Key takeaways
- A dry surface finish frequently conceals a pool of water trapped in the thermal or acoustic insulation under the screed.
- Capacitive surface measurement remains insufficient to authorise the closing of a service duct after water damage.
- Mechanical drying by air injection often requires three to six continuous weeks of operation under monitoring.
- The installer must give written notice of their refusal to install equipment on a build-up that is still damp.
The surface-drying trap and residual water trapped under the screed
When a drinking-water pipe bursts or a joint comes apart on a soil stack, water seeps down by gravity along the service ducts and penetrates under the floating screed. The free water spreads quickly through the acoustic or thermal insulation layer, made of expanded polystyrene, polyurethane or mineral wool. While the ambient air and the mortar surface dry out within a few days through natural ventilation, the insulation build-up remains saturated with liquid water. The polyethylene film placed under the screed blocks evaporation upwards, turning the levelling fill into a confined reservoir that cannot dry out on its own.
| Insulation material | Retention mechanism | Plumbing technical risk | Drying possibility |
|---|---|---|---|
| Expanded polystyrene (EPS) | Water trapped between the beads and at panel joints | Corrosion of embedded plumbing pipes | Drying by vacuum dehydration possible |
| Mineral wool (glass or rock) | Total capillarity, settlement and loss of cohesion | Massive mould and permanent loss of acoustic performance | Complete removal and replacement required |
| Spray-applied polyurethane foam | Pockets of standing water on the underside, on the slab | Musty odours along pipe penetrations | Extraction of dried air through targeted core drillings |
The plumbing installer must never validate the reinstatement of casings on the basis of a simple visual check. Where the levelling fill contains supply networks or drainage collectors, standing water attacks the metal fixings and causes permanent condensation in unventilated ducts. Remediation requires mechanical action by negative pressure, managed by a specialist firm, in order to extract the liquid water before any closing-up of the finishing work.
Depth measurement, remediation times and formalising the refusal to proceed
To verify the real condition of the substrate, the moisture check must absolutely reach the insulation layer. Surface moisture testers with dielectric contact do not penetrate the thickness of the mortar. The technical investigation requires drilling small-diameter holes in the screed, away from the routes of the plumbing pipes and heating loops, in order to insert equilibrium relative humidity probes into the core of the insulation. Analysis of air extracted from beneath the screed makes it possible to quantify residual water vapour. A relative humidity above 75% in the insulation void indicates the continued presence of free water.
- Locating the plumbing networksIdentify the supply and drainage routes using as-built drawings or a thermal camera to avoid any accidental drilling during sampling.
- Drilling depth test holesDrill holes of 12 to 20 millimetres down to the raw concrete to probe the insulation without damaging the protective sleeves of the pipes.
- Installing the humidity sensorsInsert sealed probes to record the equilibrium relative humidity of the interstitial air once the temperature has stabilised.
- End-of-drying checkWait 48 hours after the dehumidifiers are switched off before the final measurement, to prevent the rebound effect of residual moisture.
If the site management or the client demands the closing of the technical partitions to keep to the programme while the measurements reveal excessive moisture, the installer must act formally. Under art. 365 para. 3 CO, if the material supplied by the client or the ground designated by them is found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must immediately inform the client, failing which they bear the consequences. In practice, the notice is sent the same day by registered letter or by e-mail with acknowledgement of receipt.
Behaviour of floor build-ups and kinetics of technical drying
When a drinking-water pipe bursts or a drain joint comes apart under a service duct, water instantly seeps into the low points of the raw slab. In a typical Swiss floating screed configuration, the liquid passes through the perimeter expansion joints or the openings for soil stacks and saturates the thermal or acoustic insulation layer. Whether the insulation consists of expanded polystyrene, spray-applied polyurethane foam or resilient mineral wool panels, the water ends up trapped under the polyethylene decoupling sheet of the screed. At the surface, the mortar or flowing screed appears perfectly dry after a few days of natural ventilation, while the insulation sits in several hundred litres of standing water.
Letting a floor build-up dry naturally is a technical illusion: without forced air circulation under the separating film, residual moisture stays trapped for six to twelve months. The water seeks lateral outlets by capillarity, rising into the bases of light partitions, water-resistant plasterboard and the metal structures of WC or washbasin support frames. To remove this volume, the intervention of a specialist technical drying firm is essential. The process consists of core drilling the screed down to the insulation layer in order to inject dehumidified air under pressure into it, or to extract the saturated air in a closed loop via condensation or adsorption dehumidifiers.
| Type of insulation under screed | Behaviour with water | Recommended extraction method | Minimum active drying time |
|---|---|---|---|
| Mineral wool (acoustic) | Total loss of load-bearing capacity, massive capillary retention, biological risk | Vacuum extraction with HEPA filtration and adsorption dehumidification | 4 to 8 weeks (often unrecoverable) |
| Expanded polystyrene (EPS) | Low internal absorption, water trapped between the beads and under the boards | Dry air injection or overpressure through corner core drillings | 3 to 5 weeks |
| Spray-applied polyurethane (PUR) | Closed-cell structure, standing water on the slab and in corrugated ducts | Spot extraction at the low point and drying of the sleeves under forced airflow | 2 to 4 weeks |
| Lightweight aggregates / clay beads | High hygroscopic retention along embedded pipes | Continuous hot-air extraction and intensive dehumidification | 5 to 8 weeks |
Depth measurement and formalising the refusal to close up
For the plumbing site foreman, the major trap is to accept the reinstallation of sanitary fixtures or the closing of service ducts on the sole basis of a visual test or a capacitive surface measurement. A pin-type moisture tester placed on top of the screed only probes the first twenty millimetres of the material. To assess the real soundness of the substrate before anchoring the self-supporting frames and connecting the supply networks, the check must probe the core of the build-up. The reference method consists of measuring the equilibrium relative humidity of the interstitial air at insulation level using hygrometric probes inserted in sealed boreholes, or of taking core-drill samples for verification by the calcium carbide or gravimetric method.
As soon as the depth measurements reveal a residual moisture level incompatible with the mechanical hold of the anchors and the soundness of the structure, the plumbing installer must suspend their finishing operations. Under pressure from the construction programme imposed by the site management or the client, the tradesperson must on no account yield to verbal instructions to close up the casings. In application of the duty of care under the Code of Obligations (CO) and the SIA 118 standard, the firm must issue a formal notice of interruption on the grounds of an unsuitable substrate.
- Documented joint inspection recordCarry out the in-depth relative humidity readings in the presence of the site management and the person responsible for technical drying, recording the measured values and the exact locations.
- Drafting the reasoned refusalSend without delay a registered letter or a formal notice entered in the site diary stating the refusal to install the sanitary equipment and to close up the ducts as long as the moisture of the insulation exceeds the admissible thresholds.
- Notification of the programme slippageState in writing that the incompressible active drying time delays the final plumbing work by the same amount, in order to avoid any liability for late-completion penalties.
- Final release verificationRequire the end-of-drying report issued by the specialist firm before authorising the teams to fix the frames permanently and connect the waterproofing elements.
Crisis management and refusal to proceed under programme pressure
On a construction site hit by water damage, the pressure from the site management to reinstall the sanitary fixtures and close up the service ducts becomes critical as soon as the screed looks dry. The plumbing installer is on the front line: reinstalling watertight elements on an unstabilised substrate guarantees the appearance of mould, the deterioration of the bases of light partitions and the rotting of the acoustic insulation under the screed. Faced with a verbal instruction to carry on with the work, the only professional reaction is to stop the installation work immediately and to demand traceability of the remedial measurements.
- Immediate written notificationDraft a formal notice of reservation addressed to the site management and the client, in application of the SIA 118 standard and the Code of Obligations (CO). State the refusal to carry out the plumbing installation until the technical drying of the underside has been certified.
- Joint in-depth checkRequire the appointed drying firm to carry out moisture measurements by deep probe or carbide method in the floor build-up, at the insulation, with a joint reading recorded in the site minutes.
- Protection in case of a forced written orderIf the client imposes closing-up despite the reservations, require a written service order explicitly releasing the plumbing installer from any damage resulting from residual moisture.
Frequently asked questions
What should you do if the site management demands the installation of support frames before drying is complete?
You must formally refuse to proceed by means of a reasoned letter of reservation. Explain in writing that sealing frames or closing up casings over a damp slab or insulation blocks evaporation and causes rapid biological deterioration. Recall the requirements of the SIA 118 standard: without a written service order fully releasing you from liability for future defects, keep the installation work stopped in the affected area.
How can you prove that the insulation under the screed is still soaked if the surface is dry?
A capacitive surface measurement is never sufficient after a major water incident. You must ask the drying specialist to carry out an in-depth moisture measurement, either by inserting an equilibrium hygrometric probe under the floating build-up, or by core drilling and sampling. The reading of the relative humidity of the interstitial air under the screed remains the only indisputable proof of the presence of trapped free water.
How long does technical drying of a flooded floor build-up really take?
For a floating screed on mineral wool or polystyrene, the mechanical drying time using dehumidifiers and injection fans generally ranges from three to six weeks. If the water has stood for several days or if the perimeter joints are saturated, the process can exceed two months. No natural drying with windows open can extract the moisture trapped under the vapour barrier film within timescales compatible with the construction programme.
What entry should be made in the site report when water damage occurs during installation?
Immediately record the date, the exact time of the leak, the origin of the flow and the rooms affected. State explicitly that the water seeped along the walls and under the floating screeds through the openings for stacks. Conclude with a suspensive wording stating that connection work and fixture installation are postponed until compliant results of the in-depth moisture measurement have been received.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work, duties of notice and management of the contractor's technical reservations.