Water hygiene: Legionella, temperatures and stagnation: the execution reference
Intended for team leaders, foremen and plumbing site managers, this section details the technical prevention of bacterial growth in drinking-water systems. From hot-water production to the point of draw-off, you will find the requirements of SIA 385/1 and the SSIGE guidelines for designing without stagnation, maintaining the regulatory temperature regimes, carrying out methodical flushing and ensuring the health safety of users without encroaching on the boiler room.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 5
60 °C
Minimum permanent temperature at the outlet of the domestic hot-water cylinder
55 °C
Minimum set-point temperature on the return of the hot-water circulation loop
25 °C
Maximum mandatory temperature threshold for cold-water supply networks
3 litres
Maximum water capacity of a terminal branch not connected to the circulation loop
72 hours
Maximum duration of hydraulic standstill before mandatory renewal of the water volume
Technical scope of plumbing and limits of intervention
Preserving the microbiological quality of drinking water is one of the main obligations of the CFC 250 plumbing installer. The fitter's responsibility begins at the point where the public network is entered, extends to the physical treatment of the water and to the internal distribution of cold water and domestic hot water, and ends at the draw-off fittings. The central issue is the definitive removal of the conditions favourable to the growth of Legionella and biofilm: control of the temperature ranges and the systematic eradication of zones of hydraulic stagnation.
This section deals exclusively with the physical, constructional and hydraulic measures applicable to internal distribution networks under SIA 385/1 and the guidelines of the Swiss Gas and Water Industry Association (SSIGE). It covers neither the structural work of service shafts, nor the perimeter insulation of slabs, which falls to the CFC 281 screed layer, nor the floor waterproofing under tiling governed by CFC 282. The plumber guarantees the integrity of the loop, the insulation of pipes to prevent the cold water from warming up, and compliance with the prescribed hydraulic balancing flow rates.
| Component or service | Responsible trade | Standard or requirement | Role of the CFC 250 plumbing installer |
|---|---|---|---|
| Hot-water cylinder (drinking-water side) | Plumbing installer (CFC 250) | SIA 385/1, SSIGE guidelines | Plumbing connection, safety group, circulation loop tee |
| Heat production and primary heat exchanger | Heating installer (CFC 241) | Cantonal energy regulations | Transmission of power requirements and plumbing set-points |
| Back-up electrical supply and pumps | Electrician (CFC 232) | Standard on low-voltage installations | Installation and hydraulic connection, checking the direction of rotation |
| Ventilation of risers and service shafts | Ventilation fitter (CFC 244) | VKF fire protection guidelines | Proper execution of the primary stack ventilation |
Learning path and logic of intervention on the construction site
To guarantee water that meets the requirements of the federal ordinance on drinking water, the installation team must organise its work in a logical sequence: thermal sizing, rigorous geometric layout, methodical commissioning and preventive maintenance. The ten chapters of this section are arranged to accompany the construction site from the technical sketch to day-to-day operation.
- Phase 1: Hydraulic design and temperature controlLearning begins with setting the temperature thresholds prescribed by SIA 385/1 (L3-01). This is followed immediately by the geometric diagnosis of the networks to rule out dead legs (L3-02) and to incorporate series distribution loops ending at the most heavily used appliance (L3-09).
- Phase 2: Acceptance, commissioning and initial disinfectionBefore any contact between users and the installation, the strict protocol of methodical flushing with filtered water must be recorded in a report (L3-03). In the event of a microbiological anomaly or refurbishment, the safe management of a thermal shock prevents serious burns (L3-04), complemented by aseptic sampling techniques for accredited analyses (L3-05).
- Phase 3: Specific operation, terminal points and maintenanceTerminal components are the primary vector of exposure through aerosols: the maintenance of flexible hoses and shower heads requires absolute vigilance (L3-07). Since scaling of exchangers and cylinder bases fosters bacterial colonies, chemical descaling without attacking the metals is essential (L3-06). Finally, the intermittent-use regimes of schools and hotels require dedicated automation (L3-08), concluded by the legal delimitation of responsibilities at handover of the work (L3-10).
📘 Chapters in this section 10
The temperatures that matter: storage tank, flow, loop return and at-risk zone
Set your cylinders and loop returns to the exact temperatures to stop bacterial growth dead.
Water hygiene: legionella, temperatures and stagnationThe dead leg: the real cause of contamination, and how to eliminate it
Permanently remove blind stub pipes to eradicate the hidden sources of contamination in the network.
Water hygiene: legionella, temperatures and stagnationFlush before handover: vacant dwelling, flushing protocol and written record
Apply the methodical flushing protocol on a new network in order to hand over a microbiologically sound installation.
Water hygiene: legionella, temperatures and stagnationThermal shock: procedure, duration, burn risk and informing occupants
Carry out high-temperature thermal disinfection while controlling the risk of burns to users.
Water hygiene: legionella, temperatures and stagnationTaking and reading a water analysis: sampling point, method and follow-up actions
Take representative sterile samples so that you can interpret the reports of the cantonal laboratories without error.
Water hygiene: legionella, temperatures and stagnationLimescale: where it forms, what it costs, how to descale without causing damage
Remove limescale from hot-water cylinders without damaging the metals, to destroy the bacteria's shelter.
Water hygiene: legionella, temperatures and stagnationThe shower head: aerosol, biofilm in the hose and replacement
Replace degraded flexible hoses and sanitise the shower heads to neutralise pathogenic aerosols in the shower.
Water hygiene: legionella, temperatures and stagnationIntermittent use: schools, hotels, holiday homes and the flushing plan
Programme automatic flushing suited to periods of prolonged vacancy in schools and holiday homes.
Water hygiene: legionella, temperatures and stagnationDesigning against stagnation: series loop, most-used fixture at the end
Connect your appliances in a through-flow series loop to renew the water with every flush.
Water hygiene: legionella, temperatures and stagnationWho is answerable for the water: design, installation, operation and handover
Formalise the handover report to clearly delimit your warranty in relation to operational management.