the construction site, the contractor must have the load transfer plan prepared by the civil engineer. This document specifies the exact position of the props, the type of steel section or concrete beam to be installed, as well as the load rundowns applied to the floors below. Under art. 77 OTConst, shoring must withstand foreseeable loads and forces, be executed according to accepted engineering practice and be dimensioned taking additional loads into account. The site foreman checks that the underlying floors can support these point loads, which frequently requires carrying the propping down to the foundation slab or basement walls using vertically aligned shores.

  1. Setting out and locating servicesMark out the exact footprint of the future opening and padstones on both wall faces. Locate concealed conduits using non-destructive detection before any cutting.
  2. Wall penetrations and installation of needlesDrill through-holes above the level of the future lintel to slide in steel needles (HEB or IPN sections) supported on heavy-duty props on either side of the wall.
  3. Mechanical tightening of shoresPre-load the props in a controlled manner using screw jacks or tightening collars, firmly locking the connection between the needle and the upper masonry with wedge shims.

In the case of clay brick or sand-lime block masonry, loading the props must relieve the area without lifting the slab above, which would otherwise crack partitions on upper floors. Demolition and cutting works generate major hazards from projections and partial collapse; wearing a safety helmet is mandatory in accordance with art. 6 OTConst for all operatives located within the opening's zone of influence.

Opening, lintel installation, non-shrink dry-packing and controlled removal

As soon as the temporary shoring ensures complete load transfer, cutting of the masonry begins. The mason makes neat peripheral chases using a diamond wall saw or a power disc cutter with water misting to prevent any damaging vibration within the remaining masonry bond. The use of heavy pneumatic breakers is prohibited to avoid dislodging adjacent mortar joints. If the wall is thick or floor-to-ceiling clearance is limited, installing a twin rolled steel lintel in two stages (half-wall method) avoids using through-needles by permanently maintaining half of the load-bearing cross-section.

Execution criteria according to chosen trimmer method
Wall configurationLintel solutionSupport methodPoints of vigilance
Single-leaf brick wall (15 to 20 cm)Precast concrete lintel or single steel sectionThrough-shoring using needlesMinimum bearing depth of 20 to 25 cm on padstone
Cavity wall or thick solid wall (> 25 cm)Bolted twin HEB-type sectionsSuccessive half-thickness chasesTightening through-threaded rods after central packing
Masonry beneath reinforced concrete slabTight-fitted steel section or cast concrete beamDirect propping under slab soffitEnsure intimate contact under slab by injection or caulking

Once the lintel is shimmed level on its high-strength mortar padstones, the remaining gap between the top flange of the beam and the underside of the existing masonry must be filled. This void of approximately 30 to 50 mm is carefully packed with non-shrink or slightly expansive bedding mortar, mixed to earth-moist consistency and then rammed solid using a timber batten and hammer. Using standard masonry mortar is a serious technical failure: drying shrinkage would create an imperceptible horizontal crack of a few tenths of a millimetre, preventing load transfer and causing subsequent structural settlement.

Removal of the shoring is carried out progressively and symmetrically. The team leader has the prop collars unwound by a quarter-turn at a time, working from the centre of the span towards the end supports, to allow the lintel to take up its natural elastic deflection gradually. Needles are removed once the load has been transferred, and their wall openings are then made good with dense, waterproof mortar. When drawing up bills of quantities and estimating costs for this type of alteration work, estimating teams refer to the specific positions under /soumissions/.

Execution timeline: from load transfer to wall sawing

Cutting an opening in existing load-bearing masonry allows no workshop improvisation. The stability of the structure above relies entirely on the strict sequence of work phases. Operations always begin with installing the shoring dimensioned by the civil engineer, as specified in the underpinning plans. This shoring includes laying floor spreader soleplates, installing steel sections through wall penetrations above the future lintel drop, and controlled tightening of jacks. The slightest notch cut into the wall without prior load transfer leads to differential settlement and shear in upper bed joints.

  1. Transfer of layout lines and through-hole core drillingSet out the exact opening, the embedding depths of padstones according to the engineer's instructions, and the centreline of temporary needle supports. Form wall penetrations by core drilling or careful chiselling without disturbing adjacent joints.
  2. Pre-loading the shoring systemPlace timber spreader baulks on the floor, erect heavy-duty props, slide transverse steel beams through the wall, and secure pre-load shims. Verify the load transfer onto lower floors down to the stable bearing level designated by the engineer.
  3. Sawing and demolition beneath the lintel dropPerform vertical saw cuts using a diamond wall saw or petrol cut-off saw with water supply. Then hollow out the masonry beneath the future lintel in successive downward passes, removing rubble continuously to avoid overloading working slabs.
  4. Casting load-distributing padstonesScabble the bearing zones for the future lintel on the retained reveals. If the masonry consists of hollow clay blocks or perforated bricks, shutter and cast reinforced concrete padstones to prevent localised crushing under concentrated loads.

Lintel placement, non-shrink dry-packing, and prop release

Once the bearings have cured, the permanent lintel — rolled steel section or precast reinforced concrete lintel — is positioned and levelled onto its bedding mortar. The remaining gap between the underside of the retained masonry and the top face of the beam represents the critical zone for load transfer. This void cannot be filled with standard masonry mortar: setting shrinkage would leave a millimetre-wide gap preventing load transfer, throwing the load back onto temporary props and causing cracking during de-propping.

Packing with expansive mortar
Operation consisting of filling the gap between the installed lintel and the upper masonry using a shrinkage-compensated or slightly expansive fast-setting bedding mortar. Installation is carried out at a stiff plastic consistency, rammed vigorously using a timber batten or flat steel bar to eliminate all air voids.
Monitoring grouting and removal stages by material
Structural elementBonding productWaiting time before removalConstruction site point of vigilance
Steel section (IPN/HEB)Non-shrink thixotropic mortar72 h (compressive strength > 30 N/mm²)Prior grit blasting or rust removal on upper flange
Precast concrete lintelHigh-strength bedding mortar48 h to 72 h depending on temperaturePrior dampening of bearing masonry
Padstone under bearingRapid-hardening micro-concrete7 days or according to technical data sheetCheck of horizontality and substrate soundness
Bolted twin sectionInjected fluid non-shrink grout96 h before full loadingStrict watertightness of packing formwork

Removal of props occurs only after confirmed complete curing of the pinning mortar according to the manufacturer's data sheets and the deadlines set by site management. This step must be carried out progressively and symmetrically. Prop release begins with the props closest to the centre of the opening to transfer the load smoothly to the reveals, then advances towards the ends. The operator loosens the jack screws quarter-turn by quarter-turn while monitoring joint behaviour and tell-tales installed on the upper masonry. Any sudden release using a hammer is forbidden: it applies a dynamic shock likely to shatter newly formed bonds.

Managing structural surprises and securing the opening

During underpinning work, any discrepancy between design assumptions and actual wall construction requires an immediate halt to sawing operations. Discovering delaminated rubble masonry, cracked perforated clay blocks or an unidentified void compromises the load transfer path and exposes the construction site to major damage. Blindly continuing demolition constitutes a serious hazard under CP, which penalises intentional or negligent breach of accepted engineering practice that endangers the life or physical integrity of persons.

  • Stop all cuts with diamond saws or heavy rotary hammers immediately.
  • Install emergency steel shores fitted with hardwood shims beneath adjoining unpropped masonry.
  • Visually inspect the load-bearing bond above and on either side of the planned padstones.
  • Notify site management and the civil engineer responsible for the structural design without delay.

If the expansive mortar packing exhibits premature shrinkage, setting cracks, or poor tightness beneath the steel section, removing the props is strictly prohibited. The contractor must scabble out the hollow area, re-inject a high-strength non-shrink bedding grout, and wait for complete curing validated by the manufacturer's technical data sheets before resuming any de-stressing cycles.

Frequently asked questions

What should be done if the wall crumbles during the upper chase cut?

Cutting must be suspended immediately. Erect supplementary shores with spreader plates beneath the unstable masonry without delay. Carry out temporary pinning or inject consolidating mortar to bind the masonry courses together. Then contact the appointed civil engineer to adapt the opening sequence or opt for a support beam installed in two successive half-sections.

How should one react if the slab above settles slightly during jacking?

Lock prop pins and collars at once to arrest the settlement. Such movement indicates undersized shoring or deflection of the floor below under point loading. Double the transfer props on widened hardwood soleplates or steel cross-beams, then have the overall load rundown verified by the structural engineer before starting to remove any masonry.

How long must one wait before removing props after dry-packing?

Uncoupling props never begins before reaching the mechanical strength required for the expansive or non-shrink mortar. As a general rule, observe a curing period of at least 48 to 72 hours at 20 °C, in compliance with the manufacturer's technical specifications. Striking is then performed in gentle balancing stages, loosening props alternately from the centre towards the end padstones.

Why do cracks appear above the bearings of the new lintel?

Such distress often indicates excessive stress concentration on bearing masonry that is too weak, the lack of a reinforced concrete padstone, or shrinkage of the upper dry-packing. The lintel must immediately be re-propped from below to halt cracking, defective joints must be raked out, and the bearing dimensions and reveal load capacity must be validated by the engineering consultancy before demobilising any equipment.

Texts and standards cited

  • CPbreach of accepted engineering practice: whoever intentionally breaches accepted engineering practice while directing or executing construction or demolition work and thereby knowingly endangers the life or physical integrity of persons is liable to a custodial sentence not exceeding five years or a monetary penalty; if committed through negligence, the penalty is a custodial sentence not exceeding three years or a monetary penalty.
  • COmaterials and ground: the contractor is liable for the sound quality of materials he supplies; if materials supplied by the client or ground designated by him are found to be defective, or if another circumstance jeopardises the proper or timely execution of the work, the contractor must immediately inform the client, on pain of bearing the consequences thereof (para. 3).