Key takeaways
- The minimum height below finished floor level determines the pipe diameter and the required water seal.
- A high-flow tap/mixer set frequently exceeds the discharge capacity of a compact floor drain body.
- The minimum slope of two per cent ensures self-cleansing without creating a dangerous step in the tiling.
- The floor trap must remain removable by hand so that regular maintenance can be carried out without tools.
Recess height and slope: the geometric trade-off before committing
The walk-in shower requires rigorous coordination from the structural work phase onwards. Too often, the architect or the client plans a continuous floor without a step on the basis of a drawing, without having checked the total thickness available between the top surface of the raw concrete slab and the one-metre level mark above the finished floor. For the sanitary installer, this dimension determines not only the choice of trap body, but also the route of the drain pipe to the stack. If the screed and the acoustic insulation measure only 80 millimetres in total, fitting a compliant connection is technically impossible without passing through the slab.
The height calculation must always start at the lowest point: the bottom edge of the connection to the stack or the existing branch. From this point, you must work up to the bottom of the channel or drain by applying a continuous minimum slope of 1.5% to 2% to the DN 50 drain pipe. A slope below 1.5% encourages the deposit of grease, soap and hair, which in a short time reduces the effective flow cross-section. In addition to the length of this pipe, there is the overall size of the drain body itself, whose height generally varies from 60 millimetres for so-called ultra-flat models to over 100 millimetres for conventional drains providing a total water seal of 50 millimetres.
| Configuration chosen | Water seal | Body height only | Total recess required (finished floor) |
|---|---|---|---|
| Standard drain DN 50 | 50 mm | 85 to 105 mm | 110 to 130 mm |
| Low-profile drain DN 50 | 30 to 35 mm | 65 to 75 mm | 90 to 100 mm |
| Recessed wall channel | 50 mm | 90 to 110 mm | 115 to 135 mm |
| Trap passing through the slab | 50 mm | Below slab | Screed thickness only (50 to 60 mm) |
Above the drain body, the falls of the shower tray or of the masonry base must ensure drainage towards the outlet without water being retained. This surface slope must be 1.5% at minimum, the technical ideal being 2% to compensate for the flatness tolerances of large-format tiles. If the shower is 120 centimetres long and the drain is offset at the back against the wall, the high point of the shower area will be 24 millimetres above the drain. This fall is added to the thickness of the tile covering and its adhesive bed to set the required final level. Omitting this level difference inevitably leads to dirty water overflowing into the rest of the bathroom or to a reverse slope.
Actual discharge flow versus rain shower head: sizing the hydraulic trap
The second critical pitfall of curbless showers lies in the mismatch between the installed tap/mixer set and the absorption capacity of the drain. Contemporary showers often include large rain shower heads of 300 to 400 millimetres in diameter, sometimes supplemented by side body-jet nozzles. These fittings frequently deliver flow rates of between 20 and 35 litres per minute (i.e. 0.33 to 0.58 l/s) at a typical supply pressure of 3 bar. By comparison, an extra-flat trap selected to work around a slab that is too thin often discharges only 0.40 litres per second under laboratory test conditions, and considerably less in actual use.
The certified flow rate of a drain is measured at the factory with a water build-up height of 20 millimetres above the grating. In a walk-in shower without a retaining edge, a 20-millimetre depth of water means that the volume immediately spills outside the shower area and floods the dry floor of the bathroom. In a typical situation with an admissible water depth of only 5 to 10 millimetres, the actual flow rate of an extra-flat drain drops to around 0.25 to 0.30 litres per second (15 to 18 l/min). As soon as the user opens the mixer fully, the water supply exceeds the draining capacity, causing the water level to rise rapidly.
To this structural hydraulic deficit is added the fouling factor. A hair strainer or a perforated grating reduces the intake cross-section from the very first uses. To guarantee durable drainage, the sanitary tradesperson must require a device whose basket trap and trap bell can be removed by hand without the use of screwdrivers. A removable dip cup makes it possible to extract the accumulated fibrous mass and to gain direct access to the pipe inspection opening for the possible introduction of a hydro-jetting hose or a mechanical drain snake.
- Measure the supply flow rateCheck the data sheet of the specified rain shower head or measure the actual flow delivered at the draw-off point using a graduated bucket.
- Validate the discharge curveConsult the trap manufacturer's charts to find the flow rate at 5 to 10 mm of water build-up, not at 20 mm.
- Include the clogging factorApply a 30% safety margin to the discharge capacity to allow for the unavoidable presence of the hair strainer.
- Check removabilityCheck on the sample or in the documentation that the siphon bell can be pulled out vertically without force through the finishing frame.
Reduced water seal and drainage slope: the physical limits of extra-flat drain bodies
The architectural enthusiasm for walk-in showers without a step runs directly up against the physics of the gravity drainage system. When the recess thickness between the top of the raw slab and the finished tiling is less than 90 mm, the sanitary installer no longer has the height required to fit a trap body that complies with the standard water seal height. Manufacturers have responded with compact assemblies with a total height of 50 to 65 mm. However, this compactness imposes a major hydraulic concession: the height of the dip tube is drastically compressed, reducing the volume of water retained below the overflow crest.
In an extra-flat configuration, the effective water seal frequently drops to between 25 and 30 mm. This thin water barrier makes the installation vulnerable to pressure fluctuations generated in the building's waste water stack. As soon as an appliance connected downstream creates a slight negative pressure, or a stack vent proves undersized, the water seal is drawn out. Foul air from the pipes then enters the bathroom directly. In addition, a thin water seal dries out within a few days under the effect of underfloor heating that is not separated from the shower area.
The slope of the drain pipe under the screed must also be defended at every step against height constraints. A sanitary connection in sound-insulated pipe with an outside diameter of 56 mm requires at the very least a continuous fall of 1.5% up to the stack or the branch fitting. Trying to reduce this value to 0.5% in order to fit a floor channel into a 70 mm recess condemns the pipe to inadequate self-cleansing, promoting the immediate settling of body grease and soap residue.
Operation, trap cleaning and durability of actual flow rates
A channel or floor drain retains its nominal laboratory flow rate only when new. From commissioning onwards, the build-up of hair, skin flakes and shampoo clogs the internal narrowing sections. In a traditional large-volume trap, this deposit accumulates at the bottom of the bowl without immediately affecting the water passage section. In an extra-flat drain body, the slightest fibrous obstruction slows the laminar flow, causing water to overflow the tiled edge in less than two minutes of continuous showering.
| Drain type | Minimum recess below tiling | Actual water seal | Flow rate clean / fouled | Cleaning frequency required |
|---|---|---|---|---|
| Extra-flat point drain | 65 to 75 mm | 25 to 30 mm | 0.50 l/s / 0.25 l/s | Weekly (removable comb) |
| Ultra-thin wall channel | 70 to 80 mm | 30 mm | 0.60 l/s / 0.30 l/s | Fortnightly (clip-in cup) |
| Vertical suspended trap (below slab) | 0 mm (in screed) / 150 mm (below slab) | 50 mm | 0.90 l/s / 0.70 l/s | Every six months (bottom basket) |
| Standard recessed body with horizontal outlet | 90 to 110 mm | 50 mm | 0.80 l/s / 0.55 l/s | Quarterly (removable dip tube) |
To ensure maintenance without degrading the water seal zone, access to the hydraulic trap must be entirely from above, by hand, without requiring any specific tools from the end user. Removable-cup mechanisms fitted with a removable hair strainer are the only viable solution on the construction site. The connected pipes must also allow a descaling nozzle or a low-pressure drain snake head to pass through the removed immersion ring.
- Surveying the level markCheck the transfer of the architect's datum onto the raw wall to determine with certainty the finished edge of the tiling before fitting the drain body.
- Wedging and fixing the drain bodyFix the trap to the concrete base with a mortar bed or a set of adjustable feet that are acoustically decoupled, to prevent any deformation under load.
- Connecting the sound-insulated pipeFit the pipes together, ensuring a regular slope of at least 1.5%, with no 90° bend laid flat, preferring two 45° bends to limit pressure losses.
- Flow test and watertightness check at full flowInject a flow equivalent to that of the planned tap/mixer set for three minutes in order to validate the drainage speed before pouring the screed to falls.
Level conflict and insufficient flow: arbitration protocols on the construction site
When the level mark reveals a raw recess smaller than anticipated in the recess plan, the sanitary installer faces an immediate physical contradiction. If the height available below the finished tiling is cut to less than 80 mm, fitting the required water seal, the connection with the appropriate drain diameter and the minimum slope of 1.5% becomes impossible without going above the finished level of the surrounding floor. Continuing the installation under these conditions exposes the construction site to chronic overflows from the moment of commissioning.
- Report the level obstacle immediatelyThe installer draws up a documented notice of defect in accordance with standard SIA 118 as soon as the raw dimensions have been checked, quantifying the slope deficit and the hydraulic incompatibility between the actual discharge flow and the planned appliances.
- Validate routing through the underside of the slabWith the prior agreement of the civil engineer and the fire protection specialist, passing directly through the concrete slab makes it possible to fit a standard suspended trap below the lower ceiling, guaranteeing slope and flow.
- Restrict the supply or requalify the thresholdIf core drilling is not possible, two formal technical concessions are required: fit a flow regulator on the shower column, or accept a masonry step of a few centimetres forming a semi-recessed tray.
At the acceptance stage of the drainage, the check is not limited to a dry run. The installer carries out a full-load test for three consecutive minutes with the final tap/mixer set. He checks that there is no backflow, that the water seal is stable after the flow stops, and that the settling cup can be removed without any specific tool, thus ensuring that the operator can maintain the installation over the long term.
Frequently asked questions
How should you react if the planned rain shower head delivers more than the installed linear channel can handle?
You must act before the finishes are laid. If the recessed channel is limited to 0.5 litres per second according to its data sheet and the tap/mixer set delivers 35 litres per minute, flooding is certain. The sanitary installer must require the fitting of a flow-reducing ring calibrated on the thermostatic cartridge, or the replacement of the drain body with a double-outlet model connected to a vented pipe.
What minimum slope can be tolerated if the screed is thinner than planned?
The minimum functional slope for a tiled shower tray or a screed to falls is 1.5%, with a recommended target value of 2% to compensate for tile-laying tolerances. Going below 1% inevitably creates areas of standing water, promotes the build-up of soapy sludge and considerably increases the risk of slipping or of overflow beyond the shower footprint.
Can the concrete slab be ground out to recess the drain body?
It is strictly forbidden to attack the concrete slab with a chisel or a grinder without the written authorisation of the civil engineer. Uncontrolled grinding risks cutting through the upper bending reinforcement or reducing the minimum cover of the reinforcing bars, compromising the mechanical strength of the structure and its protection against corrosion, while also voiding the ten-year insurance cover.
How can a walk-in shower trap be cleaned after tiling?
Mechanical access must be preserved without requiring destructive dismantling. The drain system must include a removable cup or a removable trap accessible directly below the finishing grating or the channel profile. The downstream drain pipe must be able to receive a small-diameter manual drain snake directly from the drain recess, without having to remove the peripheral waterproofing collar.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work and handling of notices of defect