Key takeaways
- The hot work permit formalises the prior cleaning and the neutralisation of combustible insulation.
- The flexible heat screen protects the neighbouring walls and pipes from the torch's radiant heat.
- A suitable extinguisher must be within the operator's direct reach.
- Post-brazing supervision by thermal imaging tracks down hot spots over several hours.
Prepare the shaft area and formalise the hot work permit before lighting the torch
Brazing a copper tube for a drinking water distribution line inside a vertical service shaft exposes the plumber to a particular hazard. These confined spaces contain plastic drainage pipes, electrical cables and various insulation materials. According to art. 3 para. 1 OTConst, work is planned so that the risk of occupational accident, occupational disease or damage to health is as low as possible. In a riser, the heat supplied by the nozzle of the acetylene-oxygen or propane torch does not dissipate freely. The natural thermal draught turns the shaft into a duct that favours the spread of hot gases.
Carrying out open-flame work under these conditions requires a rigorously issued hot work permit. This written document commits the plumber, the construction site safety officer and the site management. It lists the singular points of the pipe route, the cleanliness of the work area, the type of heat-transfer fluid or pressurised water, and the emergency shut-off devices. Before opening the torch's gas valves, all packaging residues, cardboard and volatile materials are removed within a radius of five metres around the workstation.
- Clearing and folding back combustible insulation over a minimum distance of fifty centimetres on either side of the heating point.
- Checking that unsealed floor slab openings are closed to prevent drops of liquid brazing alloy from falling to the floor below.
- Removal or temporary bridging of the automatic smoke detectors on the landing concerned to prevent nuisance alarms.
- Prior wetting of mineral walls or thorough mechanical dust removal in the shaft.
Interpose the heat shield, position the extinguisher and carry out delayed supervision
Applying the flame to the copper fitting requires a continuous physical barrier between the heating cone and the rear walls of the shaft. The plumber systematically interposes a heat shield made of silica cloth or a rigid non-combustible class A1 calcium silicate board. This flame screen must cover the rear area generously and follow the shape of the through-sleeves. Flexible textile blankets make it possible to wrap the adjacent soundproofed polypropylene or cast-iron soil stacks to absorb the radiant flux.
Art. 82 LAA provides that the employer must take all measures to prevent occupational accidents and diseases that experience has shown to be necessary, that are applicable according to the state of the art and that are suited to the given conditions. At the brazing location, the presence of a suitable extinguisher is not a mere passive recommendation. The device, typically a 6-litre water-spray model with additive or a multipurpose powder model, must be placed on a clear floor, with the pin checked, directly accessible without the fitter having to step over obstacles or leave their stepladder. A bucket of clean water and a sponge complete the setup to cool metal parts immediately after the copper-phosphorus or silver alloy has melted.
| Material encountered | Reaction to heat | Preventive workshop measure | Inspection tool |
|---|---|---|---|
| Elastomeric foam | Rapid melting and emission of toxic fumes | Cut and remove over 50 cm | Direct visual check |
| Rock wool with kraft facing | Slow combustion of the tarred paper | Stripping off the combustible vapour barrier | Infrared thermal camera |
| Binder-free glass wool | Settling without flame below 600 °C | Silicate screen interposed | Contact thermometer |
| PP drainage pipe | Softening and geometric deformation | Enveloping thermal blanket | Dimensional check |
- Immediate active coolingAs soon as the torch is turned off, cool the brazed joint and the adjacent fixing clamps with a damp sponge to cut off thermal conduction in the piping.
- First post-flame inspectionVisually inspect the immediate surroundings, the slab penetration and the back of the protective screen for suspicious smells, whitish smoke or discolouration.
- Continuous observation watchMaintain a constant presence on the landing for the thirty minutes following the complete extinguishing of the flame, with the extinguisher ready for use.
- Delayed thermal patrolsCarry out systematic thermal-camera readings over a minimum of two hours, checking the lower and upper levels along the service riser before lifting the hot work permit.
Smouldering fire mechanism: tracking down hot spots in shaft insulation
Hard brazing of a copper distribution pipe requires a working temperature exceeding 600 degrees. In the restricted volume of a plumbing service shaft, the torch flame is not the only fire vector: the exceptional thermal conductivity of copper spreads the heat wave over several tens of centimetres beyond the fitting. When a tube passes through old insulation, a glass wool mat with a kraft vapour barrier or a sealing collar, the temperature rise initiates pyrolysis with no visible flame. This slow combustion can consume the core of the insulation for hours before breaking out into an open blaze, often well after the finishing work crews have left.
To eliminate this invisible risk, inspection by touch or by eye alone is prohibited. The foreman or the plumber responsible for the area must check the temperature drop using an infrared thermometer with laser sighting or a compact thermal camera. The measurement does not stop at the heating point: it sweeps the drinking water manifold, the acoustic-decoupling fixing clamps whose elastomer linings degrade under heat, and the hidden face of the slab penetrations. Supervision is suspended only when all neighbouring elements have returned to the ambient temperature of the shaft.
| Material in contact or nearby | Thermal reaction to hard brazing | Method of detecting the latent fire | Corrective action in the workshop or on site |
|---|---|---|---|
| Flexible elastomeric foam for cold water | Rapid melting with release of toxic gases, risk of lateral spread | Continuous thermographic monitoring and detection of acrid smell | Cut and remove the insulation over fifty centimetres before lighting the torch |
| Mineral wool with aluminium/kraft facing | Carbonisation of the kraft paper under the aluminium, smouldering fire undetectable by eye | Thermal-camera survey on both sides of the insulation mat | Mechanical spacing of the composite or interposition of a rigid screen |
| Acoustic-decoupling fixing clamps | Calcination of the rubber lining, loss of hold and glowing point | Spot temperature measurement with an infrared thermometer on the steel | Temporary removal of the clamp or protection with heat-protection paste |
| Accumulation of plaster dust and sawdust | Slow glowing by flameless combustion in the bottom of the shaft | Thorough optical inspection combined with a thermal reading at floor level | Prior industrial vacuuming of the opening before any work |
End-of-shift protocol, delayed supervision and closure of the hot work permit
The Ordinance on Construction Work requires strict planning of measures to prevent damage to health and fires at the workplace. For open-flame work, this requirement translates into the practical organisation of delayed supervision. Once the torch is out and the gas cylinders are closed at the regulators, the area remains under uninterrupted active watch during the first period defined by the hot work permit. The plumber keeps their water-spray extinguisher with additive, or foam extinguisher, suitable for class A and B fires, within reach; carbon dioxide is reserved for live technical cabinets.
The natural draught present in a vertical service shaft creates a chimney effect capable of drawing wisps of smoke to the upper levels or feeding fresh air to an incipient fire located under the slab. The post-fire patrol is therefore never limited to the room alone where the brazing was carried out. The plumber systematically inspects the lower level and the upper level, accessing the corresponding inspection hatches to check that there is no temperature rise along the riser route.
Closing out the work follows a rigorous formal procedure. At the end of the minimum delayed watch, generally set between one and two hours depending on the density of combustible elements listed on the document, the plumber and the construction site safety officer or the site supervisor carry out a joint check. They countersign the hot work permit, recording the final end time of the supervision, thereby validating the stand-down in compliance with the guidelines of the Association of Cantonal Fire Insurers. The extinguisher remains positioned on the floor until this final signature.
Emergency response: fire starting in a service shaft and recurrence of the fire
When the insulation ignites or a suspicious wisp of smoke escapes from the riser despite the heat shield, every second changes the scale of the incident. The vertical service shaft acts as a thermal chimney: the draught effect draws fresh air in from below and drives hot gases to the upper floors within a few tens of seconds. The first action is to cut the torch supply immediately at the gas regulators, then to attack the incipient fire with the extinguisher kept within direct reach of the workstation.
- Close the acetylene and oxygen valves, then purge the torches before moving the cylinders out of the radiant zone.
- Pull the pin of the suitable extinguisher and direct the jet at the base of the flames in short bursts, maintaining a safe distance.
- Alert the emergency services on the emergency number 118 at the slightest persistence of smoke or if the flame has penetrated inaccessible insulation.
- Evacuate the premises on the upper floors lying in the vertical axis of the shaft to prevent poisoning from toxic fumes.
After the fire brigade has intervened or the incident has been brought under local control, the construction site must secure the surroundings without altering the area where the fire started. The OTConst requires rigorous traceability of accidental events. The site supervisor records the exact time, the type of brazing carried out, the condition of the heat screen used and the thermographic readings. No damaged pipe or burnt insulation sleeve may be removed before the insurance experts and the site management have attended, otherwise it becomes impossible to establish responsibilities.
Frequently asked questions
Which extinguisher should you choose for a hard brazing workstation on copper tube in a shaft?
The 6-litre water-spray extinguisher with additive is the preferred means of intervention for the plumber. Unlike multipurpose powder, which irreparably destroys electrical panels and neighbouring technical installations, the additive-enhanced water effectively penetrates fibrous insulation or synthetic foams undergoing pyrolysis. It provides the cooling power essential to break the temperature rise of the copper without saturating the shaft with corrosive particles.
How do you correctly position the heat shield behind a fitting to be brazed?
The flame blanket must never simply be wedged against the rear wall. The plumber must wrap it in a trough shape behind the tube, leaving a ventilated air gap of at least two centimetres between the heat-resistant fabric and the flammable material underneath. If the manifold touches neighbouring insulation, a rigid non-combustible mineral board must be inserted to block both the radiation from the nozzle and direct conduction.
What should you do if smoke comes out of an upper floor during delayed supervision?
Start evacuating the area without delay and call 118, reporting a smouldering fire in a rising service shaft. Do not attempt to open the access hatches on the upper floors without respiratory protection: the sudden supply of fresh oxygen can turn a slow combustion into a sudden general blaze. Inform the site management immediately and prepare the location plans of the plumbing risers to guide the fire brigade.
Why is the thermal camera essential for ending supervision after brazing?
Visual inspection and checking by touch cannot detect internal combustion hidden behind a sheet-metal casing or a fixing clamp. The thermal camera makes it possible to map temperature gradients over the whole height of the shaft. It confirms that the pipes and adjacent materials have returned to ambient temperature, providing the objective evidence required to formally close the hot work permit at the end of the shift.
Texts and standards cited
- OTConstGeneral requirements on occupational safety, fire risk prevention and the organisation of rescue on construction sites.