🧱 CFC 201 / 211.0Foundations, rafts and protection of underground structuresChapter 1 of 10 in the section

Strip footing: blinding concrete, formwork and rebar placement

This chapter details the complete construction of a reinforced concrete strip footing in accordance with Swiss regulations. You will learn to master the sequence of operations, from pouring the blinding concrete to erecting the formwork, and how to secure the two critical points that cannot be rectified after concreting: compliance with nominal concrete cover and rigid positioning of the wall starter bars.

Key takeaways

  • Blinding concrete guarantees a clean surface essential for rebar stability.
  • Concrete cover according to standard SIA 262 permanently protects reinforcement against underground corrosion.
  • Plastic or mortar bar spacers must withstand the weight of steel fixers.
  • Wall starter bars require rigid tying to prevent any tipping during concreting.

From excavation formation level to formwork: methodical preparation of the bearing surface

As soon as the earthworks formation level approved by the geotechnical engineer is reached, the excavation formation must be protected immediately to prevent soil degradation from weathering or desiccation. The removal of disturbed soil is carried out manually or with a toothless ditching bucket, ensuring that safety berms are cleared in accordance with the excavation rules of the Construction Works Ordinance.

Blinding concrete
A layer of unreinforced lean-mix concrete, typically 5 to 10 cm thick, poured directly onto the cleared bearing ground to provide a clean, stable and dry horizontal working plane.

Blinding concrete serves as the geometric base for the foundation. It enables accurate setting out of strip footings using chalk lines and string lines, nailing of formwork kickers, and reliable placement of bar spacers. Its unformed surface must have a strict level tolerance to prevent any local variation in the nominal thickness of the footing. In the event of water ingress, a sump pump system keeps the working platform dewatered until the material has fully set.

  1. Handover inspection of excavation formationVisual check of soil compaction, removal of loosened excavated material and verification of elevation level using a site level.
  2. Pouring of blinding concretePlacement of a lean-mix concrete of very plastic or fluid consistency, screeded with a straightedge or rake to a minimum thickness of 50 mm.
  3. Geometric setting-outTransfer of setting-out axes from external profile boards using a theodolite or a precision laser level.
  4. Erection of formwork side panelsFixing of timber or metal panels using walers, angle brackets anchored into the lean-mix concrete, and rigid inclined raking props.

Reinforcement, bar spacers and wall starter bars: irreversible checks

Reinforcement for a strip footing generally comprises a bottom cage consisting of continuous longitudinal bars and distributed transverse bars, designed by the structural engineer. Strict compliance with concrete cover, defined by standard SIA 262 according to environmental exposure classes, directly governs the durability of the structure against chemical attack from the ground and rising damp.

Spacer dimensions and spacing for strip footings on blinding concrete
Checked elementTarget parameterOn-site verification method
Nominal bottom coverBar spacer of 35 to 50 mmMeasuring rod or depth gauge
Spacer density2 to 3 spacers per m² of rebar matVisual check before fixers walk on it
Starter bar spacingCentre-to-centre distance to drawings at ± 10 mmTape measure referenced to actual grid lines
Lap lengthAccording to bending scheduleMeasurement of straight projecting length

The choice of bar spacers determines the long-term accuracy of the positioning. High-strength fibre-reinforced mortar spacers or continuous linear plastic spacers should be favoured on blinding concrete. Point plastic spacers that are too flexible or cylindrical frequently tip over under the weight of operatives when installing top bars, causing direct contact between steel and the sub-base, an immediate source of through-corrosion.

The second critical point lies in the installation of wall starter bars. Whether individual L-bars, U-shaped bent bars or prefabricated cages, this reinforcement is subjected to the dynamic impact of concrete placed by skip or pump. They must imperatively be tied to stiffening links or longitudinal support bars tied at the top to ensure their straightness and verticality.

Pouring, vibration and maintaining alignment under concrete pressure

Once the pour is authorised following the reinforcement inspection, placing concrete for a strip footing requires a continuous delivery rate. The free fall of the mix must remain controlled to prevent aggregate segregation, especially along the formwork faces or onto the bottom reinforcement mats. Progress is made in regular layers distributed along the full length of the trench.

The poker vibrator must be inserted vertically under its own weight at regular intervals, never coming into prolonged contact with the reinforcing steel or scraping against the bar spacers. Vibration transmitted directly to the cage displaces the bars and creates air or laitance pockets along the steel, compromising the steel-concrete bond required by standard SIA 262. The poker must penetrate a few centimetres into the underlying layer if pouring in two lifts, and then be withdrawn slowly to close the compaction hole.

To ensure accurate alignment of starter bars, fitting a top timber jig or metal profile secured to the formwork panels or anchored outside the pour zone is mandatory. This device maintains the exact centre-to-centre spacing and verticality of the bars during discharge from the skip or pump hose. Continuous monitoring with a dumpy level or string line is carried out throughout the vibration phase, enabling immediate adjustment while the mix remains fluid.

Checkpoints during pouring and execution tolerances on footings
Pouring stageExecution riskTolerance / Preventive measure
Initial dischargeDisplacement of concrete bar spacersLimited free-fall height; directing the flow to the centre of the footing
Internal vibrationDetachment of rebar layers and ground contactPoker kept clear of reinforcement; no contact with formwork
Top surfaceFinished level too high, obstructing the base of the wallElevation tolerance of -10 mm to +10 mm; careful float finishing
Starter bar zoneBars tipping out of theoretical alignmentMaximum permissible deviation of 10 mm from the setting-out line

Construction joint preparation, concrete curing and handover before wall erection

The top surface of the strip footing forms the construction joint with the future reinforced concrete wall. As soon as the concrete begins to set, surface laitance must be removed to expose the aggregates without loosening the matrix. This mechanical scabbing by light bush-hammering, thorough wire brushing or high-pressure washing guarantees shear force transfer at the base of the wall in accordance with the structural engineer's drawings.

Curing treatment must be applied immediately following levelling operations. Premature evaporation of mixing water, accelerated by wind in the bottom of the excavation or direct sunlight, causes through-section plastic shrinkage cracking. Applying a certified temporary curing agent, placing damp-kept geotextile sheets, or providing thermal covers prevents desiccation of the concrete during its initial days of hydration.

Before commencing the setting out and formwork of basement walls, the site foreman records the conformity of the works in the site logbook. The handover inspection covers the level of the top surface, the absence of honeycombing at the footing toes, and full clearance of the wall starter bars. Any traces of mud or dried laitance on the starter bars are cleaned with a wire brush prior to erecting the wall formwork panels.

Post-pour non-conformities: remediation protocols and structural limits

Once the concrete has set, cover defects or wall starter bar deviations turn into critical disputes. The site foreman and structural engineer must manage these discrepancies according to approved procedures, without improvising destructive interventions that could weaken the structure.

  1. Immediate observation and joint as-built surveySurvey the actual as-built location of wall starter bars against the surveyor's grid lines. Record the deviation from the theoretical outer face of the future wall before commencing any wall formwork.
  2. Moderate deviation: engineered crank (offset bend)If the deviation remains minor (generally less than the bar diameter), the engineer may authorise bending at a maximum gentle slope (1:6). This operation requires the use of a suitable rebar bending hickey and excludes any dynamic impact.
  3. Major deviation: drilling and rebar chemical anchoringIf the bar falls outside the wall formwork, the misaligned rebar is cut off flush. New starter bars are installed by rotary percussion drilling and chemical anchoring with approved injection resin, strictly adhering to the embedment depth specified by the engineering office.
  4. Soffit or lateral cover defectExposed reinforcement or honeycombing requires meticulous chiselling away of uncompacted concrete, cleaning with pressurised water, and then application of a non-shrink thixotropic structural repair mortar to reinstate protective cover against corrosion.

Pursuant to art. 365 CO, the contractor shall immediately inform the site management of any circumstance that compromises the proper performance of the work. Superstructure wall works remain suspended until written approval of the corrective measures is received.

Frequently asked questions

What should be done if wall starter bars touch the external formwork?

Reinforcement in contact with formwork panels compromises the cover required by standard SIA 262 and exposes the structure to premature corrosion. It is forbidden to grind it down or bend it abruptly without technical advice. The engineer will prescribe either cranking at an acceptable slope, or cutting the bar flush and installing a chemically anchored dowel correctly positioned inside the wall reinforcement.

How can a cover defect discovered after stripping the footing formwork be repaired?

When reinforcement is visible at the surface of the footing due to a lack of bar spacers, the surface must be remediated without delay. Porous concrete is cut back with a flat chisel until 20 mm behind the steel is cleared. After thorough dust removal and saturated-surface-dry pre-wetting, a shrinkage-compensated fibre-reinforced repair mortar is applied at sufficient thickness to ensure density and restore alkaline protection to the rebar.

Can a starter bar be heated to facilitate straightening?

Blowtorch heating irreversibly alters the thermomechanical treatment of modern reinforcing steel and reduces its yield strength. This practice is strictly prohibited on Swiss construction sites under standard SIA 262. Any misaligned rebar that cannot be cold-bent under strict control must be cut off and replaced by an anchor bar bonded with an approved structural resin, validated by the engineer.

What positional tolerance applies to wall starter bars?

The tolerance depends on the wall thickness and the rebar type specified in the design. A deviation greater than one centimetre often compromises the placement of mesh fabrics or the required minimum cover. As soon as a setting-out discrepancy is found relative to the lines marked on the blinding concrete, the site foreman must record the measurement and obtain approval from the site management before erecting the panels.

Texts and standards cited

  • norme SIA 262Rules for the design, detailing of rebar, concrete cover, and execution of reinforced concrete structures.
  • CO art. art. 365 COContractor's obligation to give immediate notice to the client if the ground, materials, or other circumstances compromise the proper performance of the works.