🧱 CFC 201 / 211.0Earthworks, excavations and temporary shoringChapter 7 of 10 in the section

Soldier pile wall and soil nailed wall: execution and monitoring

This chapter details the construction of soldier pile walls and soil nailed walls on building construction sites in Switzerland. You will learn how to master the strict staging of excavation in lifts, check the tensioning of tiebacks and nails, and organise the metrological monitoring of deformations to ensure trench stability according to standard SIA 267.

Key takeaways

  • Staging by excavation-shoring lifts prevents premature decompression of in-situ soils.
  • The execution of tiebacks requires strict monitoring of grouting pressures and tension tests.
  • Compliance with the requirements of standard SIA 267 guarantees the sizing of temporary retaining structures.
  • Monitoring deformations using inclinometers and optical targets continuously validates the safety of the construction site.

Execution staging and installation of shoring in successive lifts

Constructing a temporary retaining structure using a soldier pile wall or soil nailed wall relies on strictly breaking down the trench excavation into successive lifts. Unlike bulk earthmoving, the mason and the site manager must coordinate the excavation with the installation of the shoring in order to prevent decompression of the ground ahead of the excavation face.

Staging by lifts
Excavation method in reduced horizontal or vertical slices, where each excavated height is immediately stabilised by a shoring element (sprayed concrete, mesh or timber lagging) before stepping down to the lower level.
  1. Drilling and installation of IPE/HEB profiles (Soldier pile wall)Vertical drillings are carried out from the working platform down to the theoretical bottom of the trench plus the embedment depth. The steel profiles are lowered by crane, adjusted in elevation and grouted at the toe with infill concrete.
  2. Excavation of the first liftThe excavator digs out the ground to a maximum height defined by the geotechnical engineer, generally between 1 m 50 and 2 m 00. The excavation face is trimmed neatly between the flanges of the profiles.
  3. Installation of intermediate laggingInstallation of shoring between profiles: hardwood lagging planks wedged tight or installation of flush-pinned welded wire mesh and application of a pass of blinding/structural sprayed concrete.
  4. Drilling of nails and soil nailing (Soil nailed wall)For the soil nailed wall, drilling is carried out directly into the excavated ground. High-bond (HA) or self-drilling steel bars are inserted and then injected with cement grout before applying reinforced sprayed concrete.

The sizing and justification of the internal and external stability of temporary retaining structures must incorporate measured geotechnical characteristics, the presence of groundwater and the precise staging of excavation steps.

norme SIA 267

Inspection of anchor tiebacks and metrological monitoring of deformations

The global stability of a soldier pile wall or a high soil nailed wall depends directly on the quality of execution of the anchors and the maintenance of prestress in the tiebacks. Transferring ground forces to the steel waling beams requires rigorous monitoring of grouting and testing operations.

Execution and acceptance checks for retaining wall anchors
Anchor typeExecution checkpointAcceptance criterion
Temporary prestressed tiebackGrout injection pressure & suitability testValidation of the grout bulb and minimum lock-off load reached during tension testing
Passive nail (Soil nailed wall)Volume of grout absorbed and sleeve bleedingGrout emerging continuously at the drill head
Steel waling beamTightening of assembly bolts and welding of base platesPerfect contact between the waling beam and the vertical profiles

Monitoring the deformations of the structure is essential from the very first excavation lift. The monitoring plan must provide for regular convergence and settlement measurements to identify any deviation from the geotechnical model.

  • Weekly reading of optical targets installed at the head of IPE/HEB profiles.
  • Inclinometer measurements in tubes grouted behind the wall to monitor the deep deformation profile.
  • Daily visual inspection of concrete faces (checking for cracks or water ingress).
  • Periodic checking of the residual load on reference tieback heads using a hydraulic jack.

Sequence of execution and staged excavation for soldier pile and soil nailed walls

The stability of temporary retaining walls depends directly on strict adherence to the dewatering and excavation staging. According to standard SIA 267 (Geotechnical design), the soil-structure interaction requires controlled decompression. Excavation is carried out in successive lifts of limited height, defined beforehand by the geotechnical engineer in the detailed design.

  1. Drilling of HEB profiles and digging of lift 1For the soldier pile wall, drilling of holes, installation of vertical steel profiles, then excavation of the first lift (usual height 1.50 m to 2.00 m). For the soil nailed wall, direct excavation of the first bench.
  2. Installation of shoring and execution of anchorsInstallation of intermediate shoring (precast concrete panels or reinforced sprayed concrete with wire mesh) on the cleared lift. Drilling for anchors and tiebacks or soil nails through the wall facing.
  3. Grouting, tensioning and next liftGrouting of cement into the anchor zone, compliance with the binder curing time, then tensioning of the retaining anchor and tieback. Once the level is validated, excavation of the lower lift can begin.

Installation of anchors, load control and metrological monitoring

The performance of the wall and the preservation of adjacent structures require rigorous monitoring of the anchors and continuous tracking of the spatial-temporal deformations of the retaining wall.

Technical comparison of anchor execution and inspection
Control parameterSoldier pile wall (Prestressed tiebacks)Soil nailed wall (Passive nails)
Loading modeActive prestressed ground anchor (immediate loading)Passive ground nail loaded by ground displacement
Acceptance testHydraulic jack loading up to the proof loadPull-out test on sacrificial or control nails
Lock-off checkVerification of the lock-off load at the head wedgesNo lock-off, rigid connection to the head via bearing plate

Requirements relating to the load-bearing capacity of elements and the organisation of trenches are governed by the construction work ordinance. In particular, trenches deeper than 1 m 50 must be appropriately propped, shored or stabilised to prevent any collapse.

  • Daily inspection of waterproofing and drainage behind precast panels or sprayed concrete.
  • Periodic logging of load cells on reference tiebacks.
  • Visual inspection of cracks on adjacent infrastructure and roadways.

Managing contingencies and deviations on temporary retaining structures

During the construction of a soldier pile wall or a soil nailed wall, deviations from the geotechnical design may occur. Soil heterogeneity, unexpected water ingress or exceeding deformation thresholds demand an immediate response from the site manager and the foreman. Worker safety and the stability of neighbouring structures depend on the strict application of stoppage and consolidation procedures.

  1. Detection of a metrological alert threshold exceedanceIf inclinometer or topographical targets measure a deflection at the top of the wall that exceeds the limits tolerated by standard SIA 267, halt underpinning excavations. Immediately notify the civil engineer responsible for the retaining structure.
  2. Implementation of emergency precautionary measuresPlace a temporary earth berm at the toe of the compromised retaining wall or install heavy temporary steel rakers to arrest increasing displacements.
  3. Special load testing of ground anchorsCarry out lock-off lift-off tests on the anchors or passive tiebacks of the upper lift to verify the absence of prestress loss or grout bulb slippage in the ground.
  4. Staging review and resumption of worksRedefine the height of excavation lifts with the geotechnical engineer. Reduce the panel advance width for sprayed concrete or increase nailing density before resuming excavation.

Traceability of these events is essential. Any incident related to ground behaviour, drill tool jamming or sudden hydraulic uplift must be recorded in the site diary and notified to the site management to adapt constructive measures.

Frequently asked questions

What should be done if a nail encounters a void or an unexpected obstruction during drilling?

In the event of lost tooling or a clear void during soil nail drilling, stop drilling fluid injection. Inform the geotechnical engineer to validate an adjustment of the nail length, an alteration of the inclination, or pressure regrouting to reconstitute the ground around the anchor bar.

How should significant water ingress behind sprayed concrete be handled?

If water resurgences occur behind the sprayed concrete shell, do not attempt to seal the facing. Install perforated pressure-relief drains through the skin to direct the water towards the trench floor ditch. An accumulation of undrained hydrostatic pressure risks causing the structural failure of the wall facing.

What is the acceptable tolerance for the setting out of steel HEB profiles for a soldier pile wall?

The setting-out accuracy of the steel shoring profiles must comply with the tolerances defined by standard SIA 414. As a general rule, the maximum out-of-plumb deviation must not exceed 1 to 2% of the wall height to prevent any clash with the profile of the permanent basement walls.

Can a new lift be excavated if the sprayed concrete from the previous lift has not hardened?

This is strictly prohibited. Excavation of the lower lift may only begin once the sprayed concrete of the upper facing has reached the minimum compressive strength specified by the geotechnical engineer (generally after a minimum curing period of 24 to 48 hours), ensuring the retention of ground thrust.

Texts and standards cited

  • SIA 267Geotechnical design
  • SIA 414Building construction tolerances
  • OTConstTrenches, shafts and earthworks: arrangements to prevent falling or sliding materials.