Fixtures, connections and built-in installations: the execution reference
Aimed at foremen and CFC 250 sanitary installers, this section details the mechanical fixing of mounting frames, the watertight embedding of taps and mixers, and the geometry of drainage outlets according to SIA 385/1 and SSIGE guidelines. It provides the execution benchmarks and installation interfaces needed to position each fixture precisely, ensure sound insulation and validate the checks before ducts and linings are closed off for good.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 5
400 kg
Minimum static test load for fixing a wall-hung WC mounting frame
150 kg
Vertical test load applied to the front edge of a wall-hung washbasin
50 mm
Minimum permanent water seal of the odour trap for an individual fixture
1.5 %
Recommended gravity slope for collecting water from a shower without a shower tray
100 cm
Height of the official reference level mark above the finished floor
Scope and execution interfaces of sanitary work
The embedding of pipework and the connection of sanitary fixtures form the point where drinking water distribution, gravity drainage and the heavy finishing work of the building converge. On Swiss construction sites, the responsibility of the CFC 250 sanitary installer stops strictly at the limits of the trade. The fitter's role is to set out the mounting frames, adjust heights to the official level mark, install the concealed tap and mixer bodies, run the supply lines and lead the waste-water collectors to the foot of the stack or to the slab penetration.
| Building element | Sanitary responsibility (CFC 250) | Adjoining third-party trade |
|---|---|---|
| WC mounting frame | Fixing to the raw structural work, axis adjustment and sound insulation | Plastering (CFC 251): double moisture-resistant facing board |
| Floor channel and trap | Installation of the receiving body, drainage connection and water seal | Liquid waterproofing (CFC 282): sleeve and bonding mat |
| Pipework under screed | Laying of pipes with continuous sleeves and acoustic bridging | Screed (CFC 281): embedding, cover thicknesses and joints |
| Concealed taps and mixers | Sealing of the built-in box and pressure testing | Tiler (CFC 282): precise cutting and perimeter grouting |
| Individual water heater | Cold water connection, sanitary recirculation and safety group | Electrician (CFC 232): supply line and circuit breaker |
A badly positioned concealed outlet or a rigidly clamped frame without acoustic decoupling causes immediate damage: damage from water ingress, structural sound bridges or the impossibility of adjusting the flush plates. In application of art. 365 CO, the installer reports without delay to the site management any incompatibility found on the screed, the concrete wall or the metal framework before setting out his openings.
Logical reading order and installation sequence
To control the installation sequence and prevent disputes at handover of the works, the chapters of this section should be read in the natural order of progress of the works, from the raw structural work through to the final inspection records.
- Phase 1: Primary structures and load-bearing frames (L5-01 to L5-03)Start with the stability of the mounting frames and their anchoring in the levelling screed or raw slab, then the geometry of level-access showers. These chapters set the non-negotiable drainage slopes and the plumb tolerances on lightweight partitions.
- Phase 2: Built-in boxes and terminal networks (L5-04 to L5-07)Study the embedding of mixer bodies, the provisions for thermostatic mechanisms, the supply to kitchens and the mounting of washbasins. This phase determines free access to wear parts and the absorption of tensile loads without breaking open the linings.
- Phase 3: Compliance in use, protection and acceptance (L5-08 to L5-10)Consult the accessibility rules for persons with reduced mobility and the manoeuvring clearances, then apply the strict instructions for protecting the construction site against limescale and impacts. Finish with the exhaustive checklist before sealing, avoiding a claim under the warranty for defects pursuant to art. 368 CO.
📘 Chapters in this section 10
The support frame: floor and wall fixing, permitted load and lightweight partition
Master the floor-to-wall anchor points and acoustic decoupling to eliminate any sagging of the WC pan.
Appliances, connections and built-in fittingsThe flush-mounted outlet: position, projection, protection and preparation for waterproofing
Adjust the depth of threaded connections to make watertight bridging with the tiler easier.
Appliances, connections and built-in fittingsThe walk-in shower: drainage, available height, slope and flow rate discharged
Secure the water seal and the drainage slope within the reduced thickness of modern screeds.
Appliances, connections and built-in fittingsRecessing a tap or mixer: depth, access provision and spare parts
Keep access to cartridges and valves so that work can be done later without removing the wall tiles.
Appliances, connections and built-in fittingsConnecting a washing machine: trap, loop height, stop valve and safety tray
Calibrate the discharge height and the anti-backflow cut-off to protect dwellings against flooding.
Appliances, connections and built-in fittingsThe kitchen: manifold, isolating valves, waste outlet and space for the furniture
Position the sanitary connection points in a recess to clear the way for low kitchen units.
Appliances, connections and built-in fittingsHanging a washbasin: reinforcement, suitable anchor and load-bearing support
Require suitable reinforcing cross-members in the metal framework to prevent pull-out under load.
Appliances, connections and built-in fittingsAccessible sanitary facility: heights, turning space, grab bars and taps
Respect the turning areas and the layout of grab rails to pass the accessibility checks.
Appliances, connections and built-in fittingsProtecting until handover: covering, scratches, construction-site limescale and joint inspection record
Fit effective basin protection to prevent damage to the enamel from construction site dust.
Appliances, connections and built-in fittingsBefore closing up: the checklist that saves you from having to reopen
Tick off the pressure tests and thermal insulation so that technical ducts can be closed safely.
