Fixtures, connections and built-in installations: the execution reference

Aimed at foremen and CFC 250 sanitary installers, this section details the mechanical fixing of mounting frames, the watertight embedding of taps and mixers, and the geometry of drainage outlets according to SIA 385/1 and SSIGE guidelines. It provides the execution benchmarks and installation interfaces needed to position each fixture precisely, ensure sound insulation and validate the checks before ducts and linings are closed off for good.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 5

SSIGE guidelines and recognised rules of sanitary engineering

400 kg

Minimum static test load for fixing a wall-hung WC mounting frame

SSIGE guidelines and recognised rules of sanitary engineering

150 kg

Vertical test load applied to the front edge of a wall-hung washbasin

SIA 385/1 standard and SSIGE guidelines

50 mm

Minimum permanent water seal of the odour trap for an individual fixture

Norme SIA 385/1

1.5 %

Recommended gravity slope for collecting water from a shower without a shower tray

Norme SIA 118

100 cm

Height of the official reference level mark above the finished floor

Scope and execution interfaces of sanitary work

The embedding of pipework and the connection of sanitary fixtures form the point where drinking water distribution, gravity drainage and the heavy finishing work of the building converge. On Swiss construction sites, the responsibility of the CFC 250 sanitary installer stops strictly at the limits of the trade. The fitter's role is to set out the mounting frames, adjust heights to the official level mark, install the concealed tap and mixer bodies, run the supply lines and lead the waste-water collectors to the foot of the stack or to the slab penetration.

Demarcation of responsibilities and execution interfaces in the bathroom
Building elementSanitary responsibility (CFC 250)Adjoining third-party trade
WC mounting frameFixing to the raw structural work, axis adjustment and sound insulationPlastering (CFC 251): double moisture-resistant facing board
Floor channel and trapInstallation of the receiving body, drainage connection and water sealLiquid waterproofing (CFC 282): sleeve and bonding mat
Pipework under screedLaying of pipes with continuous sleeves and acoustic bridgingScreed (CFC 281): embedding, cover thicknesses and joints
Concealed taps and mixersSealing of the built-in box and pressure testingTiler (CFC 282): precise cutting and perimeter grouting
Individual water heaterCold water connection, sanitary recirculation and safety groupElectrician (CFC 232): supply line and circuit breaker

A badly positioned concealed outlet or a rigidly clamped frame without acoustic decoupling causes immediate damage: damage from water ingress, structural sound bridges or the impossibility of adjusting the flush plates. In application of art. 365 CO, the installer reports without delay to the site management any incompatibility found on the screed, the concrete wall or the metal framework before setting out his openings.

Logical reading order and installation sequence

To control the installation sequence and prevent disputes at handover of the works, the chapters of this section should be read in the natural order of progress of the works, from the raw structural work through to the final inspection records.

  1. Phase 1: Primary structures and load-bearing frames (L5-01 to L5-03)Start with the stability of the mounting frames and their anchoring in the levelling screed or raw slab, then the geometry of level-access showers. These chapters set the non-negotiable drainage slopes and the plumb tolerances on lightweight partitions.
  2. Phase 2: Built-in boxes and terminal networks (L5-04 to L5-07)Study the embedding of mixer bodies, the provisions for thermostatic mechanisms, the supply to kitchens and the mounting of washbasins. This phase determines free access to wear parts and the absorption of tensile loads without breaking open the linings.
  3. Phase 3: Compliance in use, protection and acceptance (L5-08 to L5-10)Consult the accessibility rules for persons with reduced mobility and the manoeuvring clearances, then apply the strict instructions for protecting the construction site against limescale and impacts. Finish with the exhaustive checklist before sealing, avoiding a claim under the warranty for defects pursuant to art. 368 CO.

📘 Chapters in this section 10

Appliances, connections and built-in fittings

The support frame: floor and wall fixing, permitted load and lightweight partition

Master the floor-to-wall anchor points and acoustic decoupling to eliminate any sagging of the WC pan.

Appliances, connections and built-in fittings

The flush-mounted outlet: position, projection, protection and preparation for waterproofing

Adjust the depth of threaded connections to make watertight bridging with the tiler easier.

Appliances, connections and built-in fittings

The walk-in shower: drainage, available height, slope and flow rate discharged

Secure the water seal and the drainage slope within the reduced thickness of modern screeds.

Appliances, connections and built-in fittings

Recessing a tap or mixer: depth, access provision and spare parts

Keep access to cartridges and valves so that work can be done later without removing the wall tiles.

Appliances, connections and built-in fittings

Connecting a washing machine: trap, loop height, stop valve and safety tray

Calibrate the discharge height and the anti-backflow cut-off to protect dwellings against flooding.

Appliances, connections and built-in fittings

The kitchen: manifold, isolating valves, waste outlet and space for the furniture

Position the sanitary connection points in a recess to clear the way for low kitchen units.

Appliances, connections and built-in fittings

Hanging a washbasin: reinforcement, suitable anchor and load-bearing support

Require suitable reinforcing cross-members in the metal framework to prevent pull-out under load.

Appliances, connections and built-in fittings

Accessible sanitary facility: heights, turning space, grab bars and taps

Respect the turning areas and the layout of grab rails to pass the accessibility checks.

Appliances, connections and built-in fittings

Protecting until handover: covering, scratches, construction-site limescale and joint inspection record

Fit effective basin protection to prevent damage to the enamel from construction site dust.

Appliances, connections and built-in fittings

Before closing up: the checklist that saves you from having to reopen

Tick off the pressure tests and thermal insulation so that technical ducts can be closed safely.