🧱 CFC 250Drainage: stack, primary ventilation and sound insulationChapter 8 of 10 in the section

Passing through a slab: fire-stop sleeve, sealing and acoustic decoupling

A floor penetration by a plastic drainage pipe breaks the fire integrity of the compartmentation. This chapter details the compliant installation of an approved fire-stop sleeve, the rigorous sealing of the opening, the acoustic decoupling essential against structure-borne noise, and the fitting of the mandatory identification plate needed to validate acceptance by the building inspectorate.

Key takeaways

  • The AEAI-approved fire-stop sleeve must match the exact diameter and material of the pipe.
  • Sealing the opening requires a full mortar fill with no residual voids around the sleeve.
  • Acoustic decoupling prevents flow noise from being transmitted directly to the load-bearing structure of the building.
  • The identification plate fitted on site certifies the conformity of the device during the official fire inspection.

Selecting and fixing the fire-stop sleeve according to the AEAI approval

Intumescent fire-stop sleeve
Mechanical sealing device in galvanised steel containing a graphite-based intumescent material. When the temperature rises, the insert expands rapidly to crush the plastic pipe and close off the passage of fire.

In a fire, a drainage pipe in polyethylene (PE-HD) or mineralised polypropylene melts within a few minutes, leaving a gaping opening through the reinforced concrete slab. This breach acts as a draught flue that spreads toxic gases and fire to the upper floors. To restore the fire resistance of the compartmentation required by the AEAI directives (generally EI 30, EI 60 or EI 90 depending on the use and the geometry of the building), the sanitary installer must fit a certified fire-stop sleeve. The certificate of use issued by the AEAI specifies rigorously the type of polymer permitted, the range of outside diameters, and the installation method: integrated in the formwork before concreting, or fitted to the underside of the slab.

  1. Geometric check and cleaning of the substrateCheck the actual outside diameter of the drainage pipe and the geometry of the opening or core hole. Carefully remove dust from the underside of the concrete slab around the penetration to ensure a perfectly flat bearing surface.
  2. Fitting the intumescent shellOpen the hinged metal housing, snap it firmly around the pipe flush with the underside of the reinforced concrete, then lock the zinc-plated closing tab without deforming the casing or abnormally compressing the intumescent material.
  3. Mechanical anchoring to the structural workDrill the slab through the fixing lugs of the sleeve with a suitable concrete drill bit. Use only non-combustible fixings in galvanised or stainless steel, and never any plastic plug.

Ensuring fire-stop sealing, acoustic decoupling and statutory labelling

Mechanically fitting the housing under the slab or recessed is only the first step of the compartmentation. The annular space remaining between the sound-insulated drainage pipe and the walls of the concrete opening must be carefully sealed to stop cold and hot smoke. This sealing is done with a non-shrink mortar, a fire-resistant plaster or a compatible intumescent sealant, in accordance with the manufacturer's AEAI approval report. At the same time, the SIA 181 standard requires rigorous acoustic decoupling to prevent flow noise and impact noise from spreading to the load-bearing structure of the building. The installer must therefore combine fire tightness and acoustic decoupling by using a closed-cell resilient insulation strip, accepted in the certified fire-stop system without risk of creating a structure-borne acoustic bridge.

Components of a compliant slab penetration
ElementRequired materialMain functionSite check point
Drainage pipeSound-insulated PE-HD or PPGravity drainage of waterOutside diameter and material compliant
Fire-stop sleeveSteel housing and graphite insertAutomatic sealing under the action of fireValid AEAI approval and metal fixing
Annular sealingNon-shrink mortar or approved sealantTightness to smoke and flamesFull fill with no residual cavities
Acoustic insulationThin certified resilient stripBreaking structure-borne acoustic bridgesNo direct pipe-to-concrete contact whatsoever
Identification plateMetal sheet or indelible labelTraceability and conformity checkVisible installation and legible markings

Once the sealing and decoupling are complete, the sanitary installer immediately fits the statutory identification plate supplied by the manufacturer, either on the metal housing or on the slab next to the opening. This unalterable label records the product reference, the AEAI certificate number, the fire resistance class achieved, the name of the installing company and the date of installation. Without this legible marking, the municipal inspectors of the building inspectorate and the fire protection experts refuse acceptance of the work. The installer also includes a copy of the certificate of conformity and the technical data sheets in the as-built file intended for the client.

Coordinating sealing, opening filling and acoustic decoupling

Passing a drain stack through a solid concrete slab creates a double, contradictory requirement on the construction site: ensuring tightness to smoke and flames according to the AEAI fire protection requirements, while guaranteeing the mechanical decoupling prescribed by the SIA 181 standard to avoid transmission of structure-borne noise. When the plastic pipe melts under heat, the fire-stop sleeve must crush the pipe without meeting any rigid obstacle. The sanitary installer therefore cannot improvise the gap between the pipe, the acoustic insulation and the slab.

Sealing the raw opening or core hole tolerates no untested combustible filling material. After mechanically fixing the sleeve housing in the concrete, the residual void around the penetration must be filled with a class A1 non-shrink grouting mortar or a fire-resistant plaster approved in the declaration of conformity of the device manufacturer. The use of ordinary polyurethane foam expanded on site is prohibited, because it releases toxic gases and burns quickly without offering the mechanical resistance needed for the intumescent mass to expand inwards into the pipe.

  1. Cleaning and dusting the openingBrush the core hole or the formed opening to remove any trace of laitance, release oil or concrete debris before applying the sealing products.
  2. Fitting the compatible acoustic decouplingWrap the approved resilient sleeve around the pipe at the slab penetration, without any break, to eliminate direct contact between the plastic wall of the drain and the sealing mortar.
  3. Mechanical fixing of the fire-stop sleeveAnchor the metal frame of the sleeve firmly to the underside of the slab or embed it according to the intended installation type, using only fire-resistant steel anchor studs, with plastic plugs strictly excluded.
  4. Filling with non-shrink mortarCompletely fill the space between the core hole and the resilient sleeve with a dense mineral mortar over the full thickness of the slab in order to restore the fire-resisting mass per unit area of the floor.

Traceability labelling, self-inspection and acceptance before closing the shaft

A fire-stop penetration is deemed legally and technically compliant in the eyes of the fire protection authority only if it can be identified unambiguously. Each sleeve installed on a drain stack or primary ventilation stack must receive an unalterable identification label, riveted or glued to the body of the housing or fixed in the immediate vicinity on the slab. This plate certifies that the sealing was carried out in accordance with the approval requirements and directly engages the liability of the sanitary installation company carrying out the work.

Checking the conformity criteria of a fire-stop slab penetration
Item inspectedTechnical requirementVerification method on site
Sleeve approvalValid AEAI certificate number and required EI class (EI 30 to EI 90)Visual check of the factory marking and comparison with the data sheet
Anchoring to the substrateExpansion metal fixings in steel, no fusible materialCheck for the absence of nylon plugs at the clamping lugs
Continuity of the sealingFilled to refusal over the full slab thickness with mineral mortarVisual probe before closing the service shafts and fitting the linings
Statutory labellingPlate completed: date, installer, product, certificate, EI resistanceCheck of presence and legibility from the inspection hatch

The sanitary team leader records each penetration on a fire as-built plan and completes the self-inspection protocol of the supplier or of the suissetec trade association before the plasterer or mason closes the service shafts. The photos of the labelled seals, taken before lining, are the essential evidence for signing the certificate of conformity sent to the site management and to the cantonal fire insurance. Any labelling omission found at the final inspection leads to partitions being demolished at the sanitary contractor's expense for destructive verification.

Handling penetration non-conformities and acceptance before closure

On the construction site, disputes over slab penetrations almost always arise when the partitioning of the service shaft has been fitted before the formal check of the penetrations. As soon as plasterboard conceals the opening, the fire safety officer or the client's safety officer can demand the complete opening of the shafts at the sanitary contractor's expense if no traceable evidence is provided.

The first recurring defect is the acoustic bridging created by careless filling. When a mason or fitter pours standard mortar in direct contact with a drainage pipe without interposing a resilient sleeve or compressible insulation, the slab transmits all the noise of falling water into the neighbouring apartments. To correct this error without destroying the pipe, it is necessary to core or chisel around the pipe over the full thickness of the slab, restore an elastomer strip or a certified mineral wool shell, then redo the sealing according to the sleeve manufacturer's requirements.

Corrective measures for non-conformity in a slab penetration
Anomaly foundDirect consequenceImmediate technical action
Offset opening or pipe pressed against the concreteImpossible to fit the intumescent collar, and acoustic bridgeOff-centre clearance coring, fire-stop sleeve suited to an off-centre pipe, or surface-mounted fitting under the slab
Rigid mortar sealing without insulating stripFailure to meet noise protection requirementsClearing around the pipe with a point chisel, fitting an acoustic sleeve, approved sealing
Identification plate missing or incompleteAcceptance refused by the fire protection authorityCheck of the AEAI approval of the installed product, fitting of the riveted label and record of inspection

The second major trap concerns the choice of a sleeve incompatible with the material of the plastic pipe used (PE-HD, Silent-db20, sound-insulated PP or PVC). A sleeve tested for a standard pipe does not necessarily react with the same kinetics on a thick-walled sound-insulated pipe. If the inspection body refuses the installation, the sanitary contractor must replace the device with a sleeve certified under the AEAI fire protection directives for the exact piping system, apply the unalterable conformity label with an indelible marker and record each point with a geolocated photograph in the self-inspection file given to the site management.

Frequently asked questions

How do you handle a penetration if the drainage pipe is pressed against the wall of the hole?

When the pipe touches the concrete, there is no room for the acoustic shell and the recessed sleeve. Grinding down the pipe is strictly forbidden. Two approved solutions exist: fit an asymmetric fire-stop sleeve designed for a sloping pipe, or install a surface-mounted sleeve on the underside of the slab fixed with metal plugs. In all cases, a thin elastomer strip must decouple the plastic from the concrete over the height of the penetration.

What should be done if a mortar seal has blocked the acoustic decoupling?

Rigid contact between the slab and the drainage pipe ruins the sound insulation of the building. The mortar around the pipe must be cleared using a light chisel hammer or a diamond bit without scoring the plastic wall. Once the space is freed to a thickness of 10 to 15 millimetres, a rock wool sleeve or an acoustic insulating strip is wrapped round, then a fire-stop intumescent sealant conforming to the approval is applied.

Can the fire-stop label be fitted on the service shaft instead of the sleeve?

No. The statutory identification plate must be fixed directly on the sleeve, on the pipe or on the wall of the opening in the immediate vicinity of the sealing. It must remain accessible during technical inspection visits. If the service shaft has an inspection hatch, the information can be duplicated with a summary label fitted on the inspection frame, but the marking at the slab penetration remains the only acceptable evidence.

The fire authority requires the installation records before partitions are closed: how should you proceed?

The team leader draws up a sealing register before the shafts are closed. Each penetration receives an identification number entered on the location plan and on the fire-stop label. The sanitary installer takes a clear photograph showing the fixed sleeve, the fire-stop packing, the acoustic decoupling and the completed label. This signed self-inspection file is sent to the site management to obtain the shaft closure release.

Texts and standards cited

  • Norme SIA 181Noise protection in buildings: minimum and enhanced requirements for structure-borne acoustic transmission from technical installations
  • Directives de protection incendie AEAISwiss fire protection requirements for escape routes, fire compartments and sealing of pipe penetrations