Key takeaways
- A regular minimum gradient prevents the formation of stagnant water pockets along footings.
- Flushing chambers enable high-pressure jetting without having to excavate the backfilled structure.
- Filter wrapping with geotextile and clean gravel prevents clogging by fine particles.
- The connection requires strict separation between clear drainage water and wastewater.
Channel layout, fall gradient and drainage pipe installation
Setting out a perimeter drainage collector begins as soon as strip footings or the raft slab are struck. An elevation error on the channel ruins the structure: once the backfill is compacted, a drain laid on a counter-gradient or too high relative to the lower edge of the concrete will cause slow seepage into underground walls. Under art. 365 CO, the contractor reports to the client any circumstances that jeopardise the proper execution of the works, which entails refusing any installation on an unstable or muddy excavation bottom without prior muck-out.
Standard trade practice requires a continuous gradient of between 0.5% and 1% directed towards the low discharge point. The foundation channel is poured in lean concrete, trowel-finished, ensuring that the pipe invert remains positioned below the top level of the raft slab or at the base of the footing. Rigid PVC or polyethylene flat-bottom pipe, slotted on its upper section, must be mechanically wedged so as not to float during the pouring of the lateral haunching concrete. Corrugated flexible drains in coils are prohibited at the base of structures because their corrugations retain fine sediments.
Inspection chambers, filter pack and statutory outfall
Every horizontal or vertical change of direction greater than 30 degrees requires the installation of an inspection and flushing chamber. On long straight runs, installing an intermediate chamber remains essential beyond approximately twenty metres. These inspection chambers, with an internal diameter suitable for cleaning nozzles, rise up to the finished level of the natural ground or lightwell. They are fitted with a hermetic cover to prevent the ingress of gravel or surface debris.
- Chamber base with preformed channel avoiding dead sedimentation zones
- Watertight riser in concrete or plastic insensitive to differential settlement
- Manhole cover permanently accessible for camera inspection passage
- Complete absence of direct discharge of roof rainwater into the drainage circuit
Wrapping the collector determines its mechanical and hydraulic durability. The trench bottom and sides receive a layer of rot-proof non-woven geotextile. The pipe is bedded in a layer of washed filter gravel, of uniform grading free from fine particles. The geotextile fabric is then folded back over the top with a minimum overlap of 20 centimetres to form a closed sausage shape impermeable to backfill slurry. The use of unscreened run-of-bank gravel or any earthy material in direct contact with the pipe is strictly prohibited.
| Element | Recommended material | Critical installation point |
|---|---|---|
| Bedding | Lean concrete batched at 150 kg | Smoothing the gradient without water pockets |
| Pipe | Rigid pipe with upper slots | Visual inspection of slot orientation |
| Granular filter | Washed round or crushed gravel | Total absence of sand or silt |
| Envelope | Synthetic geotextile membrane | Careful overlap to prevent earth ingress |
The final outfall constitutes the last checkpoint before backfilling. Connecting a perimeter drain to the public wastewater network is strictly prohibited by municipal and cantonal water discharge regulations. The collector must connect to the municipal storm sewer network, an open natural outfall, or a soakaway sized by the geotechnical engineer. Where gravity discharge is impossible at the low point, installing a lifting station with a non-return valve and high-level alarm prevents any backflow towards the building footings.
Execution checkpoints before backfilling
Once the excavation is backfilled, a collector laid on a counter-gradient, crushed, or lacking a rodding eye becomes undetectable until the first ingress of sediment-laden water or groundwater rise. The appearance of damp on the internal face of basement walls then leads to heavy underpinning earthworks, with complete renewal of the perimeter trench under the direct liability of the executing contractor. Geometric and mechanical checks must therefore imperatively occur before any backfill material is introduced.
| Inspected element | Acceptance criterion | Measuring tool | Corrective action |
|---|---|---|---|
| Fall gradient | Continuous gradient ≥ 0.5%, high point below finished raft slab level | Construction site laser level and graduated staff | Reworking the lean concrete channel before installation |
| Slot orientation | Perforations facing upwards and sideways, solid invert intact | Visual inspection along the entire crown line | Immediate rotation of the rigid pipe or replacement |
| Filter pack | 16/32 washed gravel free from fines, minimum thickness of 20 cm | Tape measure and visual inspection of material | Suction or removal of soil-contaminated gravel |
| Geotextile filter | Sheet overlap ≥ 30 cm, no tears, closed envelope | Visual continuity inspection prior to closing | Installation of a sewn or stapled reinforcement patch |
| Inspection chambers | Watertight chamber, Teflon or elastomeric seal in place, silt trap base | Plumb check and visual inspection | Underpinning column base and penetration waterproofing |
For safety during these inspection and backfilling operations, workers ensure strict compliance with battering or trench shoring rules applicable from 1 m 50 depth, in accordance with OTConst, in order to prevent any trench wall collapse onto pipelaying personnel.
Connection to the approved outfall and acceptance traceability
The drainage network must never be connected directly to the municipal wastewater collector. Water protection regulations mandate strict separation of flows. The approved outfall depends on the hydrogeological configuration of the site and municipal or cantonal permits: direct infiltration into a permeable layer via a soakaway located outside the building retention zone, discharge into a watercourse with an energy dissipation structure, or connection to the public storm sewer (separate system) if local regulations permit.
- Installation of an accessible non-return valve in the downstream chamber to block backflow from the public storm sewer during heavy storms.
- Systematic installation of an inspection chamber with a sand trap (minimum pit depth of 50 cm) before the final discharge point.
- Prior approval from the municipal technical department and the cantonal water protection police for any discharge into the natural environment or infiltration.
- Strict exclusion of roof rainwater or yard gullies connecting into the perimeter drainage pipe.
- CCTV inspection and high-pressure jettingBefore permanently closing the chambers, perform gentle water jetting followed by a remotely guided CCTV run from the upstream chamber to the outfall to prove the absence of settlement, ovalisation, or cement laitance.
- Joint survey and georeferenced surveySurvey national datum invert levels of chamber bases, pipe crowns at direction changes, and outlet locations before full backfilling of the excavation.
- Compiling the as-built documentation fileGather the joint photo record, geotextile technical data sheets, washed gravel delivery dockets, and CCTV report to append to the special works acceptance report.
Managing defective workmanship and remediating the network under backfill
Defective perimeter drainage buried under several metres of backfill represents a major financial risk. Typical defects discovered during final testing include localised counter-gradients, lack of inspection and flushing chambers at direction changes, or inverted slots on a perforated drain. As soon as a flow problem is identified, the site manager must halt backfilling operations and record the defect.
Under art. 365 CO, the contractor is liable for the good quality of materials supplied, and if any circumstance jeopardises the proper or timely execution of the works, they must notify the client. When the drainage network is improperly installed, the defect will be irremediably concealed by earth if camera inspection is not carried out before backfilling. Remediation then requires complete trench re-excavation while complying with the construction work ordinance regarding battering and trench wall stability.
- Locate blockage or stagnation by CCTV inspection from inspection chambers.
- Expose the filter pack using a backhoe without damaging the rigid pipe or basement wall waterproofing.
- Remove soil-contaminated filter gravel and dispose of clogged material in accordance with the waste ordinance.
- Reconstruct the concrete channel with a regular fall gradient directed towards the approved outfall.
- Re-lay the non-woven geotextile with complete overlap of the filter zone before backfilling in compacted layers.
Art. 368 CO addresses the client's rights in case of defects in the work, opening the way to rectification or damages. The cost of complete remediation following ground settlement far exceeds the initial installation cost. The only safeguard lies in methodical self-checking: visual laser level inspection of the invert, pressure jetting from every chamber, and a signed report prior to introducing any backfill material.
Frequently asked questions
How do you rectify a counter-gradient detected before backfilling the drain?
Filter gravel must be cleared and rigid pipes dismantled over the affected section. The lean concrete blinding channel must be scabbled back or built up to re-establish a regular downward fall gradient towards the downstream collector. A laser check on the invert validates the rectification before re-laying the smooth-invert rigid drain, wrapping the filter gravel in geotextile, and proceeding with backfilling.
What should be done if a building corner was poured without an inspection chamber?
The lack of an inspection and flushing chamber at a direction change makes rodding impossible and holds up acceptance. The team must excavate the trench corner, cut the collector, and insert a concrete or plastic inspection chamber with a watertight cover at finished ground level. This intervention preserves access to the network for future CCTV inspections without undermining the thermal or waterproofing protection of the raft slab.
Can perimeter drainage be connected to the municipal wastewater network?
No, this practice is strictly prohibited in Switzerland. Drained groundwater and seepage must never overload sewage treatment works. Approved outfalls comprise discharge to a watercourse, a distinct municipal storm sewer if allowed by the municipality, or an on-site infiltration system. The connection requires installing a non-return valve to prevent backflow into the foundations.
Why must filter gravel systematically be wrapped in geotextile?
Filter gravel ensures the swift transfer of water ingress to the collector intake slots. Without a complete non-woven geotextile felt envelope, fine particles in the backfill soil migrate under rainfall and clog the gravel voids. Within a few seasons, the pack loses all permeability, water pressure builds up against underground walls, and the drainage system becomes entirely ineffective.
Texts and standards cited
- CO art. 365materials and ground: the contractor is liable for the good quality of materials supplied; if materials supplied by the client or ground designated by the client are found to be defective, or if any other circumstance jeopardises the proper or timely execution of the works, the contractor must immediately inform the client, failing which the contractor bears the consequences (para. 3).
- COclient rights in case of defects in the work: rejection, price reduction, rectification, damages; any clause agreed in advance that restricts or excludes the right to remedy defects is null and void if the defect relates to a construction work (para. 2bis, since 1 January 2026).
