🧱 CFC 250Tests, claims and the installer's safetyChapter 8 of 10 in the section

Going down into a trench: shoring, access, existing pipes

This chapter gives the sanitary installer the criteria for assessing an excavation before work begins. You will be able to identify the sloping or shoring profiles required by Swiss regulations, check access and secure the surroundings of existing networks before laying a single water pipe or buried collector.

Key takeaways

  • An unsupported trench presents a risk of fatal burial from a depth of one metre fifty.
  • Shoring or suitable sloping remains mandatory before anyone goes down to lay pipes.
  • The access ladder must extend one metre above the edge and be firmly wedged at the bottom.
  • Joint marking-out of underground pipes prevents the tearing out of pressurised or live networks.

Shoring and sloping: the requirements before going down into an excavation

The sanitary installer regularly works outdoors to make drinking-water connections or foul and surface-water outlets to public collectors. Even though excavation and shoring are the responsibility of the earthworks or civil engineering contractor, the sanitary installer remains responsible for their own safety when laying pipes at the bottom of the opening. A trench open with vertical walls is permanently unstable: earth pressure, vibrations from machines or a simple change in moisture cause failures without any warning sign. One cubic metre of earth weighs between 1.5 and 2 tonnes; a localised wall failure is enough to crush the rib cage of a fitter kneeling in the trench.

The Ordinance on Construction Work sets precise thresholds to prevent collapses. According to art. 68 OTConst, excavations, shafts and earthworks more than 1.50 m deep that are not propped or shored must be sloped or secured by other adequate measures. For the plumber who has to fit a sleeve or an electrofusion fitting at the bottom of a 1.80 m trench, going down is completely prohibited until shoring by metal boxes or sheet piles, or compliant sloping, is in place, whatever the planned duration of the work.

Wall protection measures according to the excavation configuration
Excavation depthType of groundMinimum measure requiredPlumber's visual check
Less than 1.20 mLoose or compact groundVertical walls permitted without shoringNo tension cracks at the crest
From 1.20 m to 1.50 mFriable or backfilled groundLight propping or preventive slopingStability of slope toes and edges
More than 1.50 mAny soil type except sound rockContinuous shoring or inclined slopeBoxes lowered to the bottom of the excavation
More than 2.00 mStandard soil or presence of waterMetal shoring with sized strutsUpper guardrail in place

Sloping consists of cutting the walls at an angle that depends on the cohesion of the soil. In loose ground, the slope must be considerably flattened to prevent the mass from sliding. If the space available at the surface does not allow the slope to be opened at the angle required by the site's geotechnical conditions, prefabricated shoring becomes the only alternative. These boxes must always project above the natural ground surface to prevent stones or tools from falling or rolling from the surface to the bottom where work is under way.

Safe access, clear edges and marking-out of buried networks

Organising the workstation in a trench requires strict arrangements around the excavated volume. The area immediately along the edge of the excavation is subject to severe mechanical stresses under the weight of excavated material or construction site machinery.

According to art. 71 OTConst, the edges of excavations and earthworks must be kept clear horizontally for at least 50 cm in width where the excavation is propped, and for at least 1 m in width where the wall is sloped. This safety berm prevents spoil or heavy tools from accidentally falling onto the plumbers working below. No coating load, cast-iron pipework or pallet of fittings may be stored on this walkway strip.

  1. Checking access and the emergency exitInstall a stable emergency ladder, firmly secured at the top and resting on a stable bottom. The ladder must project at least 1 m above the upper ground level to allow safe stepping off without losing balance.
  2. Consulting the network plans and setting outExamine the underground network plan supplied by the site management or the municipal services before entering the excavation, in order to identify gas pipes, medium- or low-voltage electric cables and optical fibres.
  3. Manual probing near pipesProhibit any violent pickaxe blow or mechanical bucket within 50 cm of a suspected pipe. Expose the crown of existing pipes with a hand shovel or by controlled suction.
  4. Supporting exposed networksSling and suspend from upper beams any pipe crossing the trench to prevent it from breaking by bending under its own weight or from settlement of the bedding.

The presence of seepage water at the bottom of the excavation worsens soil decompression and damages the bedding of the future sanitary pipe. If water enters, installing a dewatering pump in a remote sump ensures a dry excavation bottom and limits the risk of scouring beneath the shoring. The sanitary installer also checks the atmosphere in the excavation when the trench adjoins old sewer pipes or areas polluted by hydrocarbons.

Shoring, sloping and access: the stop protocol when faced with a 1.80 m trench

On a building construction site, the earthworks operator frequently opens a 1.80-metre trench to allow connection of the drainage collector or the laying of the polyethylene drinking-water service pipe. The fatal mistake is for the sanitary fitter to go down "for a few minutes" without collective protection to take an invert measurement, position a connection saddle or locate an electrofusion sleeve. A vertical wall of earth never gives warning: decompression of the soil causes a sudden shear failure. With a density close to two tonnes per cubic metre, a mere slab of earth crushing the chest of a crouching worker blocks the rib cage and causes fatal asphyxia well before rescuers arrive.

The Ordinance on Construction Work imposes strict rules for excavations. Beyond 1.50 metres depth in loose or compact ground, the excavation must include appropriate shoring or sloped walls according to the mechanical strength of the soil. The sanitary installer must refuse access until this arrangement is operational. The upper edge must remain free of any load: a horizontal zone 50 centimetres wide is required for a propped trench, and at least one metre for a sloped excavation, prohibiting the storage of pipes or coils at the edge. Access to the bottom requires a ladder fixed to prevent any tipping, whose uprights project at least one metre above the usable upper edge.

Measures required before the sanitary installer goes down into a trench
Ground configurationDepthOTConst requirementAction required of the fitter
Compact vertical excavationLess than 1.50 mBare walls tolerated if soil is stableCheck there are no cracks and set materials back 50 cm.
Narrow sewer trenchFrom 1.50 m (e.g. 1.80 m)Shoring by boxes or strutsRefuse access until the shoring has been installed by the earthworks contractor.
Open-cut excavationAny depthSloping with a gradient suited to the soilRequire one metre clear at the edge and a ladder projecting one metre.
Disturbed or unstable groundFrom 1.00 mContinuous shoring with no toleranceRecord the non-compliance and suspend the sanitary work.

Existing networks and simultaneous activities: manual exposure, suspension and management of water ingress

Sanitary connection work is often carried out in a subsoil crowded with services in operation: electricity, pressurised gas, telecommunications or municipal drinking-water pipes. Before any probing with a pointed tool or adjustment digging, the fitter must consult the marking-out plans supplied by the site management and compare the theoretical routes with the actual points where services emerge on site. Buried warning tapes provide an essential first visual marker: blue for drinking water, yellow for gas and red for electric cables.

  1. Checking plans and marking outIdentify the location of the warning tapes and mark out the approach zone for the gas and electricity networks crossing the excavation.
  2. Precise manual probingProhibit the use of mechanical tools in the immediate vicinity of located pipes. Remove the backfill with a hand shovel to locate the pipes without impact.
  3. Suspending crossing pipesSecure exposed existing pipes to a joist at the surface using textile straps to remove any risk of bending or breaking under their own weight.
  4. Pumping and stabilising the bottomCreate a dewatering sump outside the work zone to drain seepage water without washing out the bedding of the future sanitary pipe.

The presence of water at the bottom of the excavation quickly weakens the foundation of the shoring and encourages slope slippage. As soon as water ingress liquefies the bottom or causes gullying under the struts, connection work must be stopped. The sanitary installer resumes laying drinking-water or drainage pipes only after groundwater lowering or complete drying by the civil engineering contractor.

Emergency procedure: what to do in the event of excavation incidents

On a connection construction site, the appearance of a geotechnical problem or the striking of an underground network requires a methodical response. As soon as a sign of instability appears on the walls — a longitudinal crack at the crest of the slope, a clod of earth coming away, a prop buckling or a visible deformation of a shoring panel — the sanitary team leader orders the personnel to be evacuated by the site ladder. The fundamental rule remains never to try to retrieve tools or a connection sleeve left at the bottom of the excavation: the density of loose earth is close to two tonnes per cubic metre, turning any collapse into a deadly trap.

  1. Evacuation and securing the perimeterAll workers leave the trench. The sanitary foreman cordons off the crest of the excavation to prevent anyone approaching and has earthmoving machines parked at a minimum distance equal to the depth of the excavation.
  2. Alerting the site management and the earthworks contractorThe installer contacts the site manager and the earthworks contractor responsible for the excavation and for installing the shoring under the OTConst. No sanitary work resumes without a formal requalification of the excavation.
  3. Handling a damaged or unexpected networkIn the event of a leak on a pressurised water pipe or the discovery of an unmapped cable, personnel shut the upstream valves if they are accessible from the surface and notify the local utility suppliers.

After an incident or a sudden ingress of water at the bottom of the excavation, restoration requires the exclusive involvement of the civil engineering contractor. Pumping out the water, clearing the settled sludge and replacing any damaged shoring must be completed before the sanitary fitter goes down again. A joint visual inspection by the sanitary foreman and the person in charge of the earthworks validates the stability of the slopes, the clearance of at least fifty centimetres at the edges and the secure anchoring of the access ladder projecting above the crest.

Frequently asked questions

What should be done if the trench is 1.60 m deep and the work lasts less than ten minutes?

The duration of the work never exempts anyone from the safety rules. As soon as the depth exceeds one metre fifty, the OTConst requires shoring or compliant sloping of the wall. Most burial accidents occur within a fraction of a second, during work described as quick. The sanitary installer must refuse to go down into the excavation until the earthworks contractor has installed the shoring boxes or secured the edges.

How far from the edge of the excavation must excavated spoil and pipes be placed?

The OTConst requires a clear strip at least fifty centimetres wide to be kept along a shored excavation, and at least one metre if the wall is sloped. This clear zone prevents stones or equipment from falling onto the sanitary fitters working at the bottom. It also avoids placing a surcharge on the crest of the slope, a direct cause of ground failure. Tools and pipe coils must be kept back from the edge.

How should you react if an unrecorded water pipe is discovered during excavation?

The sanitary fitter stops work and prohibits any use of a mechanical excavator in the area concerned. The section must be exposed carefully by hand, with shovels without sharp edges. The team leader informs the site management and the municipal water service in order to identify the nature of the fluid and the service pressure. If the pipe is hanging unsupported, it must be suspended before any further sanitary assembly.

What are the requirements for the access ladder in a connection trench?

The ladder is the only means of rapid evacuation in the event of a collapse or sudden water ingress. It must rest on a stable bottom, be firmly secured at the top and project at least one metre above the upper level of the edge to ensure a secure grip when climbing out. Home-made ladders or stepladders are prohibited. Where the trench is more than about twenty metres long, the installer requires at least two separate access points.

Texts and standards cited

  • OTConstSafety and health protection requirements for excavations, earthworks, sloping and safe access on construction sites