Skip to content
Website
🧱 CFC 250Drainage: stack, primary ventilation and sound insulationChapter 1 of 10 in the section

Gradient: the useful minimum, excessive gradient and deposits in the pipe

After this chapter, you will be able to size and set precisely the gradient of internal collector pipes and gravity connection pipes. You will understand the hydraulic mechanism by which suspended matter is carried, identify the self-cleansing velocity required by SN EN 12056, and avoid the classic trap of an excessive gradient, which separates the liquid phase from the solids while also causing trap siphonage.

Key takeaways

  • SN EN 12056 requires a minimum gradient to ensure the continuous transport of gravity-fed effluent.
  • A minimum self-cleansing velocity of zero point seven metres per second prevents any lasting sediment deposit.
  • Too steep a gradient separates the water film from the solids, which end up stranded.
  • The optimum fall is rigorously kept between one and two per cent, depending on the collector installed.

Ensuring hydraulic self-cleansing by respecting the minimum gradient

Self-cleansing velocity
Minimum flow velocity of the liquid stream that keeps heavy particles and faecal matter in suspension, thus preventing them from settling on the bottom of the pipe.

In a gravity internal drainage network, the carrying of faecal matter, greasy residues and cellulose depends directly on the ratio between the tractive force of the water and the friction of the solids against the pipe walls. SN EN 12056 defines the calculation principles for these installations by setting the hydraulic limits necessary for the longevity of the sanitary system.

To start the movement of the solids and ensure their complete discharge without any external mechanical energy, the water must reach a self-cleansing velocity of at least 0.7 m/s, with an ideal target value of 1.0 m/s in intermittent flow. If the pipe invert is laid with an insufficient fall, the flow velocity drops below this critical threshold: the liquid flows away slowly without carrying the solid mass with it.

Permissible flow gradients in internal networks for common diameters
Nominal diameter (DN)Minimum permitted gradientStandard installation gradientMean flow velocity
DN 56 (washbasins, bidets)1.0 % (10 mm/m)1.5 to 2.0 % (15-20 mm/m)0.7 to 0.9 m/s
DN 70 (sinks, showers)1.0 % (10 mm/m)1.5 to 2.0 % (15-20 mm/m)0.8 to 1.0 m/s
DN 90 (individual WC pans)0.5 % (5 mm/m)1.0 to 1.5 % (10-15 mm/m)0.8 to 1.1 m/s
DN 100 / DN 125 (collectors)0.5 % (5 mm/m)1.0 to 1.5 % (10-15 mm/m)0.9 to 1.2 m/s

During installation, the minimum flow gradient is checked with a graduated spirit level or a pipe laser on each socketed section. A collector suspended in the basement or laid in a service duct with a local sag forms a settling zone: grease solidifies there, paper accumulates there and the useful cross-section gradually reduces until the inner bore is completely blocked.

Avoiding loss of head and stranding of solids due to excessive gradient

The common site belief that giving as much fall as possible makes it easier to empty a fixture is a major hydraulic mistake. An excessive fall profoundly alters the structure of the gravity flow by causing the liquid phase to separate prematurely from the solids it is carrying.

When the angle exceeds a typical value of 4 to 5 % on a soil water pipe, the water accelerates abruptly and spreads in a very thin sheet along the bottom of the pipe. The water depth drops drastically and is no longer sufficient to carry faecal matter by flotation. Deprived of hydraulic buoyancy, the solids rub against the plastic walls, lose speed and become stranded midway while the liquid runs on ahead.

  • Phase separation: the water rushes ahead at high speed without carrying along the dense matter left behind.
  • Siphonage by Venturi effect: the acceleration of a liquid plug induces strong suction that pulls the water seals out of neighbouring traps.
  • Noise nuisance: excessive velocity generates violent impact noise at changes of direction, degrading the performance of soundproofed pipes.
  • Encrusted deposits: organic sludge dried out by the rapid passage of water hardens and forms successive solid blockages.

A durable sanitary installation requires the flow to be kept within a strict range: a gradient between 1 % and 2 % ensures a hydraulic filling ratio of between 50 % and 70 % of the usable diameter. This partial immersion ensures the flotation of solids, stabilises the upper air column used for pressure balancing and avoids the formation of unwanted noisy turbulence in the service ducts.

The flow range according to SN EN 12056 and the mechanics of two-phase flow

In a gravity sanitary drain, domestic effluent is not a homogeneous liquid but a two-phase mixture combining water, air and heterogeneous solids (faecal matter, toilet paper, fatty particles). The dynamic balance of this flow rests on a constant interaction between the hydrodynamic thrust of the flushing liquid volume and the friction of the solids against the inner walls of the pipe. According to SN EN 12056, reliable transport of these solids is only guaranteed if the self-cleansing velocity remains continuously within a narrow operating window, usually set between 0.7 m/s and 2.5 m/s.

The minimum flow gradient meets a strict physical requirement: preventing settlement. When the fall drops below 1.0 % (or even 1.5 % on small unventilated diameters), the driving energy supplied by gravity becomes lower than the friction forces. The self-cleansing velocity is no longer reached. The water flow loses its carrying capacity, the water film thins out as it spreads, and the solids settle at the bottom of the collector. With each successive flush, these residues bind grease and residual textile fibres, forming a compact plug by layering.

Conversely, the least recognised pitfall on construction sites is to imagine that a steep fall helps clean the pipe. The consequence of an excessive gradient, beyond 5.0 % in a continuous horizontal pipe, is just as destructive for the installation. Under a steep fall, the water accelerates rapidly, its dynamic viscosity is no longer enough to hold floating bodies, and the depth of the liquid sheet (filling ratio h/d) drops abruptly. The water escapes at high speed as a thin film, leaving the solids on the bottom of the pipe. Deprived of a carrying liquid, the solids become stranded and dry against the plastic or cast-iron wall before the next flush.

Permissible fall ranges for internal gravity drains
Nominal diameter (DN / OD)Minimum tolerated gradientOptimum self-cleansing gradientMaximum gradient in collector
DN 50 / OD 56 (washbasins, showers)1.5 % (15 mm/m)2.0 % to 3.0 % (20 to 30 mm/m)5.0 % (50 mm/m)
DN 70 / OD 75 (sinks, mixed connections)1.2 % (12 mm/m)1.5 % to 2.0 % (15 to 20 mm/m)5.0 % (50 mm/m)
DN 90 / OD 90 (individual WC connection)1.0 % (10 mm/m)1.5 % to 2.0 % (15 to 20 mm/m)5.0 % (50 mm/m)
DN 100 / OD 110 (collectors and stack bases)1.0 % (10 mm/m)1.2 % to 1.5 % (12 to 15 mm/m)4.0 % (40 mm/m)

Routing requirements and handling large level differences on the construction site

To comply with the limits set by SN EN 12056, the sanitary installer must refuse to fit the horizontal gradient directly to the constraints of beams, slabs or levels imposed by the structural work. If the space available between the fixture connection point and the collector suspended in the basement results in a continuous fall of more than 5 %, the connection must never be laid as a straight inclined line at 10 % or 15 %. Such a geometry would not only cause systematic stranding of faecal matter, but would also create unacceptable structure-borne and airborne noise at the fixing clamps.

  1. Laying the connection section at a self-cleansing gradientLay the horizontal collecting pipe from the sanitary fixture with a strictly calibrated gradient between 1.5 % and 2.0 %, up to the immediate vicinity of the drop axis.
  2. Creating a clean vertical offsetInsert a clean 90° vertical offset made of two 45° bends assembled with or without an intermediate sleeve, absorbing the whole lost height at once.
  3. Connection at the foot of the offsetContinue on the lower collector using long-radius fittings or 45° bends, then resume a regular laying gradient of 1.5 % towards the discharge stack.

On new builds or heavy refurbishments, the gradient must be checked with an adjustable-vial spirit level or a pipe laser before any final tightening of the clamps and before the screed encasement is poured. Particular attention must be paid to the direction of the sockets: the female end must always face upstream of the flow to avoid any internal mechanical step that could catch paper under low water-depth flow conditions.

Corrective measures for gradient faults and reworking of defective runs

On the construction site, discovering a levelling fault before the screed is poured or the ducts are closed requires immediate action by the plumber. When the minimum flow gradient is not reached or is reversed, the self-cleansing velocity drops below the critical threshold of zero point five metres per second. Faecal matter and paper come to rest at the bottom of the pipe, forming a dense sediment plug. Conversely, the consequence of an excessive gradient on a roughly horizontal section is the abrupt acceleration of the liquid stream: the water escapes at high speed in a thin layer, leaving the heavy matter stranded on the pipe invert.

  1. Reworking an insufficient gradient or a low pointRemove the fixing clamps and adjust the threaded rods to restore the set value defined according to SN EN 12056. If the allowance height is exhausted, change the connection point on the soil stack by coring lower down or realign the axis of the suspended collector.
  2. Correcting an uncontrolled excessive gradientReplace a straight run that is too steep with a compliant geometric arrangement: keep a collecting pipe at a fall of between one and two per cent, then absorb the level difference vertically using a drop fitted with forty-five-degree bends to regulate the fluid dynamics.
  3. Visual check and flow testCheck the alignment with an electronic spirit level and carry out a real flush test with test bodies before fitting the soundproofing and before the structural work crew seals the pipework in.

Frequently asked questions

How do you correct a sanitary collector with a reverse fall before the screeds are poured?

You must intervene on the clamping before the screeder arrives. Release the guide clamps and adjust the height of the threaded hangers to restore a regular downward line of at least one per cent. If the congestion under the slab or crossings of service ducts prevent the correction, the main drain connection must be re-cut or cored lower to guarantee a continuous gravity profile without any residual stagnation.

Why does a gradient above five per cent encourage deposits in a roughly horizontal pipe?

In two-phase flow, water and solids travel together thanks to a sufficient carrying water depth. When the gradient becomes excessive, the fluid velocity rises exponentially and the water slides at high speed under the solids without carrying them along. Deprived of dynamic hydraulic thrust, faeces and paper come to rest along the bottom of the pipe, causing stubborn blockages that subsequent flushes can no longer clear.

What is the self-cleansing rule prescribed by SN EN 12056 for suspended collectors?

SN EN 12056 recommends a design ensuring a flow velocity of between zero point five and one metre per second, with a filling ratio of around fifty per cent. This kinetic range mobilises the friction energy needed to bring sand, scale and heavy sediment back into suspension. A gradient of half to two per cent provides this self-cleaning function without generating excessive pneumatic turbulence.

How do you handle a large level difference without creating a continuous excessive gradient on the horizontal network?

To cross a significant level difference over a short distance, the pipe must never be laid on a continuous inclined plane. The recognised technique is to keep the standard service gradient of one to two per cent on the horizontal sections, then insert a direct vertical drop. The transition is made using two forty-five-degree bends to avoid hydraulic disruption and the acoustic nuisance of splashing.

Texts and standards cited

  • SN EN 12056Gravity drainage networks inside buildings: general principles, hydraulic calculation and installation requirements

In the same section