Key takeaways
- Ceramics and taps and mixers are installed only after the tilers and painters have left for good.
- Peelable films and thermoformed shells prevent cement splashes and tool scratches.
- Limescale-laden purge water without regular flushing forms stubborn deposits on thermostatic cartridges.
- A joint condition record signed as soon as installation is complete prevents any improper transfer of liability later on.
Lock in the work schedule and put up physical protective barriers
On a building construction site in French-speaking Switzerland, installing sanitary fixtures too early directly exposes ceramics, chrome taps and mixers, and synthetic bowls to mechanical damage from the finishing trades. An acrylic shower tray or a glazed stoneware basin must never be used as a rinsing bucket for grouting tools or as a support for a painter's stepladder. The plumbing installer works only once the screeds are dry, the tiles grouted, the ceilings painted and the interior doors fitted with their cylinders in working order.
- Refusing to bring forward the final installationIn coordination with site management, the installer keeps the standby pipework capped under test pressure until the paint and tiling waste has been removed. Fixtures are delivered to the slab room by room the day before installation to avoid intermediate storage in a shared room.
- Fitting the resilient strip and mechanical fixingWall-hung toilet bowls and basin tops are installed on clean tiled surfaces, with a foam acoustic insulation gasket in between. Tightening is done with a torque wrench at the prescribed torques, never forcing against the enamel.
- Immediate application of the protection systemAs soon as the hydraulic connection and the test drain-down are finished, the surface receives full protection. The toilet bowl is mechanically locked with a strap or tamper-evident tape to prevent any use by finishing-work operatives.
| Fixture | Main risk on the construction site | Protection required | Precautions during installation |
|---|---|---|---|
| Synthetic or enamelled cast-iron shower tray | Falling tools, grains of sand under soles, splashes | Rigid hardboard panel or high-density needle-punched felt 200 g/m² under waterproof film | Cut to fit around the perimeter; adhesive tape that leaves no glue transfer on the adjacent tiling |
| Ceramic or resin washbasin top | Paint tins being put down, stepladder rubbing | Original thermoformed double-flute cardboard shell or bubble wrap lined with kraft paper | Keep the waste outlet closed and covered to prevent laitance from entering |
| Basin mixer and chrome shower set | Scratches from rubbing, hydrochloric acid cleaning | Fabric cover closed with a drawstring or expanded polyethylene foam sleeve | Avoid any adhesive tape directly on galvanised or powder-coated finishes |
| Wall-hung toilet bowl | Unauthorised use, standing limescale, glue splashes | Rigid temporary lid clipped onto the porcelain, supply closed | Disable the flush by temporarily removing the flush plate |
Drawing up the joint inspection record and apportioning responsibility for damage
Looking after a sanitary installation is part of the usual contractual obligations until formal handover. If the installer leaves a floor without documenting the as-new condition of the porcelain and the taps and mixers, any surface scratch or chip on a basin corner will be attributed to him, on the grounds of a manufacturing defect or an impact during installation. Art. 370 CO provides that once the client has expressly or tacitly accepted the work, the contractor is released from liability for obvious defects that could have been found by a normal inspection.
- The interim installation record: a document signed with site management certifying correct installation, clean surfaces and the protection put in place in each bathroom.
- The high-resolution photographic record: systematic time-stamped photographs showing the edges of the shower trays, the taps and mixers spouts and the bottom of the enamelled fixtures.
- Locking off the rooms: completed sanitary rooms are locked, and access is then managed under the sole responsibility of site management.
- The incident report: written notification as soon as a torn cover, a footprint or unlawful use of the drainage system by third parties is discovered.
According to art. 97 CO, the debtor of an obligation must make good the damage caused by non-performance, unless he proves that no fault is attributable to him. In managing a construction site under the SIA 118 standard, the plumbing installer must show that the damage occurred after his work was completed and as a result of intervention by a third party. Without this joint inspection record of partial completion, site management will refuse to call on the collective construction-site insurance, forcing the plumbing company to bear the full replacement of the fixture at its own expense.
Mineral and chemical attacks: cement films, limescale and fumes
Once the sanitary fixture is installed at the very end of the finishing work, the risks are not only mechanical. The finishing work of the other trades exposes bathtubs, shower trays and basins to particularly aggressive mineral soiling. Mixing water loaded with cement or plaster residues is often carelessly poured into unsealed traps, creating compact plugs in the heart of the soundproofed drain pipes. In addition, standing limescale-laden construction-site water in the bottom of bowls evaporates under the effect of temporary drying heating, leaving indelible carbonate deposits on vitrified enamels and synthetic resins.
| Aggressive agent | Exposed items | Damage observed | Preventive measure |
|---|---|---|---|
| Tile laitance | Resin trays, waste outlets | Porous encrustation, dulling | Thick peelable film and watertight plug on the waste outlet body. |
| Plaster dust | Flush mechanisms, valves | Mechanical seizing and continuous leak | Keep the access covers in place until final installation. |
| Pickling acid fumes | Mixers, chrome surfaces | Corrosion and pitting of the brass | Airtight covering and ban on hydrochloric acids. |
| Standing limescale-laden water | Toilet bowls, bowl bottoms | Encrusted ring mark | Systematic emptying after filling with water or fitting of plugs. |
The choice of protective films and adhesives directly determines the surface condition of the fixtures at handover. Standard packing tapes must not be used: under the effect of sunlight or the heat of dehumidifiers, their solvents migrate into the body of the resins and leave indelible sticky deposits. The plumbing installer prefers self-adhesive polyethylene films with a non-transfer acrylic adhesive, formulated for clean, solvent-free removal after several months in place. For acrylic or enamelled steel bathtubs, adding made-to-measure thermoformed shells or rigid cellular cardboard sheets remains essential to absorb tools dropped by the trades working later.
Transfer of custody, inspection protocol and attribution of damage
Preserving the fixtures until handover depends as much on contractual rigour as on the strength of the physical protection. As long as the work has not been formally accepted, the risk of damage rests by default on the plumbing installer, unless he can prove the direct fault of a third party. When scheduling constraints force ceramics and taps and mixers to be installed before painting or joinery work is fully complete, the installer must systematically arrange a partial joint inspection record. This condition survey formalises that the fixtures were delivered without visible defects and legally transfers effective custody of the room to site management.
- Joint inspection at installationUnpack the fixture in the presence of site management. Examine the surface under raking light so as to record, from the moment of opening, any enamel chip or manufacturing defect existing before installation.
- Fitting protective covers and sealsApply the peelable films, rigid shells and locking tapes to the toilet bowls to prevent their use as construction-site toilets. Take time-stamped overall photographs.
- Drawing up the custody recordDraw up a condition-survey slip confirming that the items are in perfect condition and that the valves are closed. Have the document signed by site management to validate the transfer of responsibility.
- Removing the protections at acceptance of the workRemove the covers at the official acceptance meeting in accordance with the SIA 118 standard. Any scratch under intact protection is the installer's responsibility; any protection torn off by a third party relieves the plumber.
Where damage is found on a sanitary fixture after the protections have been torn off or broken by third parties, the financial settlement is based on the SIA 118 standard and the general principles of the contract for work defined by the Code of Obligations (CO). If the plumbing installer has documented the initial condition of the work by photographs and warned site management in writing of unauthorised third-party interventions, the repair costs cannot be claimed from him. The replacement cost is then charged to the construction site's joint account under the share of damage caused by unknown persons, or re-invoiced to the client if the client failed to secure access.
Handling damage and recourse: what to do in a dispute
A scratch on an acrylic bathtub, an enamel chip on a shower tray or an encrusted laitance deposit on a wall-hung toilet bowl is most often discovered during commissioning cleaning. If site management disputes the matter, the plumbing installer must apply a strict method to avoid bearing financially the damage caused by a third party.
- Freeze the situation on the construction site immediatelyAs soon as damage is found, stop all work on the fixture. Do not attempt any makeshift polishing that would hide the mechanical or chemical origin of the damage. Take a complete set of photographs: a wide shot showing the condition of the surrounding protections, a close-up under raking light and a picture of the batch or serial number of the sanitary fixture.
- Put the damage notice in writingSend a reasoned notice to site management the same day, relying on the SIA 118 standard. State the time of discovery, the exact condition of the films and protective shells at the time of the finding, and the list of companies that have worked in the room since the last joint record.
- Call an urgent joint meetingRequire site management, the tiler, the painter or the end-of-construction-site cleaner to meet on site. Compare the damage found with the condition sheet drawn up when you installed the fixture. The obvious breach of a sealed protective barrier shows unlawful intervention by a third party.
- Cost the replacement or specialist repairPrepare without delay a detailed quote covering removal, new supply, refitting and the associated waterproofing connections. Refuse any charge against your account until site management has ruled on whether the construction-site insurance or the trade at fault will bear the cost.
Frequently asked questions
Who bears the replacement cost if the person who caused the scratch is not identified?
If the installer documented the installation by a signed joint inspection record and the seals on his protections have been broken, the damage falls under custody of the work entrusted to site management. The loss is then reported to the construction all-risks insurance (CAR) taken out by the client, or apportioned under the coordination rules of the SIA 118 standard, without unilateral charging to the plumbing invoice.
How should one react if site management requires the sanitary fixtures to be installed before painting is finished?
The installer must give written notice recalling the major risks of abrasion and solvent splashes. If he receives a formal order to proceed contrary to the usual sequence, he has a protocol signed stating that custody and upkeep of the surface protections are fully transferred to site management once his connections are complete, thereby releasing his liability for the later finishing stages.
Can the permanent toilet bowls be used during construction-site cleaning?
This is strongly advised against. Washing water loaded with phosphoric acid, laitance or plaster residues scratches the enamels and irreparably damages the flush mechanisms. Site management must keep temporary facilities in place or hire self-contained cabins. If access to the permanent sanitary fixtures proves unavoidable, the cleaning company must certify their initial condition and bear the full cost of any damage found at acceptance.
What type of protection should be placed on a recessed shower tray flush with the tiling?
The protection system must combine a flexible cushioning layer, such as thick felt or polyethylene foam, topped with a rigid cellular polypropylene panel or a wooden panel cut to the inside dimensions of the tray. The edges are sealed with a low-tack adhesive that leaves no residue, thus preventing cement dust from getting through while withstanding repeated foot traffic from operatives.
Texts and standards cited
- norme SIA 118General conditions for the execution of construction work, duty to give notice, custody of the work and acceptance