🧱 CFC 250Water hygiene: legionella, temperatures and stagnationChapter 3 of 10 in the section

Flush before handover: vacant dwelling, flushing protocol and written record

A sanitary installation fitted in spring and accepted in autumn presents a major health risk due to prolonged water stagnation. This chapter details the method for removing biofilm, the flow rates and flushing durations point by point according to SVGW guidelines, and the drafting of the flushing record to guarantee flawless water and discharge your liability.

Key takeaways

  • Six months of stagnation favours the massive growth of pathogenic bacteria in water-filled pipes.
  • Flushing is always carried out without aerators, from the point closest to the end of the distribution system.
  • Each draw-off point must run until the water is clear and its temperature has stabilised.
  • The record logs the durations, temperatures and flow rates measured to prove compliance before final handover.

Removal of aerators and systematic flushing of the network after six months of shutdown

On a construction site for apartment blocks or villas whose structural work was completed in March, the initial pressure tests are often carried out with drinking water. If occupancy only begins in September, the water remains trapped in the pipes for six months at summer ambient temperatures that favour microbial growth. According to the SVGW guidelines on drinking water installations, water must not stagnate for more than seven days without being completely renewed. After such a period of rest, the installer must consider the water in the network as unfit for consumption and carry out a complete renewal of the water volume before the occupants start using it.

  1. Preparation and removal of terminal fittingsRemove by hand or with a suitable assembly key every aerator, aerating nozzle and flow straightener from all mixers and taps. Remove the shower hoses and their heads so that the supply outlets are left with a free cross-section, ensuring maximum flushing flow without back pressure.
  2. Progressive flushing from the riser to the branchesFirst open the drain valve at the foot of the rising distribution riser to remove the heavy deposits accumulated in the main sections. Then work upwards floor by floor, proceeding from the draw-off point closest to the riser to the furthest.
  3. Simultaneous dynamic flushing of the fixturesIn each wet room, open all cold-water draw-off points at the same time at full cross-section to generate a high flow velocity capable of detaching the biofilm attached to the walls of multilayer or stainless-steel pipes.

Checking physical parameters, target flow rates and drawing up the record

Flushing is not simply letting the water run at random: it follows measurable criteria of volume exchange and temperature stabilisation. The sanitary installer uses a graduated bucket and a stopwatch to validate the draw-off flow rate, and an immersion-probe thermometer to measure the temperature continuously. The operation starts with the cold drinking-water network until the temperature matches that of the public distribution main, which must be strictly below 20 °C. The operation is then repeated on the domestic hot-water network, where a clear and continuous rise in temperature is expected, guaranteeing the flushing of dead legs and floor loops.

Minimum target flushing values by type of sanitary fixture
Sanitary fixtureMinimum indicative flow rateMinimum continuous flushing timeCriterion for stopping the operation
Kitchen sink10 to 12 l/min3 minutesStabilised temperature, perfectly clear water
Washbasin / hand basin6 to 8 l/min2 minutesComplete absence of odour and residual air
Bath / shower15 to 18 l/min3 minutesDischarge of three pipe volumes
WC cisternFloat valve flow rate2 filling cyclesPerfectly clear water in the cistern

Documenting the intervention is essential to prove the proper performance of the work within the meaning of art. 367 CO, which governs the inspection of the work at handover. The installer records on the flushing record the date, the site details, the method applied, the flow rates measured, and the initial and final temperatures measured at each sampling point. This document, signed jointly by the sanitary site foreman and the site management, is appended to the operating file handed to the owner before the tenants move in. The flow straighteners, previously cleaned and disinfected in a suitable solution, are refitted only after the record has been signed.

Sequential opening protocol and flow regimes at the fixtures

After six months of stationary water between March and September, putting a dwelling back into service cannot be limited to quickly opening the taps. The summer heat accumulated in the service ducts favours the adhesion of microbial biofilms on the inner walls of multilayer or stainless-steel pipes. To remove these deposits without contaminating the angle stop valves or clogging the thermostatic cartridges, flushing requires a minimum flushing velocity and a rigorous sequence at each sanitary fixture.

Flushing always begins with the main distribution pipe and the rising riser, fully opening the drain valve located at the foot of the riser or on the landing manifold, in order to discharge the stale water directly to a temporary drain without passing through the internal networks of the dwelling. Once the riser is clear, the fitter works inside the apartment, progressing from the draw-off point closest to the floor manifold to the furthest point. This approach avoids pushing the stagnant volumes from the start of the network towards the dead ends.

Flow parameters and flushing durations per draw-off point after summer stagnation
Draw-off pointTarget flow rateMinimum flushing timeVisual and thermal check points
Outdoor tap or laundry room tap15 to 20 l/min3 minutesNo turbidity, cold-water temperature below 20 °C
Kitchen sink (cold and hot water)10 to 12 l/min5 minutes per lineHot water stabilised above 50 °C, clear water
Bath and shower (without hose or head)12 to 15 l/min5 continuous minutesDischarge without backflow, check of initial colouring
Washbasin and hand basin6 to 8 l/min3 minutesStable dynamic pressure, complete absence of stagnation odour
WC cisternFull cistern volume4 consecutive cyclesCleaning of the cistern bottom, watertight closing of the float valve

For mechanical or thermostatic mixers, the operation must be carried out in two stages: first on the cold-water position alone until fresh, clear water is obtained, then on the maximum hot-water position to discharge the lukewarm water from the domestic hot-water supply pipes and floor branches. The shower hoses must remain removed during this phase, with the water running freely from the wall connection or the lower outlet of the mixer, in order to avoid the formation of aerosols that the operator could breathe in.

Formal recording, flushing report and transfer of custody

Flushing only delivers its technical and legal value if it is the subject of a precise, countersigned record. As long as the building is unoccupied, responsibility for the hygiene of the installation lies with the contractor. Once the water has been renewed and the temperature parameters confirmed, the flushing record is the certificate required by the site management and the property management before the final handover of the keys to the owner or tenant.

  1. Recording temperatures at the terminal pointsUsing a calibrated probe thermometer, measure the cold-water temperature after stabilised flow, which must remain strictly below 20 °C. Record the domestic hot-water temperature, which must quickly reach at least 50 °C at the draw-off points to guarantee renewal of the loop.
  2. Refitting disinfected aerators and filtersRefit all flow straighteners, aerators and flow regulators that have been descaled and cleaned beforehand. Connect new or flushed shower hoses, then check that there is no leakage whatsoever under dynamic pressure at each sealing joint.
  3. Drafting and signing the recordRecord in writing the date of the intervention, the estimated flow rates, the total volumes drawn off at the main meter, the temperatures measured and any anomalies noted on the stop valves.
  4. Sealing or locking-off of the installationsIf the occupants do not move in on the same day, close the main stop valve of the apartment and apply a seal or a warning label stating the date of the last compliant flushing in accordance with the SVGW guidelines.

The final document is countersigned by the sanitary foreman and by the representative of the site management or of the property management. This report formally releases the installer from custody of the work for the sanitary trade package. It certifies that the network was returned in a hygienic condition meeting potability requirements at the precise moment of transfer, thereby delimiting responsibilities in the event of a later claim relating to the taste of the water, its colouring or bacterial growth caused by delayed occupancy.

Handling non-conformities during flushing and corrective measures

After six months of complete shutdown between March and September, systematic flushing does not always guarantee an immediate return to compliance. When the water drawn off retains a rust colour, abnormal turbidity or musty odours after the theoretical flushing time, the sanitary installer must suspend the standard protocol and isolate the section concerned. The persistence of these signs reveals the presence of encrusted biofilm or the accumulation of mineral deposits in low-circulation zones, in particular on distribution loops or terminal branches under the screed.

  1. Checking filters and pressure reducersRemove the screen of the water inlet filter after the main meter. Bringing the network up to flow velocity often detaches heavy particles that immediately saturate the filter medium and choke the flushing flow.
  2. Pulsed air-water flushingIf simple hydraulic flushing is not enough to clear the water, connect an approved flushing compressor to inject trains of oil-free compressed air bubbles, in accordance with SVGW Guideline W3, in order to mechanically detach the biofilm.
  3. Sampling for microbiological analysisTake a water sample from the most unfavourable draw-off point after temperature stabilisation to measure the mesophilic aerobic bacteria count and test for the presence of legionella in an accredited laboratory.

If the microbiological analyses reveal that potability thresholds have been exceeded, the network cannot be handed over to the client. The installer records the values obtained, notifies the ban on putting into service by a written notice of non-conformity and initiates a thermal or chemical disinfection protocol governed by SVGW guidelines W3/E3. The installation remains under the legal custody of the contractor until a compliant analysis certificate is obtained, guaranteeing the absence of any health risk before the final handover of the keys to the tenants.

Frequently asked questions

What should be done if the water remains lukewarm or coloured after ten minutes of continuous flushing?

Stop drawing water and check the condition of the main filter at the building inlet. Water that does not cool down often indicates a poorly balanced thermal loop or a service duct overheated by uninsulated heating pipes. If the colouring persists, carry out mechanical air-water flushing on an isolated section, completely remove the thermostatic cartridges of the showers to clean the strainers, then take a sample for microbiological testing.

Who bears the cost of the water consumed when flushing a vacant building?

The supply of fluids for testing and commissioning is the client's responsibility under standard SIA 118, unless explicitly stated otherwise in the special specifications. The sanitary installer reads the main water meter index before starting the operations and immediately after completing the protocol. These values are entered on the flushing record in order to document precisely the volumes needed to sanitise the network.

Can terminal flushing be replaced by simply draining at the floor stop valves?

No, this method does not comply with the SVGW guidelines. The six months of stagnation occurred mainly in the floor distribution pipes and the individual branches leading to the sanitary fixtures. Opening only the riser valves leaves stagnant all the water contained in the connecting hoses, the mixer bodies and the embedded multilayer pipes. Flushing must always be carried out point by point, with aerators removed, right up to each outlet spout.

How should the intervention be recorded if the client refuses to sign the record?

In the event of a dispute or the absence of the site management representative, the installer sends the complete flushing protocol by registered letter on the same day. The file includes the flow readings, the stabilisation temperature curves, the volume of water renewed and the photos of the filters checked. This formal notification establishes material proof that the rules of the trade were properly followed before the installations are handed over.

Texts and standards cited

  • Directives SSIGE W3Guidelines for drinking water installations
  • Directives SSIGE W3/E3Hygiene in drinking water installations
  • Norme SIA 118General conditions for the execution of construction work